2026-10-22 - School Committee
Summary
- Minutes of the prior meeting approved 4-0 (a fifth member was not heard voting).
- Roof projects: signed notices of substantial completion are in for both the Jr./Sr. High School and Elmwood Street School projects, and contractors are working through punch lists and testing and balancing the new rooftop units. Some leaks appeared in a heavy rainstorm (poorly welded seams and a slipped pipe clamp) and were fixed quickly. A 30-year manufacturer warranty began Oct. 2 and Oct. 5 at the two sites, plus a one-year contractor warranty. The district paid extra for 30 years because the 2001 roof had only a 20-year warranty and leaked outside warranty. Staff are in manufacturer training on rooftop units and the building management system, and maintenance schedules will be loaded into the district's maintenance platform.
- Band equipment shed (donation): the committee voted 4-0 to accept a donation of materials and labor for a 12 by 20 foot shed to store marching band equipment, sited between the business office and the junior high within camera view. It comes at no cost to the district from a local lumber supplier and volunteers, with insurance certificates and professional installation required. The committee asked for a thank-you letter.
- Solar project: panel racking at Elmwood Street School was expected to finish the next day, ahead of schedule, with the crew then moving to the high school. Interconnection work with National Grid continues; officials said the grid utility has been cooperative and the arrays are small enough that they likely would not export power at peak.
- High school gym: the gym reopened for play after the floor project, with a senior night volleyball game and a unified basketball game already held, and gym classes and teams back in use. Some work remains.
- Policies: the second reading of the graduation ceremony policy (IKFB) was tabled until a member who wants changes can attend. Policies KHB and KHBA (use of facilities and signage, cross-referenced) were each approved 4-0; they address election-day signage at the school, which is a voting location, with the town clerk coordinating sign placement with the superintendent under state law.
- Surplus bleachers: the committee voted 4-0 to declare leftover bleacher parts from the old athletic facility surplus. The district reassembled four sets of bleachers for the tennis, pickleball and softball areas; the nature trails committee may take aluminum planks for trail bridges, and the rest will be scrapped.
- No executive session; adjourned 4-0.
- Board roster per the town's website (membership, not attendance): Christopher Wilbur (Chair), Jessica Bristol (Vice Chair), Kristen Birch (Member), Mike Taber (Member), Christine A. Pugliese Savage (Member).
Agenda
Agenda PDF posted; see Sources. Topics taken from the video.
Sources
- Video captions (uploaded, manual)
- Agenda: https://www.millburyma.gov/AgendaCenter/ViewFile/Agenda/_10222026-809
- Agenda Center: https://www.millburyma.gov/agendacenter
Video
Video: Millbury Public Access YouTube channel.
Transcript
Machine-readable captions uploaded by the channel; they may contain errors, especially names and numbers.
Transcript
This is a good evening everybody and welcome to the October 22nd school committee meeting. If you could stand and join me with the pledge of allegiance. I pledge allegiance to the flag of the
United States of America and to the republic for which it stands, one nation under God, indivisible, with liberty and justice for all. We'll start with the review and approval of the meeting
minutes. If I could have a motion to approve, I'll make that motion. I'll second. All those in favor? I. That's 4-0 Uh we are going to jump around a little bit on the agenda. Uh and we're going
to jump down to the unfinished business. Mr. Mara. Thank you, Mr. Chairman. Um [clears throat] just again a weekly or a bi-weekly update on the roof project. I just wanted to inform the
committee that we do have signed notices of substantial completion for both projects. Uh and we are working towards final completion. As you can see or or maybe tell throughout the sites, the
number of contractors and some of the footprint that the contractors uh had uh both in the front lot of the junior high as well as the basketball court at Elmwood is starting to dissipate. Uh
there's less material on site and most contractors are working on their punch list stuff which is just the end of the project. Uh we have both our project management team as well as our
architectural team um look over all the drawings, look at the work on the site and they just highlight little areas in which there might need to be some improvement, just might need to uh tie up
some of those loose ends to make sure that what is on the contracted documents is what is produced on the roof for us. So we're excited to say that that process is ongoing. We are looking at
final completion uh in a somewhat of a a expedited time frame here within uh where we're looking and um also working in the solar component. But the the Elmwood Street School roof project is
certainly uh trending towards final completion soon. Again, now we're really just working on the controls, the BMS system to be able to make sure that we can actually control the new units that
are on the on the roof. So, how you control them with the computer to make sure that they're producing the right temperature. Uh, that's the process we're in now. It's called testing and
