2026-10-21 - RHS Building Committee
Summary
Based on auto-generated captions; names and numbers may be misheard.
- Quorum present; September 23 minutes approved (one abstention).
- Four invoices approved, including Consigli's roughly 10.96 million dollar September requisition.
- GZA Geotechnical and Vibration Monitoring Extension: a 256,080 dollar request was cut back to about 180,000 dollars on a 5-4-1 vote.
- Revere High School Construction Project: about 22 percent complete, 48 days ahead of schedule, with untouched hard contingency; steel topping-off planned for December.
- No public comment. Adjourned.
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:0096.
00:01Um, today is Wednesday, October 21st,
00:042026.
00:06The time is 5:32 p.m. Roll call, please,
00:10Linda.
00:11>> Thank you very much, Susan. I am going
00:13to start with Mike Picardi.
00:16>> Here.
00:18>> Um,
00:18Stacy Rizzo, I don't see her. Um, let me
00:22check the waiting room. Nope. Um, I'm
00:24going to note as absent for now. Susan
00:27Gravelese.
00:28>> Here.
00:29>> Dr. Kelly.
00:30>> Here.
00:32>> Carl Svenson,
00:34not here, absent. No. Steve Knozi.
00:39>> Here.
00:41>> Rich Viscay.
00:43>> Here.
00:44>> Don Scarmella.
00:45>> Here.
00:47>> Nick Reistrom.
00:48>> Here.
00:50>> Um, Mayor Keefe.
00:53Absent for now. Tom Skrowronski,
00:56absent. No. John Stamatopoulos.
01:01Absent. Anthony Cogliandro.
01:05Absent.
01:07Don Martelli.
01:10Absent. Joshua Miranda.
01:13>> Here.
01:15>> Chris Scarmella.
01:17>> Here.
01:19>> Thank you. I am also going to just check
01:21the Somebody just
01:24um,
01:26joined the waiting list. Nope, that is
01:28it. Okay, we still do have a quorum. So,
01:30thank you very much, everyone. Brian,
01:32I'm going to turn it over to you
01:35to go through the agenda and all the fun
01:37stuff for tonight.
01:39>> Sounds good. 1 second. I just want to
01:42get one more file open.
01:48Okay, let me share my screen.
01:57Okay, so, uh, first order of business
02:00agenda item two, approval of meeting
02:02minutes from September 23rd, 2026.
02:05There are no questions or comments, we
02:07would move that to a motion to approve.
02:09>> So moved.
02:11>> Second.
02:20>> Sorry folks, give me a second here. I
02:22see John Stamatopoulos just arrived, so
02:25I'm going to note him as arriving at
02:285:35.
02:32And do the roll call for the minutes,
02:36uh starting with Mike Picardi.
02:39>> Yes.
02:41>> Uh Susan Gravelese.
02:42>> Yes.
02:44>> Dr. Kelly.
02:45>> Yes.
02:47>> Steve Kenosian.
02:48>> Yes.
02:49>> Rich Viscaino.
02:55>> Yes.
02:56>> Thank you, Rich. Don Ceramella.
02:59>> Yes.
03:00>> Nick Reistrom.
03:01>> Abstain.
03:03>> Thank you.
03:05John Stamatopoulos.
03:12John, I I know you just joined. We are
03:14going through the um
03:16invoice or the um
03:19approval of last month's meeting
03:22minutes, and I see you putting a note
03:25that you're on a flight.
03:27Are you able to give us a thumbs up for
03:30your vote on the meeting minutes?
03:40I don't see any chat. I will put a
03:44question mark for now. Um Joshua
03:46Miranda.
03:47>> Yes.
03:49>> And Chris Ceramella.
03:50>> Yes.
03:52>> Thank you.
03:55>> Thank you. Next we'll move into
03:57invoices. Let me move my zoom controls
04:00here.
04:03Uh four groups of invoices tonight. All
04:05the typical ones. First is left field
04:07invoice billing to 32% completion of the
04:10construction phase
04:12uh in the amount of $185,274.
04:16If there are no questions or comments,
04:17we would move that for a motion to
04:18approve.
04:20>> Motion to approve.
04:22>> Second.
04:29>> And I will do the roll call uh for left
04:33field invoice. Mike Picardi.
04:35>> Yes.
04:36>> Susan [snorts] Gravelese.
04:38>> Yes.
04:40>> Dr. Kelly.
04:40>> Yes.
04:42>> Steve Knoosie.
04:44>> Yes.
04:45>> Rich Biskay.
04:46>> Yes.
04:48>> Don Ceremello.
04:51>> Yes.
04:52>> Nick Reistrom.
04:54>> Yes.
04:57>> John Stamatopoulos. Are you able to give
04:59us the vote?
05:00>> Yes, [clears throat] please. Pay the Pay
05:01the bills. Yes. Thanks.
05:03>> Yes, perfect. Thank you.
05:05Uh
05:06Joshua Miranda.
05:07>> Yes.
05:09>> And Chris Ceremello.
05:10>> Yes.
05:13>> Thank you.
05:14>> Uh next Briggs uh independent
05:16construction testing uh material testing
05:19agency. Uh
05:20this month in the amount of $55,604.38.
05:24We have consumed 72% of this $400,000
05:29uh budget. This is one of the items
05:30we've noted probably in a
05:32two-ish months, maybe a few meetings
05:34from now, December or January, we're
05:36going to recommend a value to uh add to
05:38that $400,000 budget that is in our
05:41monthly forecast of one of the few
05:43categories here that uh might need help.
05:47Uh but we still have adequate money to
05:49be uh, moving through steel and
05:51concrete, which is where the bulk of our
05:52testing is. This uh, this will be a
05:55lesser value as we move forward uh,
05:57after all the steel and concrete tests
05:59we're doing. So, uh, more info to come
06:02on how to what we will recommend
06:05increasing this overall $400,000 budget
06:07to, but for tonight, the Briggs invoice
06:09is ready to go. $55,604.38.
06:16>> I'll move.
06:17>> Thank you.
06:18>> Second.
06:32>> Linda, you're unmuted.
06:35>> Oops, sorry. I had my
06:36>> Sorry. [laughter]
06:39I'm having too much trouble getting my
06:41brain to uh, connect with what my hands
06:43are doing. Um, that second was by Mike
06:45Picardi, correct?
06:47>> Yep, that was me.
06:48>> Thank you.
06:49>> [laughter]
06:50>> Um, and for the roll call, um, Mike
06:52Picardi.
06:54>> Yes.
06:55>> Susan Gravelese.
06:56>> Yes.
06:58>> Dr. Kelly.
06:59>> Yes.
07:01>> Steve Knoosie.
07:02>> Yes.
07:04>> Rich Viscay.
07:05>> Yes.
07:06>> Don Seramella.
07:07>> Yes.
07:10>> Nick Reistrom.
07:10>> Yes.
07:12>> John Stamatopoulos.
07:16>> Yes.
07:18>> Thank you. Joshua Miranda.
07:20>> Yes.
07:22>> Chris Seramella.
07:26>> Yes.
