Downtown crime center funding transfer

At a glance

Based on auto-generated captions; names and details may be misheard.

  • What: moving $319,000 within the downtown command (crime center) project from other costs to architecture and engineering (Districts 6 and 7, Super District 8).
  • Where it stands: approved by the full council on 10/20/2026 as add-on item 36 with same-night minutes and no opposing votes.
  • Next: phase two of the crime center can start.

Details

  • The project (IT010008) began as an IT project and was transferred to police services.
  • The transfer lets the city pay architecture and engineering invoices and start phase two of the downtown crime center.

Council action

  • Councilmember Canale moved, Warren seconded; roll call with no opposing votes.

Sources

Discussion time

About 3 minutes across 2 meetings (from transcript timestamps; approximate).

Meeting Minutes
2026-10-20 - Memphis City Council 2
2026-10-20 - City Council Committees 1