2026-09-28 - City Council Electric Strategy Workshop
Summary
Built from the City's posted agenda and YouTube auto-generated captions. Minutes are marked draft and were not read. Names and figures are as captioned and may be misspelled; the workshop took no final actions, and most polling was by show of hands or straw poll.
- Workshop on the City's electric strategy beyond the current IMEA power supply contract, which expires September 30, 2035 (item 26-1147). See Electric Utility Strategy. The mayor opened by noting no final actions would be taken.
- Public forum: eight speakers. Some urged moving away from IMEA and hiring outside independent expertise, disputing staff slides on staffing, timing and price volatility for the market-participation options. Others argued that staying with IMEA's Prairie State supply is cheaper after its bonds retire, that carbon goals should not drive the decision, and that reliability and affordability come first.
- Staff (the city manager and electric utility director) reviewed the timeline: the 2007 IMEA contract, Goldman Sachs-era supply from 2007 to 2011, the 2025 decision not to accept IMEA's extension, and the February 2026 vote to pause extension negotiations. They noted PJM capacity-shortfall projections beginning in 2030 and growing data-center demand. In answer to a question, staff said the grid's reliability would not depend on the supplier chosen, though pricing would.
- Vision statement: staff offered five drafts; two council members proposed a sixth: "to secure an energy future that prioritizes reliability, sustainability, affordability, flexibility, and local control." Another member proposed a statement on a financially strong, technologically adaptable utility. The mayor asked whether affordability could be listed first; several members preferred the unranked order. Some members worried that "sustainability" is undefined. A straw poll selected statement six by simple majority (no count was stated).
- Decision framework: staff presented affordability, resilience and reliability, sustainability and flexibility (renamed from "custom programs") with benchmarks such as cost per kilowatt-hour versus ComEd, wholesale cost, outage duration, carbon produced and program participation. Staff said the framework will come back to council before a decision, and some members asked that it be discussed as a council first.
- Options reviewed: (1) join or create a joint action agency; (2) market participation with asset ownership; (3) market participation without asset ownership (power purchase agreements); (4) sale of the utility. Staff recommended focusing on joining an existing joint action agency, on option three, and not on option two or option four. Battery energy storage could fit under options one through three.
- Show of hands on which options to keep pursuing: option two drew five hands, option three eight hands, and option four none. The option one count was not captured in the captions. Staff said no resources would go to option four unless directed.
- Council members asked whether IMEA would be invited to present; staff said IMEA was respecting council's pause but would likely appear if invited.
- Next steps: a new rate study is expected in 2027 (a member referenced June), to be presented with an evaluation of the remaining options; staff will continue the battery energy storage cost-benefit analysis and bring back the decision framework and mission statement.
Agenda
Agenda items are summarized above; the full agenda is on Legistar.
Sources
- Legistar meeting calendar: https://naperville.legistar.com/Calendar.aspx
- Video: https://www.youtube.com/watch?v=dbP0BNfyRxI (City of Naperville YouTube channel, streams)
- Video (City's own archive): https://naperville.granicus.com/MediaPlayer.php?view_id=2&clip_id=1857
Video
Transcript
*These are auto-generated captions; names and numbers may be misheard.
Transcript
08:29Yes.
09:56Good evening and welcome to the electric
09:58strategy workshop. As a reminder, no
10:00final actions are being taken at this
10:02meeting since it is a workshop. Also,
10:04the rules of city council still apply.
10:07Speakers are asked to present their
10:09comments in a respectful and courteous
10:10manner. Speakers should stay stay on
10:13topic and be cognizant of their words.
10:14Speakers are given three minutes to
10:16address the city council. And to help
10:18speakers stay within the three-minut
10:19time frame. Speakers should be aware of
10:21the timer located on the side dis.
10:25This timer will buzz when it hits zero
10:27and we will alert the speaker that their
10:29time is up. Also, when speakers names
10:32are called, they'll be called at least
10:34in groups of four. and we ask that you
10:36move to the front row right behind the
10:38podium so we can keep things moving.
10:43Miss Galahghue, are you ready?
10:45>> Yes, Mr. Mayor. There are eight speakers
10:47tonight. The first four speakers are
10:49Richard Stark, James Far, Joe Hus, and
10:53Tim Fero.
11:05Hi, Richard Stark, eight years with
11:07Neapville and also a member of the
11:10strategy team supporting Doug Kger. I'm
11:13here tonight to give you an update of
11:15the due diligence we used to check for
11:18errors in AI generated research reports
11:21and analysis.
11:25The overall process is pretty simple. We
11:28first started by uh selecting two AIS
11:31each to run the same uh answer to a
11:34prompt and we get uh two research
11:37reports. From that we pick the uh the
11:40one we like the best and then ask the
11:43other one or a different AI to conduct
11:45due diligence on that. And then
11:48following that we got some human
11:50intervention by shopping some of the
11:52major concepts with others within the
11:54community who are knowledgeable about
11:56this topic.
11:59I'm now going to uh play a response from
12:02Gemini Pro who was uh asked to do
12:05diligence on a very detailed chat GPT
12:08electricity strategy external analysis.
12:12It was a 28 page report which contained
12:1450 59 citations.
12:18>> I'm Gemini Pro. To perform AI due
12:21diligence, how do I audit a competitor's
12:24complex analysis? Because Just another
12:27AI strategic plan. Every single
12:29underlying claim and calculation needs
12:31verifying. Take my recent assignment
12:34GPT's electricity strategy report for
12:37Neapville's Richard Stark. Layer one is
12:40citation verification. My dashboard
12:42scanned the ent
12:47GPT citations accurately supported the
12:49referenced source material. Layer two is
12:52mathematical integrity. I don't just
12:55read the final numbers. I audited every
13:01data. But then my system flagged a
13:04potential anomaly, a totally fabricated
13:07fact, an AI hallucinaber
13:17to expose the error, but the joke was on
13:20me. Chat GPT was right. That's just the
13:22new National Renewable Energy
13:24Laboratory. I finalized my assessment.
13:28This reports a massive level of
13:30analytical rigor. It provides
13:32Neighborville City Council with a highly
13:34reliable foundation for their
13:35electricity strategy. So, what's the
13:38final verdict on that GPT strategy
13:40report for Neville? It passed my 59
13:44citation audit with perfect accuracy.
13:46I'll just have to find another way to
13:48criticize my competitor.
13:54Um I hope you are now confident that we
13:56are thoroughly have thoroughly vetted
13:58our sources and uh hope you have a very
14:00successful workshop. Thank you.
14:03>> Thank you. Next speaker.
14:05>> The next speaker is James Farar followed
14:08by Joe Hus.
