UEP Project Delivery Method

At a glance

Based on auto-generated captions; names and numbers may be misheard.

  • What: how the city delivers its remaining utilities extension program (UEP) areas.
  • Where it stands: negotiations for a program manager at risk failed; on October 14, 2026 council raised no objection to staff's backup plan.
  • Next: staff will engage one engineering firm for the next area and possibly future areas.

Background

  • In July 2026 council authorized a program manager at risk to design, bid and manage the program quickly, in light of the water management district pressure over septic systems.
  • Two proposals were received and ranked under state procurement law (section 287.055); negotiations ran from May to August. The top-ranked firm kept contract provisions the city saw as shifting risk to it, and the second-ranked firm was not pursued over past-experience concerns.

Path forward

  • Continue the traditional design-bid-build approach with a construction engineering and inspection firm.
  • One enhancement: hire one design firm for the next area and possibly all future areas instead of issuing a new engineering solicitation each time, for continuity.

Sources

Discussion time

About 6 minutes across 1 meeting (from transcript timestamps; approximate).