07:28>> Thank you.
07:30>> Thank you. Next invoice, Perkins
07:31Eastman, 17% of the construction phase
07:35uh, billing to no sub-consultant
07:36invoices. Total amount, $442,750.
07:40And just a reminder that I mentioned it
07:43every month. Um
07:44there um Perkins Eastman in their
07:46contract there construction phase
07:50uh
07:51began after ours did. Uh they So, these
07:54numbers, while they're not the same, um
07:57when we calculate out how these
07:59contracts are supposed to bill out and
08:00how they were structured, it remains
08:02accurate. So, um there are any
08:04questions, we would look for a motion to
08:06approve Perkins Eastman Perkins
08:09Eastman's invoice.
08:11>> So moved.
08:12>> Second.
08:20>> Thank you. Just noting that Carl Swenson
08:24has arrived at 5:40, so he will be
08:27included in the roll call for Perkins
08:31Eastman invoice. Mike Picardi.
08:33>> Yes.
08:34>> Susan Gravelese.
08:36>> Yes.
08:37>> Dr. Kelly.
08:39>> Yes.
08:40>> Carl Swenson.
08:41>> Yes.
08:43>> Steve Conosky.
08:44>> Yes.
08:45>> Rich Viscay.
08:47>> Yes.
08:48>> Don Sermella.
08:50>> Yes.
08:51>> Nick Reistrom.
08:53>> Yes.
08:55>> John Stamatopoulos.
08:57>> Yes.
08:59>> Joshua Miranda.
09:01>> Yes.
09:03>> Chris Sermella.
09:04>> Yes.
09:06>> Perfect. Thank you.
09:08>> Thank you. Final invoice.
09:10>> The uh Consigli September construction
09:12requisition 16A.
09:14Um high-level point on this just um
09:18the pro- the review process on this all
09:20of the subs as they bill Consigli,
09:22Consigli vets whether their percentage
09:25is complete and what they're um billing
09:27for is accurate. Left Field then does
09:28the same thing when the draft
09:30requisition comes through us. So, um
09:32this bill uh on a monthly basis goes
09:34through a lot of hands to make sure we
09:36feel it's accurate. Overall, billing to
09:3821% completion of the construction
09:40contract with the major contributors
09:43remaining to be concrete, which is
09:45approaching 50% complete and build out.
09:48Structural steel just over 50% and then
09:52the other main areas of focus are site
09:54work and geothermal wells billing to 50%
09:56and 59% respectively. The other smaller
10:00items of trades that are are underway
10:03are waterproofing. There is a initial
10:05waterproofing is scope along the
10:06foundation and along the base of the
10:08building. Metal siding billing 1% is the
10:11first bill from them. That spawns and
10:13support for the mock-up panel and then
10:17some of our MEP trades with early
10:19purchase equipment and long lead items.
10:21Fire 4% of fire protection build, 8% of
10:24HVAC build, 3% of electrical build. So,
10:28again, we've put a lot of attention into
10:29this in a monthly basis. We feel these
10:31are all billing to the appropriate
10:32percentages. As always, retainage comes
10:34off the bottom. We'll discuss retainage
10:36release of retainage a lot further along
10:38in the project. If there are no
10:41questions on the Consigli bill, we would
10:43entertain a motion to approve in the
10:45total amount of $10,964,840.85.
10:51>> Brian, just one question on the negative
10:53value on the CM contingency.
10:57>> The CM contingency negative value, I
11:00believe Darren, you might have to help
11:02me out. I remember talking to Brian
11:04Johnson he couldn't be on this meeting.
11:06I think that was a I forget what that
11:09was a credit for. Um
11:12I don't think it was buyout savings, but
11:14I'd have to jump in there to check. I'm
11:16not sure if you know off the top of your
11:18head, Darren.
11:18>> I don't know that number off the top of
11:21my head. I'll have to look at it closer.
11:27>> I might have to follow up with that, but
11:29um I remember talking to Brian about it.
11:31It was a credit uh for some item. Most
11:33credits within any of these sections
11:36flow into the contingency before at the
11:38end of the job them coming back to the
11:40owner.
11:43>> We always like credits.
11:45But if you could get clarity for our
11:46next meeting, that would be good.
11:48>> Yeah, we'll do.
11:56>> I'll make the motion to pay the Consigli
11:59invoice in the value of $10,964,840.85.
12:06>> Second.
12:12>> Thank you. Uh roll call, Mike Picardi.
12:16>> Yes.
12:18>> Susan Gravilleese.
12:19>> Yes.
12:20>> Dr. Kelly.
12:21>> Yes.
12:23>> Paul Svenson.
12:24>> Yes.
12:26>> Steve Knoesel.
12:27>> Yes.
12:28>> Rich Viscay.
12:30>> Yes.
12:31>> Don Scaramella.
12:32>> Yes.
12:33>> Nick Reistrom.
12:35>> Yes.
12:36>> John Stamatopoulos.
12:38>> Yes.
12:40>> Joshua Miranda.
12:42>> Yes.
12:44>> Chris Scaramella.
12:45>> Yes.
12:47>> Thank you.
12:49Brian.
12:50>> Thank you. Uh next agenda item four, um
12:53we have an item that we have been
12:56previewing as
12:57uh potential for an uh additional
13:00service contract amendment for Perkins
13:03Eastman. Uh at first, I'm going to jump
13:05into this budget summary. Uh this is an
13:08item that's been living on the
13:10architecture and engineering line in the
13:12current exposures column for a few
13:14months. Um
13:16we knew when we
13:18executed the um initial
13:23not the GMP contract, but the early
13:25construction awards,
13:27um that we did not have coverage in the
13:30existing base contract for Perkins
13:32Eastman for geotechnical monitoring
13:35during construction. Um and we would
13:37like to go through this today. Let me go
13:40through these two slides. I'll be pretty
13:42quick. And um
13:45and we'll get through this. The short
13:47story is that we carried when we awarded
13:50construction and began construction, we
13:52included a 10-week duration
13:54for the on-site monitoring of
13:56construction by the GGA um team. They're
13:59our geotechnical engineer. That's
14:01related to observations for site work,
14:04ground improvements, geothermal wells,
14:06foundations, steel, concrete. Um
14:09basically a lot of the heavy stuff that
14:11we need to ensure that the uh all the
14:13settlement parameters of various pieces
14:15of the site are all within spec and
14:18working. We also included a 16-week
14:20duration for vibration monitoring, which
14:23is uh primarily done through devices
14:25that are deployed on the site that
14:27report back to us that um the
14:29geotechnical engineer analyzes, passes
14:32reports through to make sure we're not
14:34exceeding any vibration
14:36um
14:37levels leading the site leaving the site
14:40at the uh perimeter of the site.
14:42For record, we have had no um
14:45instances of one of those vibration
14:47monitors going over the limits of what
14:49we're watching it for.
14:50Um however, based on all the items that
14:52we've been talking about related to site
14:55work, slow getting out of the ground,
14:56and some of our challenges with getting
14:58to the point where we were erecting
15:00steel,
15:01uh these services were really only
15:03carried through the end of September.
