Fletcher Free Library Design Contract

At a glance

  • What: Second amendment to the Dore + Whittier Architects contract for design development and construction documents for the Fletcher Free Library Transformational Remodeling Project.
  • Status: Approved on the June 29, 2026 consent agenda (unanimous).
  • Next: The Library Director executes the contract after City Attorney review.

Detail

Professional services not to exceed $2,792,961; the maximum limiting amount of the overall contract rises from $213,000 to $3,005,961.00. The amendment is funded by the Friends of the Fletcher Free Library. The minutes record no discussion.

Sources

Log

2026-06-29 - City Council

Consent item 6.15, adopted with the consent agenda.

2026-10-26 - Board of Finance

Board approved the construction-manager-at-risk contract with ReArch Construction, unanimous. Pre-work phase about $60,000, funded by the Friends of the Library; $35 million project, public bond contribution anticipated for Town Meeting Day.