2026-09-14 - Transportation and Infrastructure Committee
Summary
Built from the video's auto-generated captions; names and figures may be misheard.
- Rev Birmingham agreement: the Department of Transportation asked the committee to recommend an agreement with Rev Birmingham, at $125,000 through 2027, to help manage an RFQ process, meeting schedules and public engagement for a structural assessment of the closed Richard Arrington Jr. Boulevard bridge and the similarly aged 22nd Street Bridge. The department will still oversee the study and select the engineer. Staff cited a roughly $400,000 total estimate including the engineering study. The scope attachment showed an older $100,000 figure and 2028 end date, which staff said was outdated. Recommended to the full council on a voice vote.
- Bridge background: staff said a 60% design for rebuilding the Arrington bridge was put on hold because a rebuild looked unaffordable, and the city now wants to weigh all options, including preserving the bridge.
- Roosevelt City pedestrian bridge: an intergovernmental agreement with Jefferson County lets the city enter county property to repair the 1990s wooden bridge, part of which lies in unincorporated county land. Repairs are funded and expected to use wood again. Recommended on a voice vote.
- Mountain Brook roundabout art: a right-of-way maintenance agreement lets Mountain Brook install a sculpture in the larger Kahaba Road roundabout near the zoo entrance and maintain it. The design is still a concept and must pass city safety review. Recommended on a voice vote.
- Transportation Improvement Program applications: two resolutions authorize applications to the regional planning organization, due October 8 per staff, for the first open call in eight-plus years (2027-2031 program), at an 80/20 federal-local split. One is about $5 million for Red Rock Trail Corridor C (Robert Jemison Road road diet, repaving and shared-use path). The other is about $4.5 million to replace the West Boulevard and First Court North bridges and culverts and extend the Village Creek Trail. Staff noted that applying does not guarantee inclusion. Both recommended on voice votes.
- Traffic calming: council members said many neighborhood requests were denied with a one-word response and no explanation. They asked the department for an update on pending requests, clearer eligibility criteria and direct community outreach. A follow-up with the department is planned.
Agenda
Agenda listed in the Agenda Center; see Sources.
Sources
- Video: https://www.youtube.com/watch?v=2JPqhVf65Ak (Birmingham City Council YouTube channel)
- Council meeting video and agenda archive: https://www.birminghamal.gov/government/city-council/council/city-council-meeting-video-portal-archives
- Minutes: none posted
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:00Good afternoon to the committee. My name
00:02is Colin Alexander and I serve as the
00:04program manager in the Birmingham
00:05Department of Transportation. Um, as I
00:08think many of you are aware, for the
00:10last several years, we have had the
00:12Richard Arrington Jr. Boulevard bridge
00:14closed between 1 Avenue North and 1st
00:16Avenue South due to deterioration
00:18concerns. Um, and we have are now in a
00:22position where we are going to go after
00:24and do a an RFQ process to get an
00:27engineering firm under contract to
00:30evaluate the structural integrity of
00:32both Richard Arrington and the 22nd
00:34Street Bridge, which is of a similar
00:35age, and to make some recommendations as
00:38going forward. Before we can do that,
00:40however, we need we are asking to enter
00:43into an agreement with Rev. Birmingham
00:45to help us capacitywise to manage this
00:49um this study. So they would help us set
00:52up the RFQ RFQ process, help us to kind
00:55of manage the the meeting schedules and
00:58cadences of the project and then also
01:01would help provide public engagement
01:03services um as we embark on this um
01:08structural assessment study. Uh it's
01:10obviously a high-profile area, so we
01:12believe that there's going to need to be
01:13some public engagement in that process.
01:15Rev has a lot of contacts and and and
01:17connections in the area and so we think
01:19it's a good partnership. So this is the
01:21first phase and then after we get this
01:25under contract, we will start putting
01:26out a request for qualifications for a
01:29uh structural study.
01:32>> Okay.
01:34So Rev is not going to be managing that
01:36part of it. They will be helping us with
01:38the day-to-day activities. So, just kind
01:40of like getting like organizing meetings
01:42and things like that. The B dot will
01:44still be the entity overseeing the
01:46study. They're just giving us some
01:48capacity help.
01:49>> Okay. Yeah, I'm looking at the um
01:54exhibit A, attachment A, the looks like
01:57the, you know, scope of work here.