15:04So, as of this month, we asked the
15:07architect to put together a final
15:09proposal uh to cover both the monitoring
15:13of construction because we still have
15:14ground improvements, geothermal wells,
15:16foundation steel underway. And um
15:20based on some discussions, we feel it's
15:22in the project's best interest to extend
15:23the vibration monitoring through the end
15:25of the project. So, long story short,
15:27we're proposing, in addition to the
15:2910-week duration that was already
15:31carried and has already elapsed, an
15:33additional 70 days
15:35um for the construction monitoring, and
15:37we're requesting to run that vibration
15:40monitoring through the end of the
15:41project's substantial completion in
15:432028. Um but you can see in the middle
15:46of this page, down in this area,
15:49is um the original four tasks in GZA's
15:52proposal that made up the last Perkins
15:54Eastman amendment. Um RFI and submittal
15:57review, the original cost was $30,000.
15:59There's no change to that. And general
16:02project meetings and management, 80
16:04hours were carried, it remains accurate,
16:05there's no change to that.
16:07Um we are looking to add 70 days to the
16:1020 weeks that we carried for
16:12construction consulting in the cost of
16:14$154,000,
16:16and carrying the vibration monitoring
16:18past the 16 weeks we originally carried
16:21through completion of the project. Uh
16:23those total $256,080.
16:28I'll take a quick pause there to talk
16:29about this before we run we go to a
16:31motion. I just want to talk about how
16:33this would get funded in the the health
16:36of the contingencies that fund this. But
16:38I'll stop now to see if there's any
16:39questions or comments.
16:41>> I have a question.
16:43>> Sure.
16:45>> Help me understand
16:47why we had 16 weeks of vibration
16:50monitoring at 23,900,
16:53and why we need to
16:56spend fivefold on that. Is that
16:58something we need to do, or is that
17:00something that's nice to do? Uh what's
17:02what why is it quadrupling?
17:04>> Uh it's really simply it's based on
17:07time. Um
17:08at at the time when we executed the
17:10original contract, our original thought
17:12was we wanted to carry it at least
17:14through
17:15establishment of the foundations and
17:17structural steel and some of the heavier
17:20site work.
17:21Um as we've
17:23as we've continued to talk with the
17:25engineers, with Consigli, we feel it's
17:28in the city's best interest interest to
17:30continue this monitoring. It's not
17:32required by law, so to speak. However,
17:35if there are any um events that do that
17:38might cause damage offsite, we feel this
17:42is an investment in being able to uh
17:45rebuff any claims being that we're
17:47alongside a neighborhood and a train
17:49track, uh the commuter rail. So, this
17:52more or less gives us hard data if any
17:55entity outside the site comes back in
17:57the future and says, you know, banging
17:59around all that steel, hauling all that
18:01site work affected my my train, affected
18:05my house, affected my business, we would
18:07at least have a baseline to uh show
18:11show numerical values for um what did or
18:13didn't leave the site.
18:15>> And 16 weeks isn't enough data?
18:19>> Um in the 16 weeks we haven't tripped
18:21the threshold. We think keeping the
18:23machines and keeping the monitoring
18:24there through completion, I understand
18:26it's a $102,000 cost is uh
18:29is a worthy investment for the city.
18:33And I'm not sure if anyone from the
18:35project team wants to add into that. Um
18:37I'm just seeing who's on.
18:38>> I'm still not clear why it's worthy, so
18:40someone may have to take another crack
18:42at it.
18:42>> And
18:43uh and one of the reasons
18:44[clears throat] or the considerations
18:46are that um just like for instance the
18:49surveys that we did of the surrounding
18:52uh residences uh
18:54to the site is that we are protecting
18:58the school from the possibility of a
19:02claim being made for damages to the
19:04residents. The vibration monitoring is a
19:07similar uh means by which to protect the
19:10school from future claim that could be
19:13made by showing that we've had data and
19:16baseline established throughout the
19:18whole project that therefore if a claim
19:21would be would to be made that some
19:23vibration caused cracking in someone's
19:26foundation for instance, we could go
19:28back to this data and show that in fact
19:33we were below the thresholds.
19:35>> Why wasn't it in there in the first
19:36place then?
19:39>> Um
19:41It could have been should have been it
19:44would have been included as a additional
19:46cost in the original Perkins Eastman
19:48contract if we had included it. We did
19:51not it wasn't included as basic services
19:53so once we got to construction and had a
19:55real construction schedule, we were
19:57going to have to budget this from the
19:59soft contingency. Um and perhaps at the
20:02beginning when we signed them up for 16
20:04weeks we maybe should have had the
20:06discussion that we recommended going
20:07through completion at that time but
20:10either way the cost would have been the
20:11same whether it was then or now.
20:16>> Brian, can I ask a clarifying question
20:18on that?
20:19It makes sense to me to I think it's a
20:21you know $100,000 to protect the city
20:24from any litigation that
20:26people could say well you didn't
20:28continue to collect data after those
20:29first 16 weeks. That makes sense to me
20:31to spend the money.
20:32But I think Rich's original question
20:35which I have also is if the first 16
20:38weeks of vibration monitoring cost
20:40$23,000,
20:42why does the next let's call it 12 weeks
20:46cost $102,000?
20:49Do you see the discrepancy there?
20:51>> Yeah, this number is over 2 years. So
20:54through completion is 2028.
20:57It's it's it's more or less 26 months is
21:00what this 102 would entail as opposed to
21:03the 6 weeks. And it's
21:05we sort of count the what is the weekly
21:07rate. And this weekly rate is actually a
21:11little less than the weekly rate that
21:13was established here. Part of that is
21:15one of the efficiencies we can find in
21:17this is not needing a report every 2
21:19weeks from them. We can reduce the
21:21frequency of getting a report um
21:24because during the initial 16 weeks
21:26nothing has happened. We have our
21:27baseline. So, it's a little cheaper on a
21:30weekly basis for this 102 than it was on
21:33the 239 original.
21:35>> Okay, that makes sense to me. I think it
21:37would be clearer if instead of through
21:39completion it actually said
21:41>> Yeah.
21:42>> what the time was.
21:43>> So, yeah. I I think it works out to be
21:45about 26 months is what that should say
21:48instead of through completion.
21:55>> And I know Don Chiaramella has his hand
21:58>> Sorry, I didn't see that.
22:00>> Hi
22:01guys. Um so
22:04um you know, the data can also work
22:07against us. You you're assuming that
22:09we're always going to stay under the
22:10threshold of um vibrates of vibration
22:14monitoring.
22:15But, most of the heavy construction has
22:16been done.
22:18So
22:19I think there's probably less chance of
22:23um vibration in the site. You have to
22:25agree that it is a little remote from
22:27houses. Not so much the train.
22:31But, the houses I don't think would be
22:33impacted by the
22:35construction going on because you know,
22:38you're kind of an island out there.
22:40Um
22:42Also, is there a protocol for
22:45um
22:46vibration monitoring for construction
22:49projects of this scale?
