  • What: study, not to exceed $29,800 (heard as 298), of the four high-maintenance pumps that move sludge out of the clarifiers.
  • Outcome: approved October 19, 2026, paid from the sewer budget (firm captioned "Tata & Howard" and "Ti and Bond"; the agenda says Tighe & Bond). The item was taken out of order.