balancing. And we'll be doing that as we walk through the rest of the project here. Um, and as the trades finish up their punch list, our project management team as well as the design team will
be coming back out to what's called back punch to make sure that those punch list items that they said have been addressed. So, we're in the the final stages here of the roof project. We're
really excited. We've opened up the front lot. Um the contractors have crack sealed uh where they've kind of damaged some of the areas. They've done some seating and top dressing to some of the
disturbed areas. So, we're excited to to see them uh dissipating a little bit. Um we've enjoyed having them here, but we'll we'll certainly uh enjoy um when they're gone as well. So, uh, excited
to share that the the projects are, uh, full steam ahead and and we're getting towards the end here. Um, and just wanted to provide an update. Any, uh, any questions on this? No. Uh, I know
last Friday was quite a rainstorm. Um, any issues, any anything that uh, popped through and has been taken care of or Yeah, that great point. Um we've been lucky that we've had a couple of
deluges Um luckily it was it during halftime of the football game so we were able to kind of utilize that a little bit Friday night. Um there were some areas that water some intrusion was
happening. Um a couple of uh pipe clamps. Um, and I'm not too certain about some of the terms, but uh really happy with our project management team as well as our site uh Col Antonio
representative Ryan and our site um contractor Bryce. They look as soon as they observe a leak or as soon as our custodial team and Naomi Cormier says, "Hey, it's it's leaking in this area."
They go right there. They figure out a problem. Most of it is seams within the roof. um they have to weld the seams together and sometimes that weld isn't perfect. Um so they they have to reweld
that area. Sometimes in in uh two cases here at the high school there was a clamp that had slid down during installation needed to be raised up, tightened and caulked around that um that clamp
uh to seal that a little bit better. So yes, there was some intrusion, but it is definitely less and less each rainstorm in those situations in which there's a ton of water in a short amount of
time. Really tell you where you're vulnerable. So we we're actually happy to to have that experience so that we can kind of go back and make sure that what we have is acceptable and is also
working the correct way. Yeah. especially while they're still here. The timing was definitely very good. Yeah. Any other questions on the roof? Um I have one. Is there a uh I wouldn't call it a
maintenance schedule, but like a periodic check over like the next 3, 6, 12 months or something like that just to make sure that we're staying on top of those things because obviously like if
water starts to get in someplace and nobody notices like it could get a lot worse. But um you know it sounds like there are some minor issues here and there which kind of be expected in a big
project. Uh but are we just is there something on the calendar somewhere that like we're going to send somebody to go look? So that's a great question. Um so we own a one-year warranty from
final completion date uh for the contractor. So any issues that come up within the first calendar year from final completion to for that entire calendar year we call our owners project manager.
They call Antonio company here, gauge company at um Elmwood Street School, and they come back, they work with the vendors, and they make sure that that is is tightened up. Um our 30-year
warranty began on the day of substantial completion for the roof, which was October 2nd and October 5th at each site, respectively. So that 30 years begins on that date. We are insured to have
that warranty for the next 30 years based on those dates. So even after the full year of I guess more targeted um you know call back, we still have the opportunity to call the vendor um and to
go through the Sarnophil which is the type of um roof that we have that warranty. We go through that company and they come out and fix it and they do their service agreement for that. So the
fact that we were able to go for a 30-year warranty and we paid a little extra for that extra 10 years because what we found ourselves The situation we found ourselves in was the roof was put on
in 2001. It was 2025 or 26 and we were experiencing a lot of water, but we only had a 20-year warranty. So, we were outside of warranty work, but we were short of MSBA or any sort of fiscal
assistance from whether it be the state or the government. Um, so we tried to extend that warranty this time to 30 years so that we could make sure that we would stay within the useful life of
the roof and have that happen a little bit um in a longer stretch. So hope that answers your question. Um I mean it answers about the warranty but it was more about like somebody checking it
regularly over the next sure 12 months. Yep. Absolutely. Um sorry. So that's okay to uh yeah there's so many yeah there's different components of it and I think the good part is we get um so we
have we just finished day one of our training from the manufacturer and from the contractor to tell us how to do preventative maintenance both change the filters what to look for how you can
