Terrence Building Demolition

At a glance

  • What: Int. 357, agreements and an appropriation for demolition of the Terrence Building, 1201 Elmwood Avenue, the former state psychiatric hospital (built 1956, mostly vacant since 1995).
  • Where it stands: Sent forward by the Neighborhoods, Jobs and Housing Committee on 2026-10-06. The $20 million is state money that the City passes through on a reimbursement basis; no City dollars are committed and the developer covers any cost above $20 million.
  • Next: Abatement can begin once the state funding agreement is in place; abatement and demolition each take about a year.

Details

  • A representative of the developer, Whitestone Development Partners, said the project has the needed federal and state labor approvals to start abatement and has held neighborhood meetings.
  • City staff said they will review payment requests and sign off before state funds are passed through, similar to a Restore New York grant.

Sources

  • YouTube captions of the October 6 committee meeting, and the City's posted agenda.

Log

2026-10-06 - Council Committees Day 1

  • Questions on where the $20 million figure came from and the City's exposure to overruns; passed by voice vote.