Consent order 26-289 authorizing a design-build contract with Gordon Contracting Inc. for replacement of a portion of the Kenduskeag Stream retaining wall passed.
Director of Engineering recommended a design-build award to Gordon Contracting at $3,871,720, within the $4 million downtown TIF budget, after three proposals were scored and interviewed. Covers one section of the failing wall in modular block; Army Corps permits needed and the mall-area walkway will close during work. Recommended to the full Council.