Tanglewood Force Main Replacement
At a glance
- What: replacement of the aging force main serving the Tanglewood Pump Station.
- Where it stands: approved September 14, 2026; contract awarded to Garney Companies at $9,163,764.50 with $458,188 available for contingency.
- Next: none recorded.
Scope
- About 19,980 feet of 20-inch force main.
- 161 feet of 24-inch gravity sewer.
- 10 air release valves.
- 422 feet of 36-inch casing.
- New pumps.
Bids
- Six bids opened July 29, 2026, from $9,163,764.50 (Garney Companies, Garner NC) to $11,618,311 (Moffat Pipe).
- The engineer's estimate was $9,994,050.