14:16>> Good evening. In government people's
14:18feelings carry weight. There is some
14:20fraction of Neapville residents who
14:22don't want their utility payments
14:23flowing to a coal plant. I understand
14:25that and respect their opinion. There is
14:27probably a better way to say it, but
14:29their feelings will be hurt if we stay
14:30with IMEA. Unfortunately, no one really
14:33knows how many residents are in this
14:35category. It's never been measured, but
14:37here are some facts. Despite heavy
14:39marketing, only 6% of utility customers
14:42subscribe to the city's energy
14:43efficiency program. Not all of them are
14:46altruistic. Most take more money out of
14:48the program than they are paid in. That
14:50sounds like a business decision, not a
14:52statement on reducing carbon. Rexs are
14:55used to help build more solar and wind
14:57facilities in Illinois. Yet only one,
14:59yes, one resident has purchased Rex
15:02through the city's green energy
15:03certificate program. Maybe these low
15:06numbers are a statement of how our
15:08residents feel about paying for carbon
15:10reduction programs out of their own
15:12pocket.
15:13It's likely you have heard from hundreds
15:15of constituents on this matter. It would
15:17be a stretch for you to claim you've
15:19personally heard from a thousand, but
15:21let's go with that number. That means
15:24you haven't heard from 62,000 utility
15:26account holders in Neapville. They have
15:29feelings, too. Think about rateayers
15:31hurt feelings when they open their
15:32utility bill in 2035 and see it has
15:35increased by hundreds of dollars.
15:38They'll perk up and ask, "Why is this?"
15:40Those future residents will be reminded
15:42the two coal plants at the heart of this
15:44issue are still running at full capacity
15:47and producing the lowest cost power in
15:49Illinois, but no longer for them and
15:52with no carbon reductions whatsoever.
15:55Those future residents will be reminded
15:56they collectively paid $700 million over
16:00the last 24 years with the promise their
16:02power supplier would drop the price of
16:04electricity by 25%.
16:07Instead, their $700 million investment
16:09vanished into thin air and their rates
16:12actually went up. Debris reminded their
16:15city no longer has an influential seat
16:17on the board of their supplier to guide
16:19its policies, but rather it is now some
16:21faceless, profit-driven Texas-based
16:24corporation. It seems like there will be
16:26plenty of hurt feelings to go around in
16:282035.
16:29This includes retired couples on fixed
16:31income already close to being driven out
16:33of their home by property taxes.
16:36uh families working two jobs but still
16:38relying on a food pantry to make ends
16:40meet or low-wage earners hoping to stay
16:43in Neighborville to give their children
16:44a better chance in life than they had.
16:47There'll be 62,000 of them opening their
16:49bills in 2035 all with hurt feelings
16:53asking what did I get in return? Thank
16:56you.
16:58>> Thank you. Next speaker.
16:59>> Next speaker is Joe Hus followed by Tim
17:01Fero, Robert Geese, and John Doyle.
17:06And if you've heard your name call,
17:07please move to the front row.
17:17>> Um, I'm Joe Hus and I'm a volunteer with
17:19Nest and I have some concerns with
17:20tonight's presentation. Um, in options
17:23two and three it says quote requires new
17:27personnel to staff an energy management
17:29office and today we pay IMEA to provide
17:32those energy management services. if we
17:34leave IMA, we can hire uh many different
17:37experienced power marketers to provide
17:39those same services. We don't need to
17:42hire staff. Um and so I didn't
17:44understand why the slide said that. Um
17:48then on option two, it also said
17:50requires immediate action. Again, we
17:53we've shared information at past council
17:55meetings that projects are built much
17:56faster than the nine years that we have.
17:59And more importantly that most it's most
18:01common to buy assets that are already
18:03under development. Uh for comparison
18:06here in Will County, Earthwise Energy uh
18:09started construction in this year for a
18:12600 megawatt solar farm and plans to
18:14start delivering electricity in 2028. So
18:17three years. In fact, the typical energy
18:20contracts are signed three to five years
18:22before the energy is needed. And for
18:25reference, you can look at slide three
18:26of the presentation that shows that we
18:29signed the IMEA deal just four years
18:31before receiving energy. Acting nine
18:34years before we need it would limit
18:36Neapville's options and flexibility.
18:42Um, also on option two, it said market
18:44participation with assets would have
18:47frequent rate fluctuations for
18:49customers. So assets serve as a physical
18:52hedge against pricing volatility. And
18:54today the coal plant serves as that
18:56physical hedge. Uh we can replace the
18:58coal plant by purchasing assets that are
19:01allowed under SEA or by signing a power
19:04purchase agreement. And both provide the
19:06same rate stabilizing effect. Rate
19:09volatility will depend on how much
19:11energy we hedge and how much cash buffer
19:13we maintain. And that's just the same as
19:15it happens today. So we don't understand
19:18why the slide says that the opposite.
19:21Those are just some examples of issues
19:24with the presentation, but they point to
19:26the importance of hiring outside
19:28independent expertise. In a couple of
19:31years, we'll need energy experts to
19:34provide the council with facts so that
19:36we'll turn so that we can turn our
19:38vision statement into action. Nest
19:41advocates for a diverse, flexible
19:44solution like on the one on the screen
19:46that wouldn't require hiring staff,
19:49wouldn't have price volatility, and
19:51would give customers options to lower
19:53their bills. Thank you.
19:56>> Thank you. Next speaker.
19:58>> The next speaker is Tim Fero, followed
20:00by Robert Geese, John Doyle, and Lewis
20:02Halus.
20:11Thank you.
20:13Tim Fero, affordable Neighborville
20:15director and resident of Neapville. This
20:19table here is a black energy comparison
20:20[clears throat] between IMEA Prairie
20:22State Power Plant or Power versus a PGM
20:26solar PPA. For sake of time, I'd like to
20:29skip to line to second line, which
20:31provides a glimpse into 2035 when
20:33Prairie State bond cost is retired. The
20:36base cost for Prairie State is $31 a
20:38megawatt hour. This was determined from
20:41actual 2025 invoices and generation
20:45reports.
20:47You then add a capacity cost of and for
20:51for Praate it's $4 for a total of 35.
20:55Now for solar PPA in PJM the base cost
20:58is around 80. The PGM capacity cost for
21:02such a solar PPA is $25. And this is $25
21:07per megawatt hour. And this cost is
21:08going to go up for a total of 105.
21:12So in so when you look at the totals,
21:14solar is three times the cost of IMEA
21:17Prairie State post the bond.
21:22Now I would like to cover some cover
21:25vision and strategy factors to consider.
21:27The state of Illinois already has a
21:29clean power plan. So why does Neapville
21:31need to get ahead of the state's plan?
21:33In doing so, there is a risk of
21:35isolation leading to reduced access to
21:38lower cost power and higher energy cost.
21:41The state has far gre greater
21:43flexibility to adjust CJ time timelines
21:46if economic risk warranted.
21:50Most Neighborville residents prioritize
21:52reliable and lowcost energy.
21:56Neighborville's economic development
21:57goals like I88 corridor depend on
21:59ensuring incremental reliable cost of
22:02damage power.
22:04Neapville businesses consume 50% of
22:07Neapville's power. We need to ensure
22:09their access to lowcost power remains.
22:12Higher utility costs to businesses will
22:14pass through to customers.
