What: Emergency ordinance 1430-2026 authorizes the Director of Finance and Management, for the Office of Construction Management, to contract with Elford, Inc. for Construction Manager at Risk (CMaR) services on the Department of Public Safety's Easton Police Substation project, spending up to $10,000,000 from the Safety G.O. Bonds Fund.
Vote (6/1/2026): Bankston / Barroso De Padilla; approved 9-0.
Where it stands: approved. The minutes record no debate and do not say whether the $10,000,000 is the full project cost.