East Wind Route 100 Waterline Change Order

At a glance

  • What: a revised change order with J.A. McDonald for the water line extension down Route 100 (East Wind project).
  • Where it stands: on 2026-10-14 the commissioners authorized the District Manager to sign it at an estimated $516,700; one commissioner recused. Directional drilling was due to start 2026-10-19, about three weeks of work.
  • Next: progress of the Route 100 work.

Log

2026-09-09 - Edward Farrar Utility District

  • Commissioners authorized the manager to sign a change order with J.A. McDonald at an estimated $418,231, funded from leftover grant money; voice vote.

2026-10-14 - Edward Farrar Utility District

  • Change order authorized at an estimated $516,700 (original figure as heard: $418,231); passed by voice vote with one recusal.