22:52>> Uh to my knowledge this is not required
22:55by any permit or code.
22:58Um it's a belt and suspenders that is
23:00mainly about um being able to defend
23:04against potential claims and
23:08I'll I'll leave that answer. I I have
23:10just another comment on your initial
23:12comment.
23:12>> I think
23:14Let Let Dan call and respond, please.
23:19>> Sure.
23:22I didn't know that I had started
23:24speaking.
23:26>> No, I I The question was So, the
23:28protocol I've been doing this a long
23:30time. My experience is buses and trains
23:32actually vibrate more
23:35than the construction equipment on site.
23:38So, what we've seen over the years is
23:39the MBTA will come back and say they've
23:43got track improvements
23:44and they want proof.
23:46Well, we have to be able to defend that
23:49our vibrations were less than their
23:50vibrations as one example. MBTA buses,
23:53believe it or not, on
23:56out on the road there, actually bounce
23:58more and make more vibration than the
24:00equipment on site.
24:02The big picture is we're going to be for
24:05quite a while still working heavy
24:06equipment, especially down towards the
24:09um the houses. We still have the fields
24:12down there.
24:13>> Yeah.
24:13>> The fields.
24:14So,
24:15none of us disagree this is
24:19probably never going to exceed that
24:21limit.
24:22>> And maybe maybe it's possible that
24:25this duration can be trimmed back as we
24:28get closer to the finish line.
24:30>> So, that that's a worthy note that these
24:32are both These aren't lump sums. So, the
24:35both both these 70 days are going to be
24:38tracked and if there's a point in the
24:41future, namely I
24:43if we get through the work on the
24:44northern side of the site towards the
24:46neighborhood, the heavy rolling and
24:48heavy site work,
24:50we could decide to pull the plug on this
24:51at the in the future and it would just
24:54the remaining money would come back to
24:56the owner. So, neither of these are a
24:58full commitment out of the gate. If we
24:59only end up needing 50 of these days,
25:01there'll be money left over and returned
25:03to the owner. And if we decide to pull
25:04the plug after we're done rolling those
25:07fields and digging that retention basin
25:10out in the back upper corner of the
25:12site, we could always pull the plug on
25:14this at a future point. And we can make
25:17note to discuss that regularly with the
25:18team if that's something the committee
25:20is interested in.
25:23>> Do I have to wait for a motion to amend
25:25that or can I amend this motion?
25:28>> Um you can
25:29you can amend the motion however you'd
25:30like.
25:31>> I amend the motion to appropriate
25:33$180,000 for this service.
25:38>> For total, so 154
25:42plus
25:43>> I don't I don't care how it's split up.
25:45>> [clears throat]
25:49>> So, 180k. I'm just trying to do this
25:52150.
25:5726. So, that's going to that more or
25:58less would change this 102 to 26.
26:02>> Yeah, but I'll I'll I'll I'm willing to
26:04double it and I want to report on some
26:07kind of Gantt chart on when the ideal
26:09times would be to do vibration checking
26:11cuz I tend to agree with Donnie. I think
26:13most of the heavy stuff's done. If we
26:15want to do some spot checking and have
26:16some good data, but I think this is a
26:18little bit of overkill. So, that's my
26:20motion.
26:22>> Okay.
26:23>> If I could just discuss on the motion,
26:27um
26:29I just feel like we have some
26:31construction experts in the room. I know
26:33John Ciaramella is one of them.
26:35Um but we have others who have built
26:37schools and done projects like this. And
26:39if
26:40the money is not at risk of going out
26:44the door tomorrow, but we can allocate
26:46the funds so that those
26:48in charge um can act in ways that they
26:52to without being overly loose with it
26:55and have regular check-ins, I'd rather
26:57allocate the full $256,080
27:00requested
27:02and just make sure that we have those
27:03check-in meetings that Brian Day can
27:05just describe.
27:08>> Yeah, Dr. Kelly, to the same effect, I
27:09feel like if there's a need for more
27:11money, they can always come back, too.
27:13So, I'd rather the I'd rather have a
27:15little bit more control over this
27:17because I don't have enough data, but I
27:18respect your opinion.
27:20>> Um, excuse me. I'm trying to raise my
27:22hand, but I can't find it on this chart.
27:24So, I'm raising my hand manually instead
27:27of virtually.
27:29Um, I believe the process when a motion
27:31is made and someone has an alternate
27:33motion, they have to
27:35make a motion for the alternate motion,
27:37then it has to be voted on. And if that
27:40alternate motion is approved, then it
27:42will move forward.
27:44As far as like Robert's Rules, am I
27:46correct, DK?
27:48>> Yes.
27:50>> Uh, and I just want to follow along.
27:52>> That's why I asked in the first place.
27:54>> Nobody's made the original motion.
27:56>> That's what I was asking in the first
27:58place.
28:02>> And and that's also correct. I think the
28:04original motion is just proposed
28:06language by Brian, so there's no actual
28:09motion on the floor for there to be an
28:11amendment except So, Rich's motion would
28:14be the motion on the floor if somebody
28:17seconds it.
28:18>> That is correct. My interpretation.
28:20>> Yep. Yes.
28:25>> I'll second it.
28:27>> Chris.
28:30>> And can we repeat the motion on the
28:33floor before we have a vote, please?
28:37>> 108,000 dollars total as opposed to 256.
28:41>> Okay.
28:42Thank you.
28:47>> Okay. So, I'm going to do the roll call
28:51for the motion on the floor currently as
28:53it stands. Mike Picardi.
28:59>> I'm thinking. I'm here.
29:01>> Go back to him.
29:02>> [laughter]
29:03>> Back to me.
29:04>> back. Susan Gramlich.
29:06>> No.
29:08>> Okay.
29:09Dr. Kelly.
29:11>> No.
29:13>> Carl Svenson.
29:15>> Yes.
29:17>> Yes. Steve Knozi.
29:20>> No.
29:22Under all
29:22>> No.
29:24>> Yes.
29:24>> Mike Picardi.
29:25>> Going yes.
29:27>> Yes.
29:28>> Thank you.
29:29>> Uh Rich Viscay.
29:32>> Yes.
29:34>> Don Sermella.
29:37>> I'm sorry. I'm confused.
29:41Uh I don't mean to break up the roll
29:43call there, but
29:45>> No worries. The motion is uh
29:48not the one that's written, but it's to
29:50allocate 180,000
29:53to both categories tasks three and four,
29:56basically.
29:57>> Yes, but I have a lot of questions.
30:01I don't really think any of it is
30:04necessary. The amended amendment or an
30:08amendment to to continue
30:10seismic monitoring. I just don't agree
30:13with any of it.
30:14>> No.
30:15>> So, how would I vote?
30:16>> You can abstain from voting.
30:19>> I abstain.
30:20>> Okay. I'm going to change your yes to
30:23abstain.
30:26Nick Reistrom.
30:28>> Yes.
30:30>> Yes. John Stamatopoulos.
30:35>> I think we lost John.
30:36>> we lost John.
30:38Yep.
30:42Joshua Miranda.
30:44>> No.