22:18Demand response and VPP initiatives
22:20should be should demonstrate a clear
22:22monetary benefit with transparent
22:24measurement.
22:26These programs should be evaluated on
22:28cost and reliability outcomes rather
22:30than carbon-driven objectives.
22:33Ration demand is now a long-term
22:36solution. Time-of-use structures often
22:38evolve into rationing mechanisms.
22:42After years of alternative choices, 80%
22:46of Comet customers still use the
22:48standard bundle service. There is no
22:50large pent-up demand for alternate
22:52choices by residents. Thank you.
22:56>> Thank you. Next speaker. Next speaker is
22:59Robert Geese, followed by John Doyle,
23:01Lewis Halus, and Roger Bloomquist.
23:11My name is Robert Gezy. I am with
23:13Affordable Neighborville. I moved here
23:15in 1972 after earning my PhD in physics
23:18from Stanford University and I spent 26
23:21years at Argon National Laboratory much
23:24of that time studying electric utilities
23:26and energy storage. We are told that
23:29there is quote unquote a climate crisis
23:33is there. I remember Rahm Emanuel saying
23:36you never want a serious crisis to go to
23:38waste. His full point was that a crisis
23:41can create an opportunity to do things
23:44that might otherwise be difficult. I
23:46believe we should be careful that
23:48climate policy does not become driven by
23:50the label crisis rather than by careful
23:53analysis. The climate system is
23:56extraordinarily complex. It involves the
23:59atmosphere, oceans, land, cloud, and
24:02many feedback mechanisms. Climate models
24:05are useful tools, but they are not
24:07perfect representations of reality.
24:10Earth's climate has climate has always
24:12changed. During the age of dinosaurs,
24:14temperatures were substantially warmer
24:16than today. 10,000 years ago, massive
24:19glaciers covered much of North America.
24:22Natural climate processes are real, and
24:24scientists cons continue to study them.
24:27The question is how much of today's
24:29warming is caused by human activities
24:32and what policies are justified by that
24:34warming. Greenhouse gases clearly affect
24:37Earth's temperature. Without the natural
24:39greenhouse effect, Earth would be far
24:41colder. Water vapor is the most abundant
24:44greenhouse gas.
24:46But its concentration largely responds
24:49to temperature. It is claimed that CO2
24:52persists in the atmosphere.
24:54This could be wrong. There is a
24:56mechanism to bring it out of the
24:58atmosphere. CO2 and water vapor combine
25:01to form carbonic acid. Carbonic acid
25:04combines with limestone and similar
25:06stone to form carbonate precipitates
25:08which eventually wash down to into the
25:10ocean where the plate tectonics remove
25:13the CO2 to the Earth's core. In
25:16addition, the relationship between CO2
25:18and temperature is not simply simply
25:20linear.
25:22The additional warming from increased
25:24CO2 is approximately logarithmic. My
25:27concern is that legitimate scientific
25:29questions are sometimes turned into
25:31political claims that leave little room
25:34for uncertainty or debate before we make
25:37expensive long-term changes to our
25:39energy system. We should carefully
25:41examine the evidence, the costs, the
25:44benefits, and the alternatives. So, I
25:46urge you, don't simply accept the phrase
25:48climate crisis. Examine the science and
25:51the policy choices for yourself. Thank
25:54you.
25:55>> Thank you. Next speaker.
25:56>> The final three speakers are John Doyle,
25:58Lewis Halchus, and Roger Bloomquist.
26:11>> John Doyle, Neville resident. Thank you.
26:13Um, tonight's presentation is going to
26:15start with a brief procurement history
26:16of the utility. And I noticed that
26:18pricing information wasn't included,
26:19which I thought seemed relevant. Going
26:22back to 2004, there were only three
26:23years that KMED was cheaper than
26:25Neapville. All three years during the
26:27IMEA era. The biggest average difference
26:29between us and Kameed happened during
26:30the J Aaron era. 17% cheaper with J
26:33Aaron compared to 8% cheaper with IMEA.
26:36In fact, IMEA's average difference is is
26:38marginally worse than we were buying
26:40power wholesale from KMED directly.
26:43Outside of the 2022 spike, the
26:44divergence that happened after 2021 has
26:47been driven by Comeded's delivery costs
26:49increasing, not their energy costs. We
26:52do not need a joint action agency to be
26:54cheaper than COMED. We have already
26:55shown that we can do a better job of
26:57that without one.
27:00And then it looks like tonight we're
27:01going to be setting a vision statement
27:02as a key outcome. Uh regardless of what
27:05was chosen or what is chosen, I think
27:06Mr. Wilson was very much correct a
27:08couple months ago when he said we're
27:09going to need definitions for all the
27:10key words in use. And take affordability
27:13for example. Uh it's not defined by SEA
27:16but it's worked out between the ICC and
27:17the IUS in our state. And in Neapville's
27:20case, you are the legislator, the
27:21regulator, and the utility all all in
27:23one. So it's entirely up to you as a
27:25body to define these key words in our
27:27mission statement and in our vision
27:28statement.
27:33When it comes to reliability, um I'm not
27:35sure how our SAT scores are relevant to
27:37the energy procurement side of the
27:38discussion and why it would be part of
27:40the decision framework. So when we get
27:41to that section of the presentation, if
27:43someone could please explain how
27:44reliability would be different under
27:46IMEA versus PJM market participation,
27:49that would be appreciated. I'd also like
27:51to suggest two additional metrics,
27:52autonomy and flexibility. You know, one
27:54of the city's guiding principles is to
27:55protect and preserve municipal
27:56authority. Why wouldn't that apply to
27:58this decision as well in regarding
28:00flexibility? No one could have uh
28:02predicted the current state of the
28:03battery and solar market 15 years ago.
28:05Even now, they are regularly
28:06underestimating growth in both sectors
28:08year-over-year. No one knows what it's
28:10going to be like in 20440 either. So we
28:12need a plan that lets us adapt to the
28:14changing markets.
28:16And lastly, I believe the plan is to
28:18eliminate options four and options two
28:19tonight. As well as the idea of forming
28:21our own joint action agency. I'd like to
28:23suggest instead of removing option two
28:25to merge options two and three together
28:26into a single market participation
28:28option. Uh we do not need to necessarily
28:30have owned assets ready to go in 2035.
28:33Uh but we shouldn't necessarily keep
28:35them out of the uh the conversation for
28:37long-term plans either. Thank you.
28:42>> Thank you. Next speaker.
28:43>> The next speaker is Lewis Halus followed
28:45by Roger Bloomquist.
28:53>> Next speaker.
28:55>> Final speaker is Roger Bloomquist.
29:00>> Good evening. My name is Roger
29:01Blumquist. I'm speaking for myself. I'm
29:04a lifelong engineer uh with experience
29:07running the electric micro grid on a
29:10nuclear submarine. So I've had a long
29:12interest in electricity. I also served
29:15briefly on the Nest energy committee.