02:00Um,
02:04so there there'll be
02:07helping with the RFP process for that
02:11structural assessment,
02:12>> right? Helping us develop that, helping
02:14us once we'll still be the ones doing
02:16the selection process. We'll still be
02:18the ones who are the who the consultant
02:21will have the contract with, but then
02:22Rev is just going to help us with sort
02:23of the back of house management and also
02:25organizing public engagement.
02:28>> Okay.
02:31What's the
02:33term of
02:34>> um so it goes through December of 2027
02:38which is why it's coming to you guys.
02:39Normally professional services don't but
02:41it's going over two fiscal years which
02:43is why it has to go to council.
02:44>> Okay. Gotcha. All right.
02:49>> Question.
02:49>> I do have a question. So looking at the
02:51scope of services, the total budget is
02:54125,000. But then looking at the table,
02:59it goes through December 2028 and it's
03:02100,000
03:04for the rev contract.
03:06>> The rev contract should be 125. I I
03:09think that may have been an old
03:10attachment that was there. So 125 is
03:12what we're looking at. It's inclusive of
03:13the public engagement strategy to help
03:15us manage that.
03:16>> Okay. And through 2027.
03:18>> Through 2027. And so we we plan to do
03:20this whole structural assessment within
03:21a year.
03:56Okay. And it looks like we're
04:00projecting that the actual structural
04:03engineering
04:05uh component
04:07of the project is Our
04:12goal is to is to have it set up by the
04:13end of the year or early Q1 of
04:15>> 2017. That'll be additional cost.
04:17>> That's the next step, right? So, we have
04:19to get this all set up to the to for us
04:21to start the process.
04:23>> Gotcha. All right.
04:26>> So, the 400,000 is
04:28>> that's our estimate for how much we
04:29think this the total with the
04:32engineering study is going to cost.
04:33That's our full budget. And then the 125
04:35is what out of that for the rev
04:37contract. Gotcha. Okay.
04:42>> [snorts]
04:47>> So, um, you know, I know there's been
04:50previous work done on this. Um I can't
04:53[clears throat] remember the name of the
04:54firm but there was a 60% design plan
04:57that was developed.
05:00>> So yeah we Neil Schaefer there and I I
05:03don't exactly know all the details that
05:04was it predates me a little bit but um
05:07they we had them doing some design work
05:08and it became
05:11[sighs]
05:11clear that the a rebuild of the bridge
05:14was just probably not going to be
05:16fiscally sp possible for the city to
05:19take on. So, we put a hold on that and
05:21we're re-evaluating to see what our
05:23entire range of options is, including
05:25potentially preserving the bridge and
05:27then what it could be used for if we do
05:29preserve it. We never did a a structural
05:31analysis really considering that option
05:34previously. So, we really want to put
05:35all of our options on the table before
05:37moving forward with, you know, a
05:38potentially large ticket item.
05:42>> In the meantime, um I would suppose that
05:46B do regular inspections. That's
05:49correct. We we do uh as required we do
05:52regular inspections of all of our
05:53bridges just you know across the city
05:56but we don't have the in-house team
05:58capacity to do this kind of a structural
06:00analysis.
06:01>> Okay.
06:07Okay.
06:08Um
06:11yeah. So
06:13there's no other questions. So, I'll
06:15make a motion that we uh recommend this
06:18to the full council for approval.
06:20>> Second.
06:22>> All in favor say I.
06:23>> I.
06:24>> I. All right. So, that will pass. Um the
06:28next up we have an intergovernal
06:30intergovernmental agreement with
06:32Jefferson County for
06:35Roosevelt City pedestrian bridge.
06:38>> Yes. So, back in the mid to late 90s,
06:42the city built a pedestrian bridge um
06:46connecting the Roosevelt City Park
06:48across Valley Creek back to the Blockton
06:51Avenue, Sugar Ray Drive part of
06:53Roosevelt City to give those residents
06:55access to the city park. Um over the
06:58last couple years, there has been some
06:59deterioration to a lot of the and
07:01rotting to a lot of the boards of the
07:03bridge and it's been a cicklic fix
07:05request that we've been trying to
07:06address. So, we've identified funding
07:08for a capital project and we're moving
07:10forward and discovered that the br that
07:12part of the bridge lies on parcels
07:14outside of the city of Birmingham and
07:16actually inside unincorporated Jefferson
07:18County. So, in order for us to move
07:20forward, this is just an IGA with with
07:22the county granting us permission to
07:25step onto county right away and and
07:27county property to make the repairs to
07:30the bridge.
07:35I see here in the exhibit
07:40uh looks like
07:42looks like the creek is the dividing
07:44line, right?
