M Street Fiber network buildout
At a glance
Based on auto-generated captions; names and details may be misheard.
- What: M Street Fiber, a public-private open-access fiber network built under a contract with the city, updated the council on its buildout.
- Where it stands: council members were openly frustrated that early build areas already have service and that there is no timeline for the neighborhoods that most lack connectivity; the company says it is not changing the original plan, only building faster.
- Next: the company was asked to send its timeline, quality findings and plan for least-connected areas, and to return in about two months.
Company update
- Shimos joined as CEO in June; Kesler is the new general manager and president for Memphis. The company is backed by sponsor Meridiam (captioned 'Meridium') and describes an open-access network that lets multiple internet providers compete.
- Over 28,000 passings built this quarter, scheduled to reach 175,000 by the end of 2027; the first half of 2026 saw under 10,000. All 'fiber huts' (backbone sites) are connected; the ring was completed last month.
- Connecting 901 / Smart Memphis city network launches: Orange Mound a few weeks ago, Hollywood Community Center in early December.
Quality control
- Construction was slowed at the end of Q2 to retest the network because of concerns about quality at the pace of building; everything built in the last two years is being re-certified by year end.
- Contractor 'Congruix CNS' (as captioned) builds the network; Nokia has been the project management and quality control partner from the start; every new installation is re-certified before service is activated.
Council concerns
- Maps show heavy work in District 4 and the popular corridor of District 5 but little in Districts 3, 6 and parts of 2 (Hickory Hill), White Haven and Westwood.
- The original plan was a five to six year construction window (design in 2023, building from 2024); the project is in construction year four.
- The company said about 50% of completed work is in low-income areas and that it cannot create 'islands' because the network spreads from a central point. The executives did not have the figures or the original build-order rationale with them.
- Swearengen-Washington raised wires hanging low and interfering with MLGW lines; the company said it works hand in hand with MLGW.
Requests
- Send the buildout timeline and the re-certification assessment ahead of the next visit.
- Provide a plan for the areas with the least connectivity.
- Return in about two months (the chair) or six months (a member's suggestion).
Sources
- 2026-10-20 - City Council Committees (committee-day video, 10/20/2026)
- https://memphistn.gov/wp-content/uploads/2026/10/October-20-Committee-Agenda-final-as-of-10.15.16.pdf
Discussion time
About 27 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-10-20 - City Council Committees | 27 |
Log
- 2026-10-20 - City Council Committees — New leadership updated the council; members objected to the build order and the lack of a timeline for underserved areas.