Monotomy Rocks Playground Installation
At a glance
- What: The director reported the playground project at Monotomy Rocks Park is delayed by poor project management by the equipment vendor, with five defective (cracked) pieces being replaced and an expected install in late November. Change orders are over $92,000 and another contract extension may be needed. A certified playground safety inspector will check the installation.
- Related: Wood chips left at the rink delayed paving.
Based on auto-generated captions of the video; names and numbers may be misheard.
Sources
Log
- 2026-10-13 - Park and Recreation Commission - Director update on delays, defects and costs.
- 2026-10-01 - Conservation Commission - Conservation Commission staff found the related order of conditions runs to 2029.