29:18Traditionally our electricity priorities
29:20have been number one reliability, number
29:23two affordability, and number three
29:26environmental. That doesn't mean that
29:28two and three were ignored. It's just
29:31that number one was number one. This
29:34order of priorities fueled the post-war
29:37economic boom in the United States and
29:40around the world. These priorities have
29:42now been reversed.
29:44Nest and their allies have claimed that
29:46this will make electricity cheaper and
29:49more reliable. In fact, it has already
29:52made electricity more expensive, far
29:55less reliable, and only a little
29:56cleaner. And one of the slides from the
29:59previous speaker showed this.
30:02And unreliable electricity is not
30:05affordable electricity. Aware of this,
30:08lots of households and businesses in
30:10Neapville are installing fossil energy
30:13uh fossil emergency generators. That
30:16cost acts like a tax to protect us from
30:20electricity shortages. For consumers of
30:23goods, that tax appears as price
30:26increases and it makes reliability
30:28unaffordable for most people.
30:32Nest and ACS partner with Rocky Mountain
30:35Institute Pressure Group. RMI is funded
30:38by the government as it has advocated
30:40burning coal for home heating.
30:45I assume they still advocate underground
30:48homes. Or maybe they don't. They seem
30:51convinced that they alone are right
30:53about both markets and engineering,
30:57at least this time. How can we possibly
30:59take their recommendations seriously?
31:02Does anyone has anyone here ever seen a
31:06news story about falling electricity
31:08rates? I urge the city council to apply
31:11the laws of physics and economics and
31:14its electricity strategy.
31:17Aspirations are good, but not good
31:19enough.
31:20In the war between physics and
31:22platitudes, physics will win every time.
31:26Its laws cannot be repealed or amended
31:29by political systems. Thank you very
31:32much.
31:33>> Thank you. Any more speakers?
31:35>> No, mayor.
31:36>> All right. I'm going to turn the
31:37workshop over to our city manager, Mr.
31:39Kger, for the beginning of his
31:41presentation.
31:43>> All right. Uh, thanks, Mayor.
32:05All right, there we go. Uh, well, good
32:07evening. Uh, this April, we began a
32:09series of presentations to review our
32:12options for procuring energy in the
32:14future. We provided an overview of where
32:16we're at in the process, key
32:18terminology, some of the important
32:20considerations associated with energy
32:22and the key dates coming up that impact
32:24our decision-making.
32:26For tonight's agenda, we'll start with a
32:28recap of what has led us to this point.
32:31We'll review a timeline of key dates in
32:33our power purchase history. Um, we'll
32:35look at vision statements and hopefully
32:37align on a statement to guide our
32:39long-term strategy.
32:41We'll also review the decision framework
32:43that is guiding this process.
32:45Over the course of the last several
32:47months, we've reviewed all of the
32:49options from staying with a joint action
32:50agency to selling the utility. And
32:52tonight, we'll provide a highle summary
32:54of those options discussed.
32:57And then we'll have some discussions to
32:59confirm direction for staff and end next
33:01steps.
33:03Let's first take a look back at the
33:05decisions that have been made that have
33:07led us to our current situation.
33:10Back in 2007, the city approved the
33:12contract with IMEA and that current
33:14contract expires September 30th of 2035.
33:19All the options explored take
33:21considerable time and planning to
33:22implement.
33:24From ' 07 to 2011, we received power
33:27from Jiren Goldman Sachs and IMEA began
33:30handling our administrative or ancillary
33:32duties.
33:34Then on June 1st of 2011, the city began
33:37receiving power from IMEA.
33:42In late 2023, discussions began on what
33:45the city's energy future could look like
33:46beyond 2035.
33:49IMEA presented its members with a
33:52contract extension and provided a
33:54deadline to accept the offer by April
33:5630th of 2025.
33:58Uh beginning in the spring of 2024,
34:01uh the electric utility held a series of
34:03educational presentations to city
34:05council.
34:07These presentations coincided with the
34:09rate study to determine financial needs
34:11through 2027.
34:13Uh and finally, staff hired a consultant
34:15to help forecast energy prices and
34:17outline our options.
34:21Moving to 2025,
34:24uh, council chose not to accept the IMEA
34:26contract extension, uh, and it was
34:29extended to August. Further educational
34:32presentations were given at council,
34:33PUAB, and from the hired consultants, as
34:36well as an energy workshop held in July
34:39of 2025.
34:41Council chose in August not to accept
34:43the contract extension. However, council
34:46did plan to continue negotiations and
34:48discussions with 10 specific areas and
34:51an added power sales contract.
34:55In February of 2026, council votes voted
34:58to formally pause the contract extension
35:00negotiations with IMEA.
35:03Uh in the spring of 26, the be utility
35:05began a new educational presentation to
35:08review current energy industry status
35:10and to present options for procuring
35:12energy in the future.
35:14Tonight's workshop uh leads off those
35:18April through August presentations.
35:21It's worth noting that there have been
35:22shifts in market trends and important
35:24implications as we look at our long-term
35:26planning.
35:28Some of the more major shifts include a
35:31shift uh from energy concerns to
35:33capacity concerns. Uh renewable sources
35:36continue to experience price reductions.
35:38Uh there's a significant decrease in the
35:40cost of battery energy storage systems.
35:43Um, in December uh of 2025, the Illinois
35:47Power Agency indicated for the first
35:49time potential reliability and capacity
35:51shortfalls in the PJM grid. PGM has a
35:54capacity shortfall predicted um uh
35:58predicting their shortfall begins in
36:002030. Uh also PGM has been very slow to
36:04add new new uh sources of energy. Uh and
36:08there's a potential for exponential
36:10growth in demand uh due to data center
36:12proliferation
36:14uh and current volatility creates
36:16challenges for longerterm contracts.
36:20Mr. Mayor, are there any questions
36:21before we move forward?
36:24>> Councilwoman Gibson.
36:26>> Thank you, Mayor. Uh two questions. Uh
36:29Mr. Kger, on slide three, it caught my
36:31eye in
36:33that middle one. IMEA begins handling
36:36administrative duties, but we weren't
36:38getting our power, our energy through
36:41them, right?
36:42>> That that that's correct. Um uh Jer and
36:45Goldman Sachs uh was basically our
36:47billing agent. Um but for uh like FK,
36:52NERK, uh PJM reporting requirements,
36:55IMEA was uh taking care of those for us.
36:58So we were a uh non um power you uh we
37:04were a member of IMEA but not a power
37:06purchasing member.
37:08>> Okay. So when we're talking about our
37:09options later in the presentation and
37:11the options we've been talking about
37:13before and we're talking about the need
37:14for staff or administrative.
37:17>> This is essentially what IMEA did for us
37:19for several years.
37:20>> It it is um it it is a function. Uh it
37:23could be done by staff. It absolutely
37:25does not have to be done by staff. Um uh
37:28so just to kind of put that out there.
37:30>> So as a city we have a history though of
37:31splitting up the energy procurement with
37:33the administrative if necessary.
