Wastewater plant primary treatment unit No. 3 painting
At a glance
Based on auto-generated captions; names and details may be misheard.
- What: contract, not to exceed $90,000, to drain, repair and repaint the third and largest primary treatment unit at the wastewater plant.
- Why: required maintenance; corrosion and pitting require welding repairs. The same firm did the first two units. Tertiary clarifiers are next.
- Outcome: approved October 19, 2026 after some debate over cost (firm captioned "Ti and Bond"; the agenda says Tighe & Bond).
Sources
- https://www.sturbridge.gov/AgendaCenter/ViewFile/Agenda/_10192026-450
- Meeting video: 2026-10-19 - Select Board
Discussion time
About 5 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-10-19 - Select Board | 5 |
Log
- 2026-10-19 - Select Board - Contract approved, not to exceed $90,000.