Splash Pad Renovation Contract

At a glance

  • What: a contract with Archon Builders (calendar item B4) to renovate six splash pads, relocate the Washington Park pad and add one new pad in Belmont Park, about $3.4 million of ARPA funds.
  • Where it stands: highlighted on the September 30, 2026 calendar. The first bid came in about $2 million over budget; the rebid was not under the project labor agreement and increased competition.
  • Next: the city manager is to resend the scoring criteria for the splash pad priority list after a commissioner asked why Nordale Park ranked about seventh.

Details

  • The Belmont site was the top recommendation in the parks master plan. The Washington Park pad is being moved so it is more visible and less exposed to vandalism; it is expected to be finished around the end of 2027.

Sources

  • YouTube auto-generated captions of the City Commission meeting of September 30, 2026.

Log

2026-09-30 - City Commission

  • City manager described the contract; the manager's recommendations were approved by voice vote.