Burlington Electric New Generation Project Permitting

At a glance

Based on auto-generated captions; names and details may be misheard.

  • What: permitting of a battery storage project and a solar canopy.
  • Where it stands: the canopy is closer to permitting; the battery is being sited with a weekly team and awaits a finalized power purchase agreement.
  • Next: battery submission to the Public Utility Commission for a 90-day review; both hoped to operate next year.

Sources

Discussion time

About 1 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-14 - Burlington Electric Commission 1

Log