identify if there's an issue. Um so there's a day of training for some of the rooftop units another day of training um for the second day of the rooftop units. There's also four days of training
for the BMS system. So, we actually go into a room for 4 days and we talk exactly about what the envelope is, what we have to look for, what the computer is going to tell us, and then how we can
make sure we manage the devices, what [snorts] to to look for, and like our maintenance team and our custodial staff, as well as, you know, the 900 people we have in this building and then the,
you know, 550 people we have at Elmwood, they're pretty good at telling us if something's a miss. um they're in a lot of spaces. It's a very used facility. So, usually we get the information as
to whether or not there there might be a leak or a ceiling tile that looks discolored or something like that. But again, with the training that we've received for the units, the preventative
maintenance schedule, we actually bring our vendor Renad into those trainings. So, they come and sit with us so that when they come out to the site, when we call them, um based on our HVAC
contract, they know what type of units they are. they've been through the training themselves. They're not walking up there and saying, "Oh, I I haven't seen this unit before." [snorts] So, I
think we have a lot of fail safes in place um throughout the project. We also get a full closeout document set um both printed and electronic of all the asbuilds, all the owner's manuals, all
the um PM schedules, what should be in there. And we're going to use that information to populate our um operations hero platform, which is a local platform that we use to make sure that we do
remember to change the filters or the um you know things on the roof or things in the the bubblers or anything like that. And we'll be able to populate that so we can do that more consistently
uh throughout the life of the the project so we can maintain the the the long useful life of these units. And so we're definitely thinking about that and also trying to learn the new units
because they're different brands. Um, you know, some filters are in different spots, some turnoffs or shut offs are in different areas. So, you kind of have to [clears throat] get a lay of the
land first. Um, but certainly we'll always be very cognizant of those because those are really what make us run uh to a certain extent. Thank you. Yeah, no problem. Uh if if no one has any
objection, I'm going to jump back to finance and operations. Uh that way Mr. Dooley doesn't have to sit here and hear about roofs and things. Uh [laughter] but uh Mr. Mara, if you want to walk
us through the finance and operations section. Thank you, Mr. Chairman. Um so tonight I I have um Mr. Dooley here. I have a special guest. Uh Mr. Dooley is a our music teacher here at the the
school. uh our band director, a former mentee, um and a colleague that matters a lot to our school and facility. And he's done a remarkable job in in coordinating with some um very generous
folks to be able to help us out with a a need that his program has. And he just has a couple of slides just to talk about that need. Uh talk about what he's um come up with and and ask for your
support uh to accept that donation. Um so I'll let Mr. Dooley kind of outline that for you and then we can answer any questions. You could also um Oh, to I [snorts] know if I talk you have you
have the voice for Yeah, you can. Uh anyway, uh so yes, I'm here to propose uh and ask for your acceptance of a donation for materials and labor to build a shed. Um, and this shed is uh sorely
needed for a bunch of marching band equipment that is non uh weather damageable, meaning it's not instruments. It's not uniform pieces. It's things that are made of metal um or pressuret treated
wood that's been painted um and can live in a nonclimatec controlled area. Uh right now all of this stuff it consists of uh backdrop bases, frames, metal podiums and ladders and stage platforms
and all this stuff that we use for the marching band program is housed in a numerous uh list of places including under the bleachers where it's not getting protected from rain um consistently in
the hallways. Um, if you walk that way, you see all the stuff in the hallways, uh, in various storage rooms, in the robotics rooms, making custodial lives difficult, making student lives
difficult every time they have to bring everything all the way out and around for um, rehearsals every day to the field. So, we've been working on ways to get a shed that can live outside where
all this stuff can just go from there to the field and back without as much wear and tear on the floor building and the floor of the building hitting walls accidentally as careful as kids try to
steer things. Um, less wear and tear on equipment when it's not going all over the place. So, uh, here we go. So, this [clears throat] is what it'll look like. Um, it these are professionally
done drawings. I have all the schematics and things that I've shared in a meeting with Naomi Cormier, the facilities director. Uh Mr. Mara was there as well. Um and we looked at all of that. Uh
so it will be a 12 x 20 shed. It'll have a garage door opening there which you can see on the bottom. Um it will have no windows. Uh it will probably have another door put in on the side in the
back. So there's a second egress point. The garage door, it won't be sorry, not a garage door. It looks like a garage door. It'll be like shed doors like this. Um it will have a ramp as well