37:37>> Uh yes uh from ' 07 to 2011 we did that.
37:41Prior to that um as a KMED customer took
37:44care of all our ancillary requirements.
37:46Um and then post IME took care of it.
37:50>> Okay. And so just to clarify the commed
37:51part so this timeline starts in 2007.
37:54Prior to that, we're commed customers
37:56just so we're on the same page.
37:57>> That's correct.
37:58>> And then um my other followup was you're
38:00talking about the PJM capacity concerns
38:03for 2030 2035.
38:06>> Um would where we get our energy from
38:10impact whether or not PJM
38:15I don't know if brown out's the right
38:16term affected our power supply. Okay.
38:18So, the reliability of the energy
38:20Neighborville gets from PJM and the
38:22grid, is that dependent on whether we're
38:25with a a joint action agency, um any of
38:28these other options?
38:30>> It it really should not. Um it's
38:32probably larger effect would be on, you
38:34know, pricing at that time.
38:37>> Okay. So, IMEA wouldn't necessarily cut
38:40Neighborville's power
38:43in 2030 if there were outages to the
38:44grid based on where we're sending our
38:48money for the power.
38:48>> That's correct.
38:49>> Okay. Thanks. That's helpful.
38:55>> I don't see any other questions.
38:57>> All right. Uh let's quickly review the
39:01difference between vision and mission.
39:03Uh at high level, a mission statement
39:05defines what we do today and answers the
39:08question, why do we exist? A vision
39:10statement is aspirational and describes
39:12what we want to be in the future. And
39:15that aspiration is one of the items
39:17we're here to discuss tonight.
39:21Whoops. How about that way? To develop a
39:24vision statement, we need to focus on
39:26our utility's future. The central
39:28question to answer is what will
39:30Neighborville's electric utility look
39:31like when we have successfully achieved
39:33our goals? In response, any vision
39:37statement we draft must satisfy four key
39:40criteria.
39:42First, it must be future focused and
39:44projected over a long term, such as a
39:4620-year horizon. Second, it should be
39:49inspirational and directional. That sets
39:51a clear trajectory for utility planning.
39:55Third, it must define our final
39:57destination. It does not focus on the
40:00granular day-to-day steps required to
40:02get there. Uh and finally, it must be
40:04explicitly anchored in the values we use
40:06to make decisions.
40:08With these guard rails in mind and to
40:11get the discussion going, let's consider
40:13a few samples of vision statements.
40:18Staff has drafted five vision statements
40:20which are shown over the next two
40:22slides. uh one statement uh that would
40:24be statement number two is also repeated
40:26as statement six just to make sure
40:28people were paying attention. Um but
40:30let's review each. Uh number one,
40:33delivering affordable, reliable power
40:35today while fostering the flexibility
40:37and sustainability Neapville needs for
40:39tomorrow. Two, providing reliable and
40:43affordable electricity while preserving
40:45long-term flexibility in demonstrating a
40:47commitment to the environment.
40:50Three, leading Neapville into an
40:53affordable, reliable, resilient, and
40:55carbon-f free electricity future through
40:57a flexible portfolio of supply, storage,
41:00and demand resources that can adapt to
41:02changing markets, technology, and
41:04community needs.
41:08Four,
41:09uh, envisioning an energy future built
41:12on affordable, reliable, and fortified
41:14power delivery. We will maintain a
41:16diverse supply oriented mix of clean
41:19Illinois compliant energy resources
41:21including m modern thermal generation.
41:25And finally, five, provide affordable,
41:27reliable electricity while preserving
41:29future flexibility and advancing
41:31Neapville sustainability goals.
41:34Neapville will continue to be a model
41:36community by keeping emissions from
41:37rising, bringing them below the Illinois
41:40average within 10 years and achieving
41:42carbon-f free electricity by 20 uh 2045.
41:47In addition, some of you have offered up
41:49additional options for a vision
41:51statement that are believe that I
41:52believe are worthy of further
41:54discussion.
41:57This is the current mission statement of
41:59the electric utility. Once a vision
42:01statement has been created and selected,
42:04uh would then advise the city undertake
42:06revising the mission statement later as
42:09needed, but not at this time.
42:13Now that you heard each vision
42:14statement, Mr. Mayor, I recommend
42:16opening the floor for discussion with
42:17the goal of reaching consensus on one or
42:20a version of one value statement.
42:25>> All right, council. I've asked Director
42:27Llloch to run the computer for us. She's
42:30going to um live type any versions that
42:34might come out of the council discussion
42:36here and we will have our
42:41ideas put down on the computer screen in
42:43front of you. We will call first on
42:46Councilwoman Jane.
42:48>> Thank you, Mayor. Thank you, Mr. Kger,
42:51for your presentation thus far over the
42:53summer and for offering these examples
42:57for vision statements. Um I agree with
43:01uh the key points delineated on slide
43:04nine which talked about it being um
43:08long-term focused, aspirational.
43:12Um but I will also add to that that I
43:15think it needs to be a statement that's
43:17succinct
43:18um easy to understand and hopefully
43:21measurable
43:23uh through our decision framework and
43:26our ultimate mission statement. So, um,
43:30for those reasons, uh, Councilwoman
43:32Gibson and I kind of been thinking a lot
43:35about that and looking at the options,
43:38um, here we'd like to offer, uh, another
43:42possible statement um that I would love
43:44to hear my the opinions and thoughts
43:47from my my colleagues up here. And that
43:49is as follows.
43:51to secure an energy future
43:55that prioritizes.
44:02Reliability,
44:05sustainability,
44:08affordability,
44:12flexibility,
44:15and local control.
44:18This statement we believe reflects Oh,
44:22I'm sorry. No, that's it. Period. We're
44:24good. Yeah. Uh just just explain the the
44:29thought process behind this statement.
44:31Um it it doesn't have concrete terms in
44:35here to operationalize what we mean by
44:37each of these values, but that these
44:39five values we believe have been brought
44:42up in multiple discussions over the last
44:44few months, if not years. um where the
44:48terms are easily identifiable
44:52not sequenced in particular order. In
44:54fact, we would argue that the values
44:58five of them are interconnected. If we
45:00take the example of let's say
45:02flexibility as a value um and we were to
45:06practice that and measure that let's say
45:08by the purchase of storage batteries
45:11that in turn should help or may help
45:14sustainability and affordability right
45:16so we see that interconnectedness of
45:19these five values um again not to be
45:22operationalized in this statement but to
45:24be perhaps in um our discussion of the
45:28decision framework um but mo most
45:31importantly aspirational and reflective
45:34of our core values as a community um and
45:37what we've been discussing so thoroughly
45:39over the last months um and so with that
45:43I'd like to present that as an
45:44alternative statement.
45:48>> Okay, Councilwoman Gibson and note that
45:50we're identifying that as number six at
45:53this point.
45:55>> Thank you, Mayor, and thank you,
45:56Councilwoman Jane. Um, as she mentioned,
45:58we uh talked about this a lot. Um, and
46:02particularly I appreciated Councilwoman
46:04Jane's background coming from District
46:05204.
