159 Tory Street Golf Course Cart Bridge
At a glance
Based on auto-generated captions; street names and numbers may be misheard.
- What: a notice of intent (captioned 159 Tory Street, at the Thorny Lea golf course) to replace a deteriorating earthen berm and paved cart path between two ponds with an elevated timber bridge on 12-inch pilings, a project of roughly half a million dollars.
- Where it stands: the commission closed the hearing and issued an order of conditions on October 21.
- Why it matters: the work crosses open water, bank and a 25-foot no-touch zone (about 160 square feet of unavoidable impact), but removes impervious cover and adds open water habitat.
Key points
- The commission's peer reviewer (Weston and Sampson, as captioned) found its comments addressed. It agreed the project fits the limited-project provision for footbridges and that stormwater standards are met.
- Mitigation includes a turtle nesting area of 12 to 18 inches of clean sand in a contained depression near the 18th fairway.
- Special conditions: extra filter bags for dewatering; turbidity monitoring of bypass discharge, stopping if visible; field verification of water depths before sheet piling, with sheet piling preferred over sandbags; a signed illicit discharge statement before construction; a finding that bordering vegetated wetlands exist but their boundaries are not confirmed; a detail sheet or narrative for the turtle habitat before work; signage around the turtle habitat; and weekly visits by the commission's agent during active construction (the commission chose this over a paid environmental monitor, which would add cost). A pre-construction meeting will decide whether a turbidity curtain is needed.
- Work is expected to start in November and take a few weeks. No one from the public attended.
Sources
Log
- 2026-10-21 - Conservation Commission - Order of conditions issued by roll call after the peer review summary.