What: A $549,902 change order on the Belmont pool and locker room renovation, raising the contract from $1.7 million to about $2.25 million.
Where it stands: Approved with the city manager's recommendations on September 9, 2026.
Next: Staff were asked for fuller background on the original assessment and contingency.
Details
Staff said demolition revealed far more corrosion of concrete and reinforcing steel than projected, so more was removed and the concrete treated to last, typically about 25 years.
A speaker asked what structural assessment preceded the original award and what contingency was budgeted.
Sources
Dayton City Commission 2026-09-09 minutes and YouTube auto-generated captions.
A speaker questioned the change order; a commissioner asked staff for context and the city manager's office explained the corrosion. Recommendations passed by voice vote.