that will be removable so there's no issues with snow removal, plowing, etc. not causing uh traffic blocking. Um if you go to the next slide, you can see that it's it's legit, right? Um this is
kind of being spearheaded by a parent we have who works at Coupeman's Lumber. Um and she's not only does she work there in a managerial capacity, but she's very knowledgeable in the design and
the schematics. And so all of this, she's done all this design work. Um it's all of course up to code and everything as you would want it. Um and then this is the location. So, we had a few
different locations that we looked at. Uh, one was way back by where Orchard Street lot kind of used to be. One was by the softball field. And for a number of reasons, including including
plowing, logistics, uh, being out of the way of things, aesthetics, you know, um, this was the one that was chosen. So, it's kind of right beside the between the business office and the junior
high. You can see um, where the little star is over there. That's the top down view. And you can see there's a spot right there where that cone is. It can just slide right in. Um the other thing
was maybe that trailer would move and the shed would go closer to the building. Of course, maintaining spacing away from the building for egress from the windows, repairs for the shed,
everything like that. Um, and the great news about this is that this will do a lot of things, including eliminate hallway and storage room clutter in the building, better protect the equipment
for longevity for marching band, so it's not going in and out, tons of miles, through doors, over hills. Um, and the whole shed and materials and labor are at no cost to the district or band
program. It's all will be donated materials and labor by people at Coupeman's and their various connector people. So, Does anybody have any questions? What color is it going to be painted?
Whatever color you want it to be. Well, [laughter] I have a reference. It's actually It's going to be um I don't think it's a painting. I think the siding is I don't remember what the technical
term is. Sorry. But maybe maroon. Maybe we'll put a little M on it. Go Woollies. Right. I think maybe you could have like the um maybe the senior class like put something on the side of it or
something like that. I don't know. Yeah, we can definitely we'll definitely make it look uh nice. So, that'll be the plan. Any other questions? I'm assuming our camera system is good enough in
the back to keep an eye on. Definitely that I think that was one of the reasons uh through the chair that um we we picked that location. Just it's a it's a location that currently our our mini
yellow bus, Mr. Swinson's buses parked there. We've talked to him about some different locations about where to park that vehicle. Uh we feel like that's both close enough. It it makes sense in
terms of of loading up for the shows. You know, the the trucks that Mr. Dooley and the the band uses for the shows can't go under the catwalk. So, we needed it to be both close to the field,
close to the catwalk, um and really kind of make sure that it was within sight of our cameras. Um, and I know that this I think will will substantially help the loading process uh for some of
those competitions which you have one coming up which you could publicly promote if you desired at this time. Saturday in Wakefield. I'm sure nobody will make that drive. That's fine. [laughter]
So the chair I have a question. So, um, the donation of materials and labor that's coming from Coupeman Lumber, are they the ones that are installing the whole thing or are you getting like
family volunteers as well? Um, so there will be a couple of parent and family volunteers who are knowledgeable about this thing. The parent who's coordinating it also has a team of people who
work at Coupeman's um who are going to be uh coming to assist with it. Um, and she did assure me that um insurance certificates will be present and everything. That was my next question. Yep.
Yeah. the the first thing that um Miss Cormier and I spoke about was just to make sure that we have COIs and we make sure that we move forward with um you know professional installation so that
we know what we're getting um on site and you know that with the drawings and also the conversations that Mr. Douly has had is it's it's been very apparent to us that it will be done in a
professional way. uh and that was very important to us and also we're very appreciative of that because it will maintain the test of time um because of the materials that they're using which
are very quality materials uh as well as the professional installation. Excellent. Please thank that um family member for all her work. Bring that. Any other uh could I have a motion to accept
the donation from Coupeman Lender Lumber? I'll make that motion. I'll second. All those in favor? I um could we send a letter to Coupeman thanking them for this and uh Mr. Douly as always, thank
you for uh growing the the uh band uh to what it is today cuz I remember many many years ago uh what the band at Milbury was and it was nowhere close to uh the program that you are running
today. So I want to thank you personally for that u because it's a very important uh activity for our kids and and you can see just by the number of kids who are are attending your your program.