07:45>> That's correct. And and so there's a
07:48couple of uh parcels right on the creek
07:51that fall into the county and then
07:52you're back in the city of Birmingham.
07:55>> Okay.
08:01>> Yeah. It's pretty
08:04straightforward. Just establishing
08:06permission to enter into their property.
08:09>> Correct.
08:09>> Yeah. Okay.
08:17>> So, um
08:20there there's already a capital
08:22improvement project.
08:23>> We've got it funded. We we we've got it
08:25roughly scoped, but once we discovered
08:27that we had to go through this, we kind
08:28of put a hold until we could get this
08:30IGA executed. Okay. Gotcha.
08:34All right. Any questions? All right.
08:38>> So, the bridge was built with what type
08:40of product? Wood.
08:41>> Yep.
08:42>> So, what are you guys doing different
08:44this time?
08:44>> Um, we're probably going to go back with
08:46wood, but I'm not exact I'm not 100%
08:49sure that it's still going to be
08:50determined by our engineering team as we
08:52as we scope out the project. But, I
08:55think we're probably going to go back
08:56with what's there because we're not
08:57replacing the bridge. We're just making
08:59spot repairs to bad spots. So, we want
09:01to make sure that's consistent with
09:03what's there.
09:04>> Okay. So,
09:07and I guess I'm asking that because if
09:10the wood is deteriorating, what's the
09:11maintenance plan to make sure that it
09:13doesn't um
09:15you know,
09:16>> well, I mean the curse problems.
09:18>> Yeah. I mean, the bridge is 30 something
09:20years old. It's about time to to make
09:23these kind of repairs. I think this is
09:24pretty standard. I don't think that this
09:26is unforeseen maintenance. It's just a
09:29matter of the logistics of not realizing
09:32that part of the bridge was outside the
09:33city of Birmingham when it got built.
09:37>> Okay.
09:38Thank you.
09:40>> All right.
09:42Um
09:44so I'll make a motion that we recommend
09:46this to the full council for [snorts]
09:48approval.
09:49>> Second. Right.
09:51>> All in favor say I. I. All right.
09:55That one moves on to the council. And
09:57next up, we have a rightaway maintenance
09:59agreement with the city of Mountainbrook
10:01for Kahaba Road roundabout art
10:03installation.
10:04>> Yes. Um last year we completed a long
10:08awaited project in partnership with the
10:10city of Mountain Brook um to build two
10:13roundabouts near the Birmingham Zoo and
10:15Botanical Gardens. Um, now the city of
10:18Mountainbrook would like to commission
10:20an public arts p piece to go in the
10:23middle of the larger of the two
10:24roundabouts and so they are asking
10:27permission to install that sculpture.
10:29Um, that larger roundabout is actually
10:31in the city limits of Birmingham as well
10:34in the in the agreement. Mountain Brook
10:36would agree to maintain the sculpture
10:38going forward as part of that.
10:42Wow.
10:45And so this this rendering that's
10:47included in the packet is that
10:51>> that's that's as far as Mountain Brook
10:53has gotten in the design concept. Um it
10:56still needs some refining, but that's
10:58what they provided us to get to this
11:00point.
11:05>> So this is the the roundabout right in
11:08front of the the zoo entry.
11:09>> Yes.
11:10>> Okay.
11:41And as part of that, to your point about
11:44the rendering, you know, part of the
11:45agreement is obviously that they would
11:46finalize a rendering and it would be
11:48reviewed by our department and by our
11:50capital projects team to make sure it
11:51meets all of our safety specs and things
11:53like that before we approve it. This
11:55just provides the framework for them to
11:57get that done.
11:58>> Okay.
12:00I think it's [snorts]
12:02I'm glad that Mount Brookke is taking on
12:04the maintenance responsibilities because
12:09um my experience is that uh anything you
12:12put in or next to a roadway eventually
12:16gets hit by a car.
12:17>> [laughter]
12:17>> So,
12:20um,
12:22you know, there's Miss Fancy and
12:24Aenddale that's, uh,
12:28had some close calls.
12:37All right, any questions?
12:41>> All right, so I'll make a motion that we
12:43recommend this to the full council for
12:44approval.
12:46>> Second. All right. All in favor say I.
12:49>> I. And next up we have the Birmingham MO
12:53Transportation Improvement Program
12:55application for the Red Rock Trail
12:57Action Plan Corridor C.
