Fire Station 5 Replacement

At a glance

  • What: design of a replacement for Fire Station #5.
  • Where it stands: a consent item on the 2026-11-04 tentative agenda.
  • Next: Mayor and Commission consent action on 2026-11-04.

Details

  • Little detail was recorded in the documents read.

Sources

Log

2026-11-04 - Mayor and Commission

  • Schematic design approved unanimously on the consent agenda (per posted results).

2026-11-04 - Mayor and Commission

  • Consent item approved unanimously; additional SPLOST 2020 funding for the station approved on a separate vote.

2026-10-01 - Planning Commission

  • Planning Commission approved the rezoning of the 4730 Old Lexington Road site to government.

2026-11-04 - Mayor and Commission

  • Design on the consent agenda.

2026-11-02 - SPLOST and TSPLOST Oversight Committee

  • Committee heard that zoning and schematic design were on the November 4 agenda; neighbors' screening concerns led to added screening near the building. No plan yet for the extra land.

2026-10-20 - Mayor and Commission Agenda Setting Session

  • Schematic design discussed: one-story, low profile, funded by about $2.5 million of SPLOST 2020 interest, with fewer bays and no fueling station or community room. A commissioner had aesthetic reservations.