30:46>> No. And Chris Sermella.
30:48>> Yes.
30:50>> Yes. Okay, I'm going to have to actually
30:52check this math here. So, we've got
30:54>> I got one Five yes, four no.
30:57One abstain.
31:00>> Four
31:01Five yes, one two three
31:05four no and one abstain.
31:09Oh, sorry. No. One two three
31:12four
31:14five yes
31:15one two three four no's and one abstain.
31:20>> Agreed. That's what I got, too.
31:22>> Okay, perfect.
31:23>> So, that means the motion passes and we
31:27will um
31:29we will divide that up. We'll come back
31:31with a report on how far that gets
31:33vibration monitoring and if we need to
31:34talk about that in the future, um we'll
31:36bring it back to the committee.
31:39>> Brian, could you ask Could that
31:40evaluation kind of go with the flow of
31:43the type of construction that's going to
31:44be done? What kind of impact, what kind
31:47of vibrations may happen versus
31:49one task versus another?
31:51>> Yeah, I think that's how we'll follow
31:53up. I'll discuss with the team and um
31:55see if maybe
31:57see how far that can get us in terms of
31:59perhaps stopping it and then getting it
32:01back out there when um
32:05when we're rolling those fields and
32:06getting closer to the neighborhood.
32:07We'll we'll come back with some sort of
32:09idea
32:10um
32:10and discuss it further at the next
32:12meeting.
32:12>> And probably worth having the data on
32:15the 16 weeks that were actually done and
32:17see what the
32:18the you know, the bell curve is and how
32:20close we were to any impacts. I mean, I
32:22think that's a pretty big number to
32:24quadruple without much of data, so
32:26thank
32:28>> Yep.
32:31So, I have this next slide. I just let's
32:32just cover this if that's all right with
32:34the committee. I I wanted to snapshot
32:36the contingencies cuz that is um this is
32:39funded by contingency. Just as a
32:41reminder, the two main owners
32:43contingencies, we call one the soft
32:44contingency. That's primarily for things
32:47like this, uh engineers, architects,
32:49OPM's professional services.
32:52Um and that original value was just over
32:542 million for the soft cost.
32:57Um before tonight's motion,
32:591.4 of it was used and 605 was left.
33:04Um this bottom is now slightly out of
33:06date cuz I just used the entire
33:07amendment amount, but um we'll basically
33:10take 180,000
33:12um
33:14as the value. Regardless, the whole
33:16point of looking at this was, yes, we're
33:19eroding soft contingency.
33:21Um we'll have around probably 400,000
33:24remaining, not 349, after we do the math
33:26from tonight's motion.
33:28Um the only known items that we have
33:30against that, one is that topping off
33:32the construction testing budget, which
33:34we'll come back to um with some better
33:37ideas at the next meeting of what that
33:39value should be.
33:40And next is um something that's been
33:43lingering for a little bit that we
33:44talked way back in the day that once we
33:46get construction rolling, we potentially
33:48want to um
33:50go through whatever process is needed
33:52from an environmental environmental
33:54permitting point of view to clean up the
33:56ditch, to clean phragmites out of the
33:58ditch, to clean trash and other items
34:01out of the ditch. So, those items are
34:03the only ones we have on our radar, so
34:05to speak, that might go against this
34:07remaining balance, which would end up
34:08around 400K.
34:11I wanted to point out we haven't touched
34:12the owner's hard contingency, which it's
34:14primary uh this primarily funds
34:18construction changes, physical changes.
34:21Um we haven't touched it and there's
34:23nothing in the pending column to go
34:25against it. Um however, the story is a
34:28little bit better than that. I wanted
34:29just to remind folks that in addition to
34:31the untouched 18.5 million contingency,
34:34we do have 14.8 million in savings from
34:37signing up the GMP. Once we receive the
34:39MSBA project funding agreement bid
34:42alternate um
34:44the PFA bid amendment, sorry.
34:46This money will probably most likely
34:48flow into this 18 value. So, the 18.5
34:52and the 14.8 will be combined.
34:54And to date against buying out the GMP,
34:57which was 14.8 million under, we're
34:59tracking almost 3.5 million under on
35:02buyout savings. So, that savings
35:04ultimately would get moved to the CM
35:06contingency and any unspent CM
35:09contingency gets returned to the owner.
35:10So,
35:11the point of this was even though the um
35:13soft cost contingency on paper is you
35:16know, been eroded and has about 400k
35:19left,
35:21in the event that it ever zeros out, we
35:23can still tap this hard contingency if
35:26needed. But, generally speaking, the
35:28project is uh very financially uh
35:31healthy.
35:32And as we get further into getting that
35:35PFA amendment back from the MSBA and we
35:37get closer to the end of construction,
35:40we'll be previewing where we think we'll
35:42land. I'm confident we'll exceed any of
35:44the values we've discussed with the
35:46city, the committee, and you, Rich, um
35:48at the end of the day. But, we need to
35:50get this next 2 years of construction
35:52done.
35:59Uh I hid my Zoom controls. If there's no
36:01hands up, I'm going to move back to the
36:03agenda.
36:06Uh we'll come back to the very end
36:08talking steel topping off. But, uh quick
36:10in terms of monthly report overview
36:12before I hand it over to Consigli for
36:14their update. Um the two most important
36:17pages summaries from the monthly report.
36:20Again, GMP schedule in green middle
36:22columns current schedule in blue. Long
36:25story short, looking down at the bottom
36:27line, we are still tracking uh 48 days
36:30ahead in terms of substantial
36:32completion. Contract substantial
36:33completion date November 8th, 2028, and
36:36currently tracking towards September
36:3821st, 2028. So, we still got a lot of a
36:42lot of 0% we're working our way down
36:44from earthwork into the structural frame
36:47and closing the building in. So,
36:49this has to hold up for the next few
36:51years, but schedule overall is in very
36:53good shape. And same outlook for the
36:56budget. I know I just touched upon that
36:58a minute ago,
37:00but here you can see those two values I
37:02talked about the 18 million and the GMP
37:04savings added into 133 million in hard
37:07contingency, none of it expended, and
37:09nothing on the radar against that.
37:13Ultimately, 400 or so 400 and change
37:16remaining in soft contingency with the
37:18project about 22% done overall.
37:22>> All right, before we before we go too
37:24deep into budget, can we go back to
37:25schedule?
37:26>> Sure.
37:27Let me Which was that in? That was in
37:30here.
37:31>> Is there anything that's changed here
37:33since last month?
37:37>> Um
37:40There's been small
37:43movement one way or the other, but
37:46the the the thing that you want to
37:48always be focused on is substantial
37:51completion date.
37:54Last month, we were showing 921, I
37:57believe, and this month we're still
37:58showing 921.
38:03Versus versus the the target substantial
38:07complete, or I should say not the
38:08target, but the
38:10the GMP agreement
38:13number
38:14date of 11/8.
38:17Which is a static number.
38:20That's what's in the yellow yellow
38:23columns are are what we must
38:27obtain versus in the blue columns which
38:30are what we're tracking.
