- What: Design for replacing the Route 20 sewer pump station (Special Town Meeting Article 39).
- Where it stands: Board reviewed the engineering options memo on October 5, 2026: in-place floodproofed replacement is about $3 million cheaper than relocation with no added land taking; article placed and supported.
Sources
Log
- 2026-10-05 - Select Board - Board reviewed the engineering options memo on October 5, 2026: in-place floodproofed replacement is about $3 million cheaper than relocation with no added land taking; article placed and supported.