Airport Roof Projects

At a glance

  • What: airport roof work: a roof replacement, a partial roof replacement (Roof Systems of Maine) and renovations of the roofs of Docks 11 and 13.
  • Where it stands: the Finance Committee agendas of 2026-09-09, 2026-09-21 and 2026-10-05 carried these items; the Docks 11 and 13 renovations were recommended to the Council. Outcomes are not verified.
  • Next: follow the Council agendas.

Details

  • Dollar figures from the bid tabulations were not read.

Sources

Log

2026-10-05 - Finance Committee

  • Three bids for Docks 11 and 13; low bidder Roof Systems of Maine, which has done other recent airport roofs. The bid equaled the budget because the airport added savings from earlier roofing to an insufficient budget; councilors asked for original and amended budget lines on purchase forms. Recommended to the full Council.

2026-09-21 - Finance Committee

  • Partial roof replacement (Roof Systems of Maine).

2026-09-09 - Finance Committee

  • Roof replacement bid.