46:07As some of you may know, I um was on the
46:09park board previously. And at both of
46:12those um levels of government, I'd say
46:14we really
46:16uh worked a lot on strategic planning
46:18and vision and mission. Um, and one of
46:20the things I took away from my time at
46:22the park district is that a good vision
46:23mission statement is short. you want
46:26everybody in the organization to be able
46:27to say it at the drop of a, you know,
46:30drop of a hat. Um, at the park district,
46:32it was in the email signature. And I, at
46:35least I used it kind of as my guiding,
46:38my guiding light when I was making
46:39decisions at the park district. And what
46:41I particularly like about this last
46:43option six is that uh they are five
46:47pillars that are inter intertwined, but
46:50also they apply to both our electric
46:52utility and the energy procurement
46:54decision. that's before us. Um,
46:57especially flexibility and local
46:59control. Those are something that we
47:00care about at a resident and commercial
47:03level here in Neapville, but also as a
47:05city when we're looking about procuring
47:07our energy um because they really are
47:10intertwined. you know, what our
47:11residents pay and being able to
47:18have control and drive those prices is
47:21directly tied to the prices we pay at a
47:23procurement level. Um, so I I'm going to
47:27be in favor of option six. I appreciate
47:29Councilwoman Jane's work on it and I'm
47:32anxious to hear from the rest of my
47:33colleagues.
47:34>> Councilman McBroom.
47:36>> Thank you, Mayor. Um, [clears throat]
47:40so you know, my my and I do have a
47:43suggestion um to add to the list, but uh
47:47you know, my my concerns are always
47:50slippery slope. Um, what are these words
47:54going to be used for in the future? uh
47:57are we boxing some future council, some
48:00future city manager
48:02into financial commitments that
48:05may be reckless at the time? Um and and
48:08so
48:11if if the statement is is largely
48:14symbolic,
48:16um
48:18I don't know how we could have any
48:20assurances. Uh, Director Pier, you just
48:22mentioned that
48:24uh that whatever adoption of a vision
48:26statement,
48:28the next step would be it would it would
48:30cause a change in our mission statement.
48:33>> Yeah. In in terms of order, um, we would
48:35use the vision statement to establish uh
48:39a decision framework to make sure that
48:41we are capturing all of the components
48:44um for future strategic uh electric
48:48utility decisions. Um but uh the mission
48:52statement should definitely follow
48:53behind the vision statement that we're
48:55looking to establish tonight.
48:58>> Um as far as words, uh sustainability is
49:01a word that has come up all the time. Uh
49:04we we don't really get a definition of
49:06what that is. Um if if the vision
49:08statement is meant to be vague, um you
49:13know, I just I just it causes some
49:15concerns. Um so my my suggestion um
49:22would be to
49:24simply
49:26I got two that are very similar here but
49:29I'll go ahead and start. So to to
49:32maintain
49:35a financially strong
49:40technologically
49:45adaptable
49:51electric utility
49:55capable of meeting Neapville's future
49:58energy
50:06needs while preserving flexibility
50:13for generations to come.
50:19That's it. Thank you.
50:25Okay. Anything else? Council members.
50:30>> All right. Our goal here, Councilwoman
50:32Wilson.
50:33>> Sorry, Mayor. Um I I don't have an
50:36additional statement to add. I guess uh
50:39I don't know. You know, both uh seem the
50:42two new ones here seem um
50:45pretty succinct. Both add flexibility.
50:50Uh which to me makes sense. you know,
50:52with uh you know, IPA, for example, I
50:55think Director Kger talked about this,
50:57it's been talked about before with IPA
51:00projecting uh capacity concerns in 2030.
51:05Um but as I've talked about before, the
51:09sustainability bit does and and again if
51:11it does change um future statements and
51:15um things that we might be locked into,
51:18I do have concerns just because as I've
51:20talked about sustainability means
51:22different things to different people. Um
51:24and and especially when we think about
51:25metrics as well. Um to me I don't know
51:28what metrics we we'd be defining there.
51:31Um, then there's also um could be
51:35competing trade-offs when we're thinking
51:36about sustainability. Um, so I don't
51:39know. I um I do like obviously
51:42reliability and affordability. I think
51:44most people know what those mean. We we
51:46we look at different things when we're
51:49we have presentations from our our water
51:53um you know how many outited how many uh
51:56water main breaks there are. You know,
51:57that's part of the liability. um similar
52:01here here with energy. Um
52:05but
52:06uh I again I do have concern with that
52:08and whether it would similarly wash us
52:11lock us into something um without having
52:15some sort of metrics or uh scope etc in
52:20mind. Thank you
52:23>> Councilwoman Jane second round.
52:25>> Yeah, thank you. Um I I agree metrics
52:29are very important but to my
52:31understanding Mr. Kger that that metric
52:34and rubric by which we'll assess our
52:36future decision making and actions will
52:39be based on the decision framework and
52:42the mission statement perhaps right that
52:44that will help us define which what each
52:48of these values mean is is my
52:50understanding between what a vision
52:53statement is for versus the decision m
52:55framework and mission statement.
52:57>> Yeah. Um that is correct. um uh in about
53:01three slides uh we kind of kick into
53:03decision framework. Um we're not looking
53:06to kind of lock in on either those
53:08definitions or metrics, but really to
53:10just start that conversation um in light
53:14of a hopefully, you know, newly selected
53:16vision statement.
53:18>> Yeah. And the thinking behind the number
53:21six was um first of all it captures many
53:24of the words we've been talking about
53:26and using as part of the presentations
53:29as the framework or the lens through
53:31which we were analyzing all four
53:33options. Um, a good vision statement
53:36won't just be symbolic, but that it's
53:39really those next steps that are
53:42critical that where we delineate and
53:44operationalize, make these terms more
53:46concrete and then we live up to that,
53:50right? Like we um it's our job up here
53:53and in our community to to make sure
53:56that those words mean something and not
53:58to give just lip service. Um, I think
54:01that is totally possible. I think we're
54:03in a very unique time. We're in uniquely
54:06positioned at this moment to really
54:09think about the future um in a way that
54:13um is flexible, hence some of the some
54:16hence the term flexibility in there. Um
54:19but so I just wanted to add that to the
54:22conversation.
54:26>> Councilman White.
54:28>> Yeah, thank you. I um yeah I I guess
54:32we're looking at something that's more
54:33aspirational. I I'm
54:36a little concerned for some reason we're
54:39a couple of my colleagues are concerned
54:41about specifically the word
54:43sustainability and what it means and if
54:45it's locking us into something. I I mean
54:47I could take a look at almost any one of
54:49these and and say something similar. I
54:52mean what is techn techn techn
54:55technologically adaptable? I mean, okay,
54:57it sounds great, too, but and that can
55:00mean a lot of different things as well.