38:34>> Right. It's I think it's just helpful to
38:37see or to hear
38:39so that everybody doesn't have to go
38:41line by line comparing two dense
38:43spreadsheets.
38:45Uh if that if there was anything changed
38:47if we could know what that is from month
38:49to month.
38:51>> What I can do Dr. Kelly is uh in advance
38:53of the building committee meeting I'll
38:54do a comparison to last month's and just
38:56highlight a few cells um and we can sort
38:59of see up in here the these numbers all
39:01get these dates rather all get updated
39:03on a monthly basis or not if there's no
39:05change. And what we can start doing is
39:08I'll jump in this file after Consigli
39:10sends it over and just highlight a few
39:11areas. Did we lose time? Did we gain
39:13time? Um
39:16>> That would be helpful.
39:19>> Okay. You can note.
39:23Okay.
39:24Um
39:26Wasn't much more to say in the budget
39:28department. Um
39:30we're going to move the money the
39:32preview of the GZA money that we moved
39:35tonight out of the exposures column
39:37and into the $180,000 of it into the
39:41approved CEO column.
39:43Otherwise we're still previewing the
39:44same potential overrun for furniture.
39:46We'll be talking about that a lot more
39:48this winter. And
39:50um a couple of potential overruns namely
39:53testing services which we're plugging
39:55150k in this value for now. Um and just
39:59a small value 25,000 is in this column
40:03for if we need to return to uh
40:06some sort of permitting effort based on
40:07cleaning up the ditch. So really nothing
40:10new in here except for the removal of a
40:14$200,000 preview we had about the
40:17National Grid permanent electrical
40:19service. Um we have since got the final
40:22permanent electrical service back charge
40:24from National Grid. It is not over
40:27budget like we feared it would be. So, I
40:29have removed uh 200,000 from the current
40:32exposure column in the uh miscellaneous
40:35cost category as compared to last month.
40:37So, in terms of a compact the last
40:39month, this month's current exposures in
40:42the budget are 200,000 less than they
40:45were last month.
40:49>> That's good news, Brian. Where does that
40:50200,000 live now?
40:54>> Uh the 200,000
40:55>> no, no, no, where?
40:57>> Yeah, nowhere. Correct. It came out of
40:58this cell that only has the 150 left for
41:01potential um
41:04I'll see if I can zoom in and you can
41:05sort of see my note a little better, but
41:07the the note that pops up here, I
41:09removed the 200,000 from this cell and
41:12we're keeping 150 as a preview for um
41:17potentially needed in
41:19testing category. So, it came out of
41:21this cell, H14.
41:23>> I got it. Thank you.
41:32>> Oh, that was John in the chat. Um
41:36If there are no other questions on these
41:38items, I will turn it over to Consigli
41:41uh for their progress update.
41:48>> Okay. Um um
41:50Just one one minute while I get
41:56if I can uh share here.
42:08Okay. Hopefully, everyone is seeing my
42:10screen.
42:11>> Looks like it's loading. Yep, it's
42:13there. Got it.
42:14>> All right.
42:16Okay, so for the last um
42:20for this meeting, this kind of shows the
42:23latest and greatest where we are over
42:25the last uh
42:27several weeks.
42:29Um
42:32I I'm assuming everyone is fully aware
42:35of the project layout, but I'll I'll
42:38start scrolling to some of the locations
42:40and explaining where we're at.
42:43Um
42:44So, the net this item here is a uh
42:48aerial view of the geothermal well
42:50field, which will eventually be
42:53the baseball field.
42:55Um the geothermal wells have all been uh
42:58drilled. They're uh all So, all the
43:01drilling is complete, thankfully,
43:03finally.
43:05Uh we are now in the process of running
43:08all of what we call the circuitry, which
43:10is the the lines that make connections
43:14uh from the drill wells all the way down
43:17to the end uh which would tie into a
43:22series of vaults
43:24that then feed from those vaults to the
43:26building.
43:28So, right now what we're doing is we're
43:30we're back we're trenching to run those
43:33circuits between the each one of the 300
43:36wells
43:38across the field to the end of the
43:40field, and um
43:43uh and then we're um
43:45in the process we're also um
43:48removing a lot of
43:50uh unsuitable uh
43:52unsuitables in the field, uh in this
43:54case peat.
43:56Uh and then we're backfilling. So,
43:59we're um
44:00we're about uh a little
44:03around halfway across the field at this
44:05point
44:06uh with regards to that process, but we
44:09still have a ways to go in terms of the
44:11general uh thermal well installation. We
44:14still have to set the vaults. We still
44:17have to run all the the lines from the
44:20vaults to the building.
44:22But, this is coming along uh pretty
44:24well.
44:27Um
44:29drone photo over here over the entire
44:32site or I should say the entire
44:34footprint of the building. Uh in the uh
44:37foreground is building C. Uh the walls
44:40are nearly complete. Um what you don't
44:43see at the very bottom here is the end
44:46wall, which is in the process of being
44:48formed
44:49uh right now to be poured in. That would
44:52complete everything, the entire
44:54perimeter foundation of the building
44:56with the exception of
44:58uh an entranceway that we're using for
45:01logistical uh purposes at the center of
45:04the building,
45:06uh what we call uh well, building B.
45:09And uh as soon as we get uh farther far
45:12enough along with the uh steel erection,
45:15uh which will be in approximately 3 to 4
45:19weeks, we're going to uh move to that
45:23area and uh go ahead and put in the um
45:28the final section of wall.
45:32Um
45:33you can also see that and there'll be a
45:35a better view of this in a minute, but
45:37uh
45:38uh just to reiterate, this
45:40[clears throat] tallest tallest section
45:42to the right is the what we call
45:44building E.
45:46That is the
45:48where the auditorium will be.
45:50In the background uh is the gymnasium.
45:55Uh let me see if I can just zoom in a
45:58little bit better here for everybody.
46:00This is a little bit better to see.
46:03Um
46:05So, again, the gymnasium uh is behind
46:07building E in this in this picture. Uh
46:10you have building G
46:12uh which is basically going to be
46:14eventually the courtyard area.
46:16Um
46:17And then uh build the first section of
46:21the front uh classrooms of the building,
46:24which is building A, and we've we've
46:27erected that up to the
46:29to the uh roof at this point.
46:32I'm going to um go back to
46:36full view here. And uh then I'm going to
46:39scroll down. Uh we've Logistical's, but
46:42we we've got temp power established.
46:44This is kind of an important one for us
46:46so that we can move forward with the
46:48rest of uh construction in a more
46:51efficient manner and not work off of uh
46:53generators for the rest of the job.
46:57Now, moving into uh the uh gymnasium.
47:01Um
47:02To try to pan down a little pan back a
47:06little bit and uh scroll down. Whoops.
47:09One second here. Just trying to maneuver
47:11this
47:12this little bit.
47:14Uh so, this is we we have we poured the
47:18gymnasium uh floor
47:21over the last week. So, this is the uh
47:23concrete floor that's been poured in the
47:25gym
47:27first level.
