At a glance
Based on auto-generated captions; names and details may be misheard.
- What: study, not to exceed $29,600, to redesign the plant water system, which reuses treated effluent instead of drinking water to run equipment.
- Why: the pumps have had operating problems. Follow-on construction was estimated at $100,000 to $150,000; the system saves roughly $200,000 a year in purchased water.
- Outcome: approved October 19, 2026 (firm captioned "Tata & Howard"; the agenda says Tighe & Bond).
Sources
- https://www.sturbridge.gov/AgendaCenter/ViewFile/Agenda/_10192026-450
- Meeting video: 2026-10-19 - Select Board
Discussion time
About 3 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-10-19 - Select Board | 3 |
Log
- 2026-10-19 - Select Board - Study contract approved, not to exceed $29,600.