55:02So, I think it's going to uh it's
55:04important at this stage to not feel like
55:07we're we're locking something in. We
55:09haven't put any metrics around any of
55:10these things. Um, we've also have um
55:14taken a look at our uh our survey that
55:17recently came out that talked about
55:20sustainability and environmental uh
55:22concerns are important to the community.
55:24So I think it's important um at this
55:28stage that we include sustainability as
55:31well as some of the the other words that
55:33I I see that are in there. I think we
55:36have all seen uh up here on the dis as
55:40well as listening to members of our
55:42community that these are things that I I
55:45seem to be important to everyone. So um
55:48I guess I would caution us to keep it
55:52high level so that we can narrow it down
55:55into
55:57the things that we want to measure this
55:59on and then let's get to our mission
56:02statement and and let that drive let
56:04this vision drive all the decisions that
56:07we make once we come up with a uh
56:12something that we all can agree upon.
56:15Thank [clears throat] you, Councilman
56:17Hzar.
56:17>> Thank you, Mayor. I just wanted to give
56:19a shout out to Mr. Stark who probably
56:23for the last two years has been talking
56:25about the importance of uh having a
56:27vision statement. Um I appreciate
56:31Councilwoman Jane's comments. I I will
56:32be supporting number six is the the
56:34version of this. I in particular like
56:37that there's um five pillars that makes
56:39it very easy I think to build a mission
56:41statement later on and and
56:43operationalize.
56:44Um, but just as a general comment, I
56:47think beyond just the energy discussion
56:50as we think about strategic planning for
56:52our city in the next couple of years, it
56:54would be it's been a long time since
56:56we've had this discussion more broadly
56:57about what the city's vision is and and
57:00um I I just appreciate that we're
57:03talking about this more broadly and um
57:05and I hope that it becomes a habit for
57:07council. Thank you, mayor.
57:10>> Thank you.
57:12One thing I I'm looking at here
57:14throughout all of these different vision
57:15statements is the use of the word
57:17affordable. I I kind of interchange that
57:19with competitiveness as well. Um let's
57:22face it, there's a lot of communities
57:24around us that we are hearing hearings
57:27on um their water supply and how the
57:31privatization of their water supply has
57:34driven the costs up
57:36to to make it almost um unaffordable to
57:40live in their communities based upon
57:43what that private water supply costs.
57:46Right? So I I I do think we have to
57:49understand that in the business of
57:51selling electricity, we have to be
57:53competitive against what those
57:55communities next to us are selling
57:57electricity for, whether it be Kameed as
57:59their supplier or another
58:02municipallyowned electric utility. So
58:05going back to our our national community
58:07survey results, I mean, there was
58:08indication in there that affordability
58:11on power is something in the heads of
58:15the respondents. And I I think the
58:16positioning of that word near the
58:19beginning of any of these different
58:22terms really needs important placement.
58:24So whether it's competitiveness or uh
58:27affordable,
58:29you know, I I don't know how we don't
58:32prioritize that word in the vision
58:34statement.
58:36So Councilwoman Jane, I I I know number
58:38six is your suggestion. And would you be
58:41willing to uh offer some movement of
58:46affordability
58:48in front of the reliability?
58:51So it would read as to secure an energy
58:54future that prioritizes affordability,
58:56reliability, sustainability,
58:58flexibility, and local control.
59:02>> I I would be interested in hearing what
59:05my colleagues think of that move.
59:09I I have reason in the order that I
59:14placed it in. I I do think when you
59:16think about utility, reliability and
59:18affordability are often time the
59:20cornerstone values associated with it.
59:24Um,
59:27but I I do find the order to be
59:35perhaps reflect what I what I think um
59:40interconnectedly. I I do think though
59:42sometimes by putting sustainability
59:44towards the end, we think of that as an
59:46afterthought. Um that that could be a
59:49perception. Um although that's not
59:51necessarily the case here. Um so I I
59:55would love to hear from my from others
59:57on the dis on what they think about
59:59that.
59:59>> Yeah. My position is we have to have
1:00:02customers.
1:00:03>> Yeah.
1:00:04>> And and you can't sell a product without
1:00:05customers and you have to have an
1:00:07affordable product for those customers
1:00:09to buy.
1:00:10>> Councilman Hoszar.
1:00:11>> Thank you, Mayor. Um actually I think
1:00:13the mayor's point is exactly why I'm
1:00:15going to support number six. I mean, I
1:00:16think Councilwoman Jane was very clear
1:00:18that the intent is not for one of these
1:00:20to to stand out as a priority.
1:00:22Understand the mayor's argument, but I
1:00:24think the mayor's argument essentially
1:00:25is we are setting aside and agreeing to
1:00:27set aside affordability over the other
1:00:29four. And I I think that overlooks some
1:00:32of the interconnectedness part of this,
1:00:34right? So if we lack flexibility in
1:00:37local control as an example, we lack the
1:00:41ability even under our current contract,
1:00:43we lack the ability to purchase systems
1:00:46which would actually make our system
1:00:48cheaper. Um if we have reliability
1:00:52issues um that is that has second and
1:00:57third order effects. I mean look at the
1:00:58decision we made to underground our
1:01:00wires. That is unquestionably making and
1:01:03you know the energy price to neighbor
1:01:04consumers more expensive actually quite
1:01:06a bit more expensive over the next
1:01:09generation but we're we're doing that
1:01:11because we decided liability is
1:01:13important and it's a component of of all
1:01:16of this. I'm I'm not um I don't like the
1:01:19r the rationale of let's set one to the
1:01:22front because it's the highest priority.
1:01:26Um, I also
1:01:28would say to the credit of number six,
1:01:30it's not like sustainability was placed
1:01:32first to, you know, to make that one
1:01:35seem the most important. I think
1:01:36reliability, which is one we can all
1:01:38agree on, was the one that was put
1:01:39first, not to be prioritized over the
1:01:41other. Um, but I I like the framework
1:01:44then and yeah, I'm I'm going to support
1:01:46six. Thank you, Mayor.
1:01:49>> Councilwoman Gibson.
1:01:51>> Thank you, Mayor. Um, I I agree. I'm
1:01:53going to echo Councilman Holeshower's
1:01:56comments. Uh affordability obviously
1:01:58essential to bring in businesses. Also
1:02:00reliability. Um and I think maybe even
1:02:03the tension between those two. If we
1:02:05have really cheap energy but it's not
1:02:07reliable, that's just as likely to drive
1:02:09away businesses and residents and people
1:02:12that want to be in Neapville. Uh so
1:02:15personally, when I look at vision
1:02:17statements like this, I I see five
1:02:20pillars. I don't see any hierarchy
1:02:23in the way they're ordered. I think, you
1:02:26know, moving it around and explicitly
1:02:28saying or putting them in hierarchy,
1:02:32um
1:02:33I think they work together and putting
1:02:36them in an order will cause a tension
1:02:38between them where we have to prioritize
1:02:40one versus the other. Um and I don't
1:02:42think that's a strict rubric we want on
1:02:45our decision-m going forward. So, I like
1:02:48it as is with number six.