12:59>> Yes. So the NPO which is housed here at
13:03the regional planning commission
13:05oversees the management of the
13:07transportation improvement program which
13:08is their program for administering
13:11federal um
13:14sorry excuse me um allocated funding
13:18um block funding if you would to
13:20transportation sectors in in the region
13:22um from the carbon mitigation and
13:25congestion mitigation and air quality
13:27program, the surface transportation
13:29program and in the carbon reduction
13:30program. And so every four years the no
13:34has to create a new tip, right? And they
13:38get new funding and that's the funding
13:39that's available every four years. Over
13:42the last eight plus years, the no has
13:46not been accepting new grant
13:48applications. Um rather they've been
13:50allocating those funds to cover overages
13:52in older projects. We had a lot of
13:55projects in the region from the early
13:572000s that were stuck in various phases.
13:59They were over budget for various
14:01reasons. And so the MO is being
14:03conservative and helping those projects
14:04get to to conclusion. Now for the first
14:07time in eight plus years, the MO is
14:09opening up applications um for the 2027
14:132031 TIP. And so we have two uh
14:16applications we want to present um to
14:19them for this cycle. The applications
14:21are due October 8th, I believe. Um so
14:25the first is back in 2022 [snorts]
14:28um Freshwater Land Trust completed an
14:31action plan what they called the Red
14:33Rock Trail action plan which outlined a
14:35loop around the city. And so we've been
14:38partnering with them looking at
14:39corridors to implement. Corridor C is
14:42the corridor between Vulcan Trail and
14:45Red Mountain Park. And so the proposal
14:48here would be a project that would focus
14:51on Robert Gemson Road from 24th Avenue
14:53South to the city limits. We'd do a road
14:55diet. We would repave. We'd add in a uh
14:58a shared use path. And 24th Avenue. We
15:02uh previously about two years ago put in
15:04bike lanes. So now we were going to put
15:05in sidewalks on both sides of that to
15:07connect down to Green Springs where we
15:08have a sidewalk project that is pending.
15:10And then we would work to connect the
15:12end of Vulcan Trail to get it down to
15:15Green Springs. So that way you would
15:16have a a continuous trail network. So
15:18that's the first project
15:23and that's we're we are asking for a
15:25total of $5 million for that project and
15:28it's an 8020 uh federal local split.
15:32>> Okay. And you want to go ahead and just
15:35talk about the other
15:37>> Sure. So, the other one that we are
15:39proposing um over on the eastern side of
15:41town um near the robot golf course, Don
15:45Hopkins Park, we need to replace the
15:49bridges and culverts at West Boulevard
15:51as well as at First Court North. Both of
15:53those bridges are deteriorating. They
15:55need to be replaced. Um it's a little
15:57more than what we can afford to do just
15:58in house. Um there's some flooding
16:00issues that we hope to um mitigate by
16:03replacing these bridges. We'd also um
16:06extend the end of the village creek
16:09trail that terminuses at First Court and
16:11get it all the way to West Boulevard as
16:13part of that just a couple more blocks.
16:16>> Okay.
16:16>> And that also is about $4.5 million
16:20total ask at an 8020 split.
16:23>> Yeah. So these two resolutions are just
16:28you know the council authorizing the
16:30mayor to
16:31>> to apply for the grants. That's correct.
16:35So, just because we asked doesn't mean
16:37that we get included on the tip.
16:39>> That's correct.
16:40>> Right.
16:42All right.
16:44Any questions about this one? All right.
16:48Uh All right. So, I make a motion that
16:51we approve that we recommend these two
16:54items to the council for approval.
16:57>> Second.
16:58>> All right. All in favor say I.
17:00>> I.
17:03Um, all right. Uh,
17:06any new or old business that we need to
17:09discuss?
17:21>> Yeah. Um, I just guess as a FYI, we uh
17:30some of the neighborhood associations
17:32are starting to be notified about their
17:35requested traffic calming projects and
17:39um so we're I know for for district 5,
17:45we've we had several neighborhoods that
17:48applied for those traffic calming
17:50projects and uh
17:53uh for one reason or another, most of
17:56those requests uh were not granted. So
18:02um the plan is to have follow-up
18:05conversation with BOT about you know the
18:08process. Um because my my biggest
18:12concern is is that you know I think it's
18:16the right approach to engage do
18:19community engagement when we're trying
18:21to identify the locations where those
18:24types of projects need to happen. Um
18:28what I don't want us to
18:33get in the position
18:35of of doing is
18:38um
18:39allowing people to ask but then telling
18:42them no, you know, more often than not.