47:28Uh there's still uh another level that
47:31has to be poured in the gym uh
47:33between uh
47:35between the building F and building G.
47:38Um but that's a a nice shot of the
47:41progress of the gymnasium floor.
47:44Uh obviously, that floor is not an
47:46exposed concrete and it will be uh
47:49covered with uh sports floor uh
47:53um
47:54>> [clears throat]
47:54>> gymna- uh, gym floor
47:56uh
47:57finish floor system. Um,
48:00concrete slab placement, just another
48:02example of an area in the gymnasium
48:05where we're pouring uh, kind of a action
48:07shot, if you will, of the progress of
48:10making the pour where in the background
48:13you can see the concrete being poured in
48:14the foreground. The uh, area still uh,
48:17remains to be poured during that day.
48:20Um,
48:22another shot here. This is uh,
48:24This is the building G. Again, this is
48:27the what will be the courtyard and that
48:30that entire uh, concrete slab was poured
48:33slab on deck was poured as well. So,
48:35it's in place.
48:37Um,
48:40moving down into uh, the garage area.
48:43We've also started the spray
48:45fireproofing of the structural steel
48:47members
48:48uh, in the garage.
48:51Um, which is an important uh, part of
48:54what we have to do to get ready to pour
48:56the slab on grade
48:58uh, eventually in the garage.
49:02Um,
49:05another shot of the uh, formwork for
49:07just one of the stairs
49:09that is going to be uh, poured in the
49:12future here.
49:14Uh, this is at the first at the ground
49:16level going from the garage up to what
49:20will uh, up would be to the uh, first
49:22level.
49:23Just an example.
49:26Um,
49:27and this shot here, I'll try to zoom in
49:31a little bit better so everybody can
49:33see.
49:34Uh, this is just like we did last uh,
49:37month, kind of showing how the job is
49:41uh, progressed over the last month in
49:43terms of erection. So, um,
49:46last month
49:48uh, on the left-hand side you can see
49:50that uh, while the building F and
49:53building uh, E were are in the same
49:56situation now as they were then
49:59except for the slab pores. Building A
50:02had just kind of begun erection and as
50:06you can see on the left-hand side of
50:08that picture there's there's no steel on
50:11top of the foundation.
50:13If you go to the
50:15let me just
50:17try to
50:19I'm not
50:21losing effect here.
50:24So once again, no steel on this half of
50:28building A, but the other half of
50:29building A the steel is underway.
50:32All right, then you go to this month
50:36and this month's update and
50:39as you can see that the building A steel
50:43building A steel has all been erected up
50:46to the roof the roof line in this shot.
50:50The next
50:51the next outlook here is that we're
50:53starting to erect
50:56building
50:57building D.
50:59If I go back to the first page
51:04overall to give everybody kind of a
51:06better outlook on what
51:08building D is.
51:11Um
51:13So we have a we have a crane set up
51:16within the footprint here now and we are
51:18beginning to
51:20erect what what will be building D which
51:23is the cafeteria.
51:25Um so we're going to work on that over
51:28the next month as well as we're going to
51:31start getting back on to the erection of
51:36areas of building E that were incomplete
51:39due to the to to the foundation walls.
51:43I can answer questions on anything
51:45regarding that if you like after I'm
51:48through with the
51:49presentation here, but uh the plan is to
51:52work on uh building E
51:54as well as uh
51:55commence with building C. We're going to
51:59start erecting building C. Um so, one
52:02crane will move over into building C,
52:05the other crane will work in D, uh and
52:08then one of those two
52:11who uh whichever one's first ends up
52:13going uh and retreating to the rear to
52:16uh finish up the remainder of building
52:18E.
52:20>> [snorts]
52:21>> Um and then
52:23before I leave this, Dr. Kelly,
52:26regarding your question on the uh CM
52:29contingency,
52:32um
52:33that is
52:36if uh if the if everybody will remember,
52:39we
52:40uh
52:41we procured the site, the concrete, and
52:44the steel
52:46uh last year, about this time actually.
52:50Um they were early procurement packages.
52:52The contract documents were not 100%
52:56complete um at the time because of uh
53:00the projected GMP completion, which uh
53:03of the of the contract documents, which
53:05occurred in uh December of last year.
53:09So,
53:11following the completion of the contract
53:13documents,
53:14a reconciliation of scope with some
53:18things that that materialized that
53:21affected uh site,
53:24uh concrete, and steel uh were
53:27reconciled, and that 70,000 is just kind
53:31of a
53:32uh
53:32one of
53:34a few of the first
53:37change orders, if you will, but they're
53:39not change orders, they're just
53:40contingency uh
53:42everything is being applied to the
53:44contingency. So, what you're seeing is a
53:46net result of us um
53:50of us uh
53:52putting that money or uh uh
53:55billing that uh contingency for those
53:58changes to reconcile those scopes.
54:03>> Am I correct in interpreting that as uh
54:06it came in about 70,000 less than what
54:08we anticipate?
54:12>> Yes, in fact, yeah, that's that's the
54:14net result of that particular one, but
54:17but be careful because we're we're not
54:19entirely done with that process yet. I
54:21mean, this is just the four first foray
54:24into a few others that still have to be
54:27uh that the design team, the
54:29construction team, the the the OPM, and
54:33the design team have to still uh
54:36uh complete uh their the process of
54:39approval.
54:41So,
54:42it's not 100% done yet.
54:46>> Understood. Thank you.
54:50>> Okay, that
54:51that kind of uh
54:55I guess uh finalizes my uh presentation.
54:58Is there any Are there any questions?
55:04>> Uh I don't see any hands, Darren, and um
55:10if anyone's
55:12thinking of questions, I'll just say
55:13right now, we haven't finalized any
55:15days, and and Darren, correct me if I'm
55:17wrong here, but
55:19we are shooting for um
55:22somewhere in the early to mid-December
55:24to do a steel topping off ceremony, and
55:27we're working out logistics to have a
55:29beam on site that can uh we'll have
55:33we'll call them visiting hours uh for
55:35people to come and sign the beam, and
55:36then there'll be a ceremony. We wanted
55:38to give you guys a heads up. Um it won't
55:41We'll have our November meeting, so
55:42we'll be able to definitively tell you
55:45before then. But um if you have anything
55:48to add, Darren, on just uh it's one of
55:50the things we wanted to give the
55:51committee a heads up that's coming.
55:53We're not quite there yet. It'll be in
55:54there in December and we'll have it
55:56worked out in the next week or two. Um
55:58but
55:59just wanted to throw it out there.
56:02>> Correct. We're just We're working with
56:03Dr. Kelly on making arrangements to get
56:06the beam uh signed.
56:09The uh beam's going to be delivered in
56:11the next uh couple of weeks.
56:13And then uh
56:15we're working with Dr. Kelly to um
56:18make arrangements with uh
56:20those folks uh
56:22with the city, the school that want to
56:24um
56:25be a part of that signing.
56:27>> And I think uh just for clarity that we
56:30were looking at doing any kind of
56:32signing a little bit earlier, like maybe
56:34the week before Thanksgiving, just to
56:36have that finished and completed and we
56:39can take pictures of it and all of that.
