Sword Street Force Main Rehabilitation
At a glance
- What: phase one lines about 2,700 feet of the Sword Street force main (five access pits) through the historic area of most breaks.
- Status (Aug 20): six bids; low bid just over $2.4 million against an engineer's estimate near $3.3 million; engineer reviewing. Work may start with valves this fall and the main work in spring.
- Open: the town meeting funding covers Sword Street and Goddard Drive; staff may prioritize Goddard Drive over phase two.
(From auto-captions; names and numbers may be misheard.)
Log
- 2026-08-20 - Sewer Commissioners - Bids reviewed; low bidder about $900,000 under estimate; construction timing and bypass plan discussed (from auto-captions)