18:45So um
18:48I think for our own skin um we don't
18:52want to be putting ourselves in a
18:54position where we
18:57um create false expectations
19:01[laughter]
19:02and and then have to uh deal with the
19:06the yeah aftermath of you know telling
19:09people no most of the time. So, um,
19:13anyway, the plan is to to follow up with
19:16BOT on that and, um,
19:20you know, modify the process. You know,
19:22hopefully we can still pres preserve the
19:25community engagement component of it.
19:28Um,
19:29um, but, you know, the folks who are
19:33making these requests need to have, you
19:38know, an understanding on the front end.
19:41of you know what situations
19:46uh are likely to be approved so that you
19:49know
19:51they can make the appropriate request.
19:53Um you know I don't I don't think
19:57anybody is going to spend their time you
20:00know asking for something that they're
20:03more than likely going to be to told no
20:06we can't do that. So, want to position
20:09them so that they're able to have some
20:14reasonable e expectation that if they
20:16make a request um that it it you know
20:19it's possible that it could be uh
20:21granted. So, keep you up.
20:26>> I I hear you know what you're saying.
20:28So, what about the people prior to you
20:32guys um you know coming up with this new
20:36way of um individuals as council Quinn
20:38saying applying for
20:41um traffic coming because we often
20:44experience and we have to carry the
20:46burden of trying to explain to those
20:49individuals in community how traffic
20:52comes. And I think the Birmingham
20:56Department of Transportation should be
20:58um where you all need to be as council
21:02Quinn saying going out explaining the
21:04process to the community rather the
21:07community hammering down on us because
21:09we only translating information you guys
21:12have given us.
21:14>> Yeah. And so, um, we were able to talk
21:18with Director Blevens, uh, yesterday
21:21actually and mentioned to him that,
21:24>> you know, ba, basically the way this
21:26getting getting communicated is that the
21:28community resource representatives are,
21:31you know, just being told what the
21:34outcome of the evaluation was, uh,
21:38whether it's an eligible project or
21:40ineligible,
21:42and that there was no accompanying
21:45information, you know, with that. It was
21:47just really that one-word response. Um,
21:51and I think it's, you know, just natural
21:54for the people who are making the
21:57request to say, well, well, why is it
21:59ineligible? And that type of um, you
22:03know, information didn't come, you know,
22:06with with the response. So, um,
22:12you know, that's part of what we think
22:14is important is it's like, okay,
22:19if it's ineligible for a tracker calling
22:22project, tell me
22:25>> what types of projects are going to be
22:26eligible so, you know, I can frame my
22:30request appropriately.
22:33>> I think I I would like to know those
22:35requests, you know, that have been
22:37pending. um
22:40what's the out you know what what's the
22:42outcome going forward I know we talked
22:45about Card way a lot Clemens Grand
22:48Boulevard um and I did see a a letter
22:54that the Smithfield estates neighborhood
22:56president had written I mean you guys
22:58had sent to them that they you know this
23:01is your half and the city is responsible
23:03for um their half. So I think what I
23:07would like to know is those projects
23:10that are pending, when will work begin
23:14on those projects?
23:16>> I think that's what I would like to
23:18know. And as councelor Quinn stated,
23:20then the broader
23:22um
23:24you know explanation of how people
23:28properly apply for traffic come should
23:30come from you all. So we shouldn't be
23:32out here getting beat up about things
23:35that we only translating information
23:37that we have been given. And so I think
23:40people deserve uh you know a robust
23:43answer than saying hey this is not you
23:45can't get it. So I you know we
23:48definitely like to see um you know a
23:52reason why and how people really need to
23:55be applying you know to receive traffic
23:58come you know in their neighborhoods. So
24:00I guess for me I guess my question going
24:03forward and what I want from B do is an
24:07update on those
24:11individuals that
24:13um has have been waiting for traffic
24:15coming and this new process of those
24:19that have been denied. like how do you
24:21go back and um give the people a clear
24:26precise
24:28way that they need to be applying for
24:30traffic coming. I mean, not giving
24:32somebody a cookie cutter answer saying
24:34this is not going to get you what you're
24:37you're looking for. I think people
24:39deserve to know more than what's being
24:42told to them. So, if you guys can um you
24:46know
24:48have some engagement and tell
24:50individuals this is what we're looking
24:53for when we um approving traffic coming.
24:57I I think people in the neighborhoods
25:00and constituents, they deserve to know.
25:01But I think for me, I want an update on
25:04those traffic coming requests that
25:07people have been waiting for for years
25:10um from you guys. Thank you.
25:13>> Yeah.
25:15Right.
25:16Anything else? All right. Motion to
25:19adjurnn.
```*