- What: trail and bridge project at 469A Main Street with wetland and critical species concerns.
- Decision October 19, 2026: approved a $218,300 proposal for bidding administration, construction-phase services and post-construction environmental monitoring, and authorized the town administrator to sign.
- Next: bidding and construction.
Sources
- https://www.sturbridge.gov/AgendaCenter/ViewFile/Agenda/_10192026-450
- Meeting video: 2026-10-19 - Select Board
Discussion time
About 2 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-10-19 - Select Board | 2 |
Log
- 2026-10-19 - Select Board - Approved $218,300 proposal for bidding, construction-phase services and environmental monitoring.