At a glance

  • What: schedule, procurement and state aid for the next phase of the joint city-school construction program.
  • Where it stands: State aid fell at Webster and Seymour; design development is complete and construction documents under way; owner's representative RFP authorized on 2026-10-29.
  • Next: Proposals due December 3; design development submission to the State late November or early December; bids June 2027; phase 3B architect and construction manager RFPs at the December meeting.

Sources

Log

2026-10-29 - Joint School Construction Board

  • Resolution 23 authorized the owner's representative RFP; Resolution 21 moved Blodgett ahead of Delaware Primary School (Delaware to phase 3C); state aid reduced at Webster and Seymour because of a lower enrollment projection, with talks continuing.