Western Bus Rapid Transit

At a glance

(From auto-captions; names and numbers may be misheard.)

  • What: the Western BRT corridor from Raleigh to the Cary multimodal center (about 12 miles, six stations in Cary) and its extension toward RTP (two more Cary stations).
  • Where it stands: 30% design submitted; service expected about late 2032 or early 2033; CAMPO action on the extension expected in September.

Log

  • 2026-07-23 - Town Council Work Session - Transit director update on both corridors and how BRT differs from local bus service (dedicated lanes, signal priority, level boarding, 10 to 15 minute peak frequency). A further study of options along I-40 and Kildaire Farm Road begins this fall. No action.

Sources