1:02:50Councilman McRo.
1:02:52>> Thank you, Mayor. Uh, Councilman Mike
1:02:54White makes a good point. Um, you can
1:02:56[clears throat] take all these words,
1:02:57technology, uh, you can extrapolate that
1:02:59into close to the microphone.
1:03:01>> What could that mean in the future?
1:03:02Thank you.
1:03:03>> Um,
1:03:05and and my concern is where where does
1:03:08the cost come in? Like what are we
1:03:09committing to? And so, [clears throat]
1:03:12it's pretty simple to me. Reliability
1:03:14and affordability. I mean, that's that's
1:03:16really what what's important to people.
1:03:18Um and uh and sustainability quite
1:03:22frankly it's a but it's it's a code word
1:03:24and I'm concerned that no one is able to
1:03:27define it for me and if we put it into a
1:03:29mission statement it's not something
1:03:31that
1:03:33are just words it's flexible it's
1:03:35something we aspire to we don't even
1:03:37know what it is um and and when I look
1:03:40at our mission statement
1:03:42frankly I think the mission statement
1:03:44could be stronger on on affordability
1:03:45but reliability quality responsive cost
1:03:48efficient services.
1:03:50I don't know what else we want. Uh I'm
1:03:52I'm fine with that mission statement.
1:03:53So, uh I'm I'm not sure I'm going to be
1:03:56supporting any of these vision
1:03:57statements.
1:04:01Okay. So, um
1:04:05it sounds like we've got
1:04:07three versions that were offered up from
1:04:09city council. Um, we've got to identify
1:04:14one from this group and we'll do a straw
1:04:18poll to determine what that looks like.
1:04:21So, um, we'll straw poll number six.
1:04:32>> Six, Mr. Mayor.
1:04:33>> Okay. And that's a simple majority.
1:04:39>> That's correct.
1:04:41We'll test number seven
1:04:47and number eight.
1:04:52Okay. Number six it is next item.
1:05:08>> All right. Uh thank you mayor. Great
1:05:10discussion there. Actually very helpful
1:05:11for us. Um because of the similarities
1:05:14between most of the options uh and also
1:05:16capturing the one that was selected uh
1:05:19we felt it was appropriate to discuss
1:05:20some of the key factors that would be
1:05:22used to help evaluate our direction and
1:05:25in other words begin discussion about
1:05:28our decision framework.
1:05:30So um [clears throat] under
1:05:32affordability
1:05:34certainly there's a practicality to
1:05:35consider for our customers. We want to
1:05:38continue to deliver value for our
1:05:40residents. Um, resilience and
1:05:42reliability. Uh, being a public power
1:05:44utility all these years has afforded us
1:05:46tremendous reliability compared to our
1:05:48neighboring communities. Uh, we can
1:05:50respond fast when there's an outage and
1:05:52we've been investing in our
1:05:54infrastructure and technologies over the
1:05:56years so that we can restore power
1:05:57quickly. Uh, sustainability. This topic
1:06:01has been heavily discussed in recent
1:06:02years. Uh we're all being more mindful
1:06:04of our carbon footprint and the city is
1:06:07taking this into consideration as we
1:06:08plan. Uh and finally, custom programs.
1:06:12Um in discussing the decision framework,
1:06:15I've met with um dozens of people uh
1:06:18about the categories and I have yet to
1:06:20meet anyone who likes uh the title
1:06:23custom programs. So um uh listening to
1:06:28the discussion uh at this time we would
1:06:30like to revise this topic to flexibility
1:06:33uh and that would be um flexibility to
1:06:36reflect the ability and make choices and
1:06:38changes at the customer customer and
1:06:40supplier levels.
1:06:45So um in terms of benchmarks or how we
1:06:48would measure affordability um we're
1:06:50looking at the actual total cost per
1:06:52kilowatt hour compared to KMED. It's
1:06:55also worth looking at the wholesale cost
1:06:57to gauge the efficiency of electric
1:07:00utility operations.
1:07:02Uh the measurement most commonly used in
1:07:04the industry for reliability or
1:07:06resilience is what's called SADI. This
1:07:08is a system average interruption
1:07:10duration index. And um what it is is a
1:07:13measure of the number of minutes or
1:07:15hours over a period of time that the
1:07:17average customer is out.
1:07:20Uh when measuring sustainability, we're
1:07:22looking at the metric tons of carbon
1:07:24produced by generation sources. Other
1:07:27metrics likely worthwhile tracking would
1:07:29include uh number of solar installations
1:07:32or number of EG EV chargers installed in
1:07:34our community or number of people
1:07:36participating
1:07:38um in uh some of our sustainability
1:07:41initiatives. Uh and then finally um
1:07:44custom programs again will make this
1:07:46flexibility uh measurement of success of
1:07:49providing our customers choices in
1:07:50retaining flexibility could be through
1:07:53evaluation uh evaluating participation
1:07:56in the range of offerings like our green
1:07:58energy certificate program uh or um
1:08:01uptake uh by offering demand response uh
1:08:04to our top co top customers for example.
1:08:08Uh and this would also flow through uh
1:08:10on the supplier side.
1:08:14Um we uh we're not uh really just kind
1:08:17of wanted to introduce those topics for
1:08:19tonight. Uh now that we've established
1:08:21the vision statement, we can kind of
1:08:23hone in on those a little further before
1:08:25we would bring them back to city
1:08:26council. Um but uh during this next
1:08:30section, I will recap at a high level
1:08:32the four options presented at the May
1:08:34through August city council meetings. uh
1:08:37creator joint joint action agency market
1:08:39participation with asset ownership
1:08:41market participation without asset
1:08:43ownership and selling the unit utility
1:08:47uh to another power provider such as
1:08:49Commonwealth Edison.
1:08:52So for the first option uh joining or
1:08:54creation of a joint action agency the
1:08:56primary benefits here um economies of
1:08:59scale shared resources uh governed for
1:09:02and by the members um concerns uh are
1:09:06that it requires other utilities to
1:09:08agree to the same agency requirements
1:09:10that Neapville has meaning in other
1:09:12words shared goals and significant
1:09:14negotiation required to join and have
1:09:17Neighborville specific priorities met.
1:09:20Um there would likely also be
1:09:21performance risk with size uh dependent
1:09:25mitigation and limitations on our
1:09:27ability to withdraw. Um so kind of
1:09:30working against the flexibility piece.
1:09:33Option two uh market participation with
1:09:35asset ownership. Main benefits of this
1:09:37option uh large amount of autonomy and
1:09:40the ability to consider multiple sources
1:09:42of energy generation. concerns with this
1:09:44option um uh will require options sooner
1:09:48than other choices uh to begin
1:09:50evaluating cost, funding, feasibility,
1:09:53return on investment as well as levels
1:09:55uh of market hedging. Um uh I would
1:09:59agree with Mr. Hus about uh frequent
1:10:01late rate fluctuations for customers. Um
1:10:04you know during the last couple of