Burlington Electric New Generation Project Permitting
At a glance
Based on auto-generated captions; names and details may be misheard.
- What: permitting of a battery storage project and a solar canopy.
- Where it stands: the canopy is closer to permitting; the battery is being sited with a weekly team and awaits a finalized power purchase agreement.
- Next: battery submission to the Public Utility Commission for a 90-day review; both hoped to operate next year.
Sources
Discussion time
About 1 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-10-14 - Burlington Electric Commission | 1 |
Log
- 2026-10-14 - Burlington Electric Commission - General manager's update.