Buckeye XO Enterprise Zone Amendments

At a glance

  • What: Four ordinances (2467-2026 Building 1D, 2468-2026 Building 1C, 2469-2026 Building 1B, 2470-2026 Building 1A) amending the Enterprise Zone Agreements with Buckeye XO LLC for the first time. Each was amended as submitted to the Clerk and then approved as amended.
  • Changes in each agreement: expected project start date moved from August 2022 to August 2026; expected completion of real property improvements moved from October 2023 to December 2027; the tax exemption period revised so that no exemption starts after 2028 or runs beyond 2037 (the original period was 2024 to 2033); the minimum wage threshold for city incentive eligibility raised from $15.00 to $20.00 per hour; the associated annual payroll for new employees raised from $904,000.00 to $1,206,400.00; and the legal description of the project site revised. The Building 1D ordinance also revises the capital expenditure.
  • Vote: every amendment motion passed 9-0. Each final approval passed 8-1 with Green voting no. The minutes give no reason.
  • Where it stands: approved 9/28/2026 under the emergency, postponed and second-reading section; no debate is recorded in the minutes.
  • Related: another Enterprise Zone amendment passed the same night, see OhioHealth Enterprise Zone Assignment.

Motions and votes (9/28/2026)

Ordinance Building Amend (mover / second) Approve as amended (mover / second) Result
2467-2026 1D Bankston / Ross Bankston / Ross 8-1
2468-2026 1C Bankston / Wyche Bankston / Wyche 8-1
2469-2026 1B Bankston / Barroso De Padilla Bankston / Barroso De Padilla 8-1
2470-2026 1A Bankston / Wyche Bankston / Wyche 8-1

Voting in favor on each final vote: Bankston, Barroso De Padilla, Day-Achauer, Dorans, Remy, Ross, Wyche and Hardin. Against: Green.

Sources

Log

2026-09-28 - Columbus City Council

  • All four ordinances amended 9-0 and approved as amended 8-1 (Green opposed).

2026-09-14 - Columbus City Council