FY2027-2030 Strategic Plan

At a glance

Based on auto-generated captions; names and numbers may be misheard.

  • What: a multi-year City of Topeka strategic plan being developed with the University of Kansas Public Management Center, which also produced the 2023-2027 plan.
  • Where it stands: work plan presented to the Governing Body on 2026-10-13; interviews start in November 2026.
  • Next: adoption by the council is targeted for early March 2027.

Process

  • Phase 1: project start-up with the City Manager's team.
  • Phase 2: virtual interviews with each governing body member and executive staff in November and December, then a one-day work session with the governing body and one with leadership staff in January.
  • Phase 3: written plan and a half-day governing body discussion in February (dates to be set), including how progress will be tracked.
  • Phase 4: adoption in early March 2027, with Word and PDF versions, a summary handout and presentation materials.
  • Separate from the annual goals in FY2027 Strategic Goals.

People

  • Christy Northcut presented; Robert M. Perez introduced the item; Mayor Duncan asked members to respond to interview requests.

Sources

Discussion time

About 9 minutes across 1 meeting (from transcript timestamps; approximate).