CY26 Sidewalk Reconstruction Contract

At a glance

  • What: The 2026 Sidewalk Reconstruction and Pedestrian Crossing Improvement Project budget and construction contract with S.D. Ireland Brothers Corporation (Public Works).
  • Status: Approved on the consent agenda on April 27, 2026.
  • Next: The Public Works Director executes the contract after City Attorney review.

Detail

The Chief Administrative Officer or designee was authorized to make budget amendments and transfers to a project total of $1,657,399.70, and the Public Works Director to execute a construction contract with a maximum limiting amount of $1,506,727.00, within existing project appropriations. It passed with the consent agenda, unanimously (Schachter/McKnight); no discussion is recorded. See also CY25 Paving Contract Budget Amendment.

Sources

Log

2026-04-27 - City Council

Consent item 5.8. Approved unanimously with the consent agenda.