So thank you. Thank you. I appreciate it. It's been my pleasure. I've enjoyed every minute of it. Go Owls. Go [laughter] Owls. Stop it. I know, but we're Woolies right now. [laughter] Thank you,
Mr. Dooley. Thank you. Thank you. Yes. All right. We'll slide right back down into the unfinished business. Uh Mr. Mara. Sure. Thank you, Mr. Mr. Chairman, uh just wanted to briefly update the
committee on the timeline for the solar project. Uh we spoke about the roof project, how that's uh kind of wrapping up. That means the solar project is ramping up. Um really can't tell you how
pleased we are with certified safe electric. Uh they'll actually be done racking Elmwood Street School by tomorrow. Uh is what's happening, which is ahead of schedule. Uh they're flying. um they
have to do some electrical work and some some tie-ins and things like that, but the actual placing of the um panels up at the Elmwood Street School could be done as early as tomorrow. Uh which
is really remarkable to think as we're kind of finishing up the the roof project, having that project already kind of being kicked into gear. Uh that delayed a little bit at the high school
because they wanted to focus on Elmwood and then once they're done the racking there, they'll move their team over to the high school to begin the racking there. And then they'll have their
electricians begin the interconnection process uh to make sure that it's up and running so that it can both be um observed by the uh folks you know terms of the permitting but also for national
grid uh with the interconnection agreement um which we are working through as well. So I agree. So we're only two two years away from getting that. I think Mr. Myers was um yeah, put the
infinity symbol there for for a reason, I think. So, um [laughter] we'll certainly continue to work with them. I will say uh we've had really good movement with National Grid and we've we've
appreciated their desire to help us. Um, again, as I spoke about a couple of meetings ago, LPC light is a a smaller array that most likely even in peak um minimal demand and peak production
would not send power back to the grid. National Grid is trying to find a niche area for those so that they don't get lumped into big studies of solar farms or battery farms or things like that.
So, we're they are really trying to work with us. we feel like they're not only working with our vendor, Certified Safe Electric, but also our um design team, um Chris White. So, we've really
felt like they're working with us here, um and are very hopeful that our experience this time with National Grid and with turning the solar on and the interconnection agreement [snorts] will be
more palatable for the district and for the town. Any questions on the solar? No. Right. Uh the high school gym. Yes, Mr. Chairman. Thank you. Um very excited to uh potentially take this one off
the docket here. Um really excited to say that we've opened the gymnasium for for play. The contractors [snorts] removed uh the equipment on Monday. We were able to play our senior night
volleyball game on Monday evening. Uh yet just yesterday we played our unified basketball game at home uh on the new floor. So just wanted to to publicly thank um our our teachers, our students,
just for the patience, the community for the patience during the the project. Uh really excited that it's it's open for business now and back to normal to a certain extent. um can't say how nice
it was to to see a freshly clean gym with a nice bright floor and you know um some of our our unified students you know hooping it up last night. So it's just it's remarkable. Um you know we
couldn't have done it without our project management team as well as the um you know New England sports floors. Uh you know they really really worked with us to to make sure that this timeline
was as truncated as possible done well. um with good craftsmanship and and we're really pleased with the outcome and and are still have some work to do in there. There's no doubt. But um in
terms of a playable safe surface, we have that now. And you know, the the damage of the summer uh is is not in our memory anymore. We'll-we'll-we'll take this picture uh to our um in our
memories now. So excited to say that we're we're back up and running. Our gym classes are back into using the facility. there may be some, you know, some changes, a little bit of um, you know,
just trying to make sure that some of the equipment that's used in there for whether it's volleyball stands or um, you know, I know floor hockey is a big winter carnival activity, right? We just
want to make sure that we're both adhering to the tradition of our of our school, but also making sure that the floor uh can continue to evolve um, you know, as as we begin here. So, I think
we'll continue to work uh in that space, but now the the gym classes are back in there. Our teams are practicing uh and the hustle and bustle has picked up like it never left. So, excited to say
