School HVAC Replacement

At a glance

Uploaded (human-made) English captions; minor errors are possible, and no speakers are labeled.

  • What: replacing the middle school chiller and an elementary air handler (about $1.8 million), amid other equipment failures.
  • Where it stands: waiting on City Council approval, expected October 21 or at the end of the month; the chiller takes about 30 weeks to build.
  • Next: bids after approval; installation anticipated next summer.

Details

  • A project manager said much of the equipment still works for now but new problems keep arising.
  • At the high school a fire alarm panel failed and a fire watch is in place; elevators also failed. Staff attributed repeated damage to lightning strikes. A temporary chiller is in place.
  • A board member asked about bollards for the car pickup line (no answer given) and the city said it would follow up by email on an earlier question.

Sources

Discussion time

About 4 minutes across 1 meeting (from transcript timestamps; approximate).