10th Avenue Alley Sanitary Sewer Replacement

At a glance

  • What: Sanitary sewer replacement along the alley on 10th Avenue between Lafayette and Indiana, budget about $1.22 million.
  • Where it stands: Committee approved 3-0 on Oct 20, 2026.
  • Next: Easements finished around the end of November, construction in early spring 2027 for about 120 days.

Concerns

  • Councilmember Ortiz (her district) worried about residents' parking behind the strip park during work; staff will share a plan, hold a neighborhood meeting, and phase the work in three stages.
  • Staff said eminent domain was used for two easements and some residents have been hard to reach. The sewer line is failing and could back up.

Sources

Discussion time

About 6 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-20 - Public Infrastructure Committee 6