that we're back up and running and um couldn't be more pleased. Great. Any questions? No. No. That's good news. Uh let's move on to um some policies that we're going to review. Uh, I'm going to
ask that we table policy IKFB, uh, the graduation ceremony policy for the second reading until, uh, Tina can be with us. Uh, because I know that she had some, um, strong ideas of how that should
change. So, I'm going to table that one. Um, but Mr. Taber, if you could walk us through uh, policy KHB and KHBA. Yeah. Um so both of these policies are uh related to one another and uh if you
look at the changes to them uh they do cross reference to one another and that was added specifically because they are so much related uh there's language in there that uh bridges back and forth
between the two and it's identical and we wanted to make sure that in the future when other people are reviewing the policy that if there are changes being made to one of them that those are not
overlooked in the policy uh in the other policy. Um the main reason this comes about is because of um the fact that the school is used as a uh voting location. And so in the past there um it's
been sort of a tacid agreements to uh from the town clerk to allow people to put up uh signage while the uh voting is going on. And um it's not necessarily spelled out in the policy. In fact,
it's actually said that you can't do that. So, the some of this policy is being changed specifically to address that. Um, and then for the signage, it also relates to that. And, um, the town
clerk's going to coordinate with the superintendent of schools to make sure that, uh, everything is going that all the placement of the signs and the locations of them are acceptable and, uh,
legal according to state law. Any any questions? No. No. Uh, could I have a motion to uh accept policy KHB? I'll make that motion. I'll second. All those in favor? That's 4-0 And uh could I have
a motion to approve KHBA? I'll make that motion. I'll second. All those in favor? I. Thank you, Mr. Taber. That was 4-0 as well. I believe that closes out our um unfinished business. Uh moving
on to new business. Uh Mr. Mara. Yes. Thank you, Mr. Chairman. Uh tonight we're requesting uh the committee consider declaring surplus some bleacher parts uh from the old athletic facility. Uh
something near and dear to my heart. So um before we updated the athletic facility, we purchased new bleachers a few years before that renovation began. Uh at that time we did not want to
dispose of the bleachers during that project. So we actually dis uh disassembled them, put them into a container at the Elmwood Street School and uh there it has sat uh for a few years now. Uh
so recently, Miss Cormier has made it her mission to make sure we get these uh back into service, back into some of the locations, including the tennis and pickle ball court, our softball um
field, and put some more bleachers and more uh seating for some of our athletic events out into uh into service. So happy to say that Gallivan Company um out of Foxboro, Massachusetts came in,
assessed all of the parts that we had, told us what we had um and then erected four different sets of bleachers ranging from five rows to or seven rows to three rows um and which we are going to
put out into our athletic facilities. that did leave some leftover materials uh in which we do not have the capacity or the space to be able to continue those to be in service. Uh so today we'd
we'd ask that the committee uh declare those surplus. Uh just as a side note, uh we have uh spoken with Bruce Devault uh of the nature trails committee and he actually is interested in using
some of the plank uh where you put your feet and and sometimes where you sit uh for some what he called a a boy scout bridge in some of his trails. Uh some of the aluminum actually would would
wear pretty well on his trails in some of the local um the local walking trails that he has with his committee. So, uh, with your permission tonight, we'd like to offer Mr. Devault an
opportunity to take some of those planks for him and then Miss Cormier will, um, we'll dispose of and scrap the rest, uh, for the district's benefit. So, uh, that's the plan. I spoke with Mr.
Mr. Devault this morning, um, and he seemed excited about using some of that material and and being able to enhance some of the trails that were there, especially in some muddy um, spots, some
low spots of some of those trails. So if that's okay with the committee, um we'd like to offer offer Mr. Devault to be able to do that so that after he kind of picks through what he and him and
his committee might need, uh then we'll take care of the rest. Great. Any questions? I have a motion to uh declare uh surplus the bleacher parts. I'll make that motion. I'll second. All those in
favor? I. It's 4-0. Thank you. Um, if anybody else has any other new business uh for future meetings, uh, we can bring them up now. Hearing none. Uh, we don't need to go into executive session
tonight. So, could I have a motion to adjourn? I'll make that motion. I'll second. All those in favor? I 4-0. Thank you everybody. Thank you.