56:41And then um as Brian and Darren
56:43indicated, the actual topping off
56:46ceremony is probably mid- December, when
56:50um folks can actually come and watch
56:52that final beam be lifted on the top of
56:54the building.
56:57>> Brian, Don Seramella has his hand up.
57:01>> Yep.
57:03>> I I just have a question and in
57:05comparing this building with some of our
57:08other schools that we have, um
57:13something that I know nothing about, and
57:15that's the courtyard and how that works.
57:17And this is probably not a question for
57:19this meeting,
57:21but
57:22um what are some of the details so that
57:24this
57:25courtyard doesn't become a maintenance
57:28problem as far as, you know,
57:31um
57:32I I know I when I was looking at some of
57:34the pictures that Darren was displaying,
57:36uh looking at some of the reinforcing
57:38rod that's used in a lot of the
57:40applications that's you know, it's
57:42uncoated. It's not epoxy coated.
57:45And I was just wondering if that if that
57:48theme can
57:49ran through the whole project as far as
57:51the the deck for the courtyard.
57:54Um
57:55you know, we learn by some of our
57:57mistakes and some of the old schools and
57:59you know, Dr. Kelly is is tasked with
58:01some of the problems many of the
58:03problems that some of the existing
58:04schools have
58:05and
58:06um
58:07I was just kind of curious. What are
58:08some of the details as far as the deck
58:11is concerned so it doesn't become a
58:12maintenance problem as far as
58:14waterproofing and application to the
58:16steel. Was the epoxy coated rebar used
58:18in the in in embedded in that concrete?
58:21Um so it doesn't rust or spald the
58:24concrete. Just curious. I mean, it's
58:26done in I'm just kind of curious.
58:30>> Um so I'll I'll I'll defer I'll defer
58:33I'll defer
58:34>> to Dan on any specifics, but I would
58:37just say I would offer that the design
58:40team has required that the concrete uh
58:44that's being poured have um corrosion
58:47inhibitors additives as part of the
58:50concrete mix design. So even and so
58:53there's some concrete areas that do not
58:57have epoxy, but all the concrete has a
59:00corrosion inhibitors.
59:02Uh but there are some areas of concrete.
59:05So for instance, that that one uh view
59:08that you saw, that was
59:10um
59:11it's it's in the basement, so it's under
59:14the building, okay? It's not outside.
59:17But um but like [clears throat] I said,
59:20the concrete has uh corro- corrosion
59:23inhibitor admixtures in the concrete.
59:26When you get outside the building,
59:29like for let's say
59:31retaining walls and exposed concrete
59:34areas,
59:35that concrete
59:36it does have epoxy coating on it. That
59:40I'm sorry, the rebar has epoxy coating
59:42on it.
59:45>> That probably makes the most sense to
59:47share the details with you.
59:49>> So but the
59:51>> I'll certainly send them to you.
59:53>> The rebar that was used in the deck for
59:55the courtyard was
59:58bare steel?
1:00:01>> It is not epoxy, no.
1:00:04>> Okay.
1:00:05>> There are other waterproofing agents
1:00:07that are being will be employed that to
1:00:10Dan's point,
1:00:12that that those details can be relayed
1:00:15to explain how
1:00:17the the green deck, if you will, which
1:00:20is this is a green roof basically, how
1:00:23that green roof system works.
1:00:26>> There's a substantial build-up above
1:00:27that deck.
1:00:29>> Yes.
1:00:29>> Okay. So where are the
1:00:31>> That's that's you're not walking on
1:00:33that.
1:00:33>> Yeah, where it is where we're at at a
1:00:35pivotal point with that deck where
1:00:38all the necessary
1:00:40precautions have to be taken so that
1:00:43you know, that deck doesn't deteriorate
1:00:46ahead of its time.
1:00:48>> That deck is thoroughly protected by
1:00:51many layers. That's why I think it's
1:00:53best if I send you the details and
1:00:55you can take a look at how this is
1:00:56really built up.
1:00:57>> Like I said, I know nothing about them.
1:01:00Thank you.
1:01:02>> John, we'll follow up. We can at least
1:01:03walk you through some of the design
1:01:04measures
1:01:05um
1:01:06to protect against what you're
1:01:08what you're justifiably concerned about.
1:01:11>> Thank you.
1:01:16>> Uh any other questions for Darren or
1:01:18about construction progress?
1:01:23>> It looks great.
1:01:27>> I was actually going to say I just
1:01:28looked back. This was a
1:01:30$4 million steel month and I think from
1:01:32those
1:01:33um
1:01:34to put it into numbers, to put it into
1:01:35dollars, from those pictures Darren had
1:01:37left and right.
1:01:39Um that's that's what $4 million worth
1:01:41of steel looks like and I will be
1:01:43we'll be right up around there for the
1:01:44next
1:01:452 months probably.
1:01:48>> And I'll just add that um
1:01:50Dave from Consigli sent us a link to a
1:01:53drone fly through of the
1:01:57it building as it exists right now and
1:01:58that's going to be going up on the
1:02:01new building website if anybody wants to
1:02:02take a look at that. I don't know Linda
1:02:04if it's gone up yet. You can maybe let
1:02:06us know when that's going to
1:02:07>> Yep, I'll get it up tomorrow morning.
1:02:11>> I was thinking of throwing that on the
1:02:12screen, but I think it would crush our
1:02:15throughput of connectivity here and
1:02:17probably crash our Zoom. So we'll get I
1:02:19can circulate that link and we'll get it
1:02:20on the website.
1:02:26After no other questions or comments, we
1:02:28will move to agenda item seven, public
1:02:30comments. Let me just just first check
1:02:31the committee. We good to move to public
1:02:33comment?
1:02:37Looks like uh yes.
1:02:39Um if anyone
1:02:42out in the public is on the meeting, you
1:02:44will have to raise your hand.
1:02:47>> We only have
1:02:48uh
1:02:50one person in as an attendee, which is
1:02:53Bob Bell. So
1:02:55no public attendees today.
1:02:57>> Bob Bell
1:02:58is a Perkins Eastman employee for any of
1:03:00those of you who forget. So uh
1:03:02>> Yes, Bob. I did invite him.
1:03:05>> [laughter]
1:03:05>> I did invite him to be a panelist if he
1:03:08wanted to say something, but he rejected
1:03:09it. So
1:03:11>> [laughter]
1:03:11>> I think he's more comfortable in the
1:03:14in the waiting room, I guess.
1:03:17>> Sounds good. We'll just do a for the
1:03:19record going twice public comment seeing
1:03:21none. We would entertain a motion to
1:03:24actually is there any other new business
1:03:25or other business from the committee
1:03:27agenda item eight.
1:03:33Seeing none. We would entertain a motion
1:03:37to adjourn.
1:03:39>> Motion to adjourn.
1:03:42>> Thanks everybody.
1:03:44>> Thank you.
1:03:44>> Thank you everybody.
1:03:46>> Thank you everyone.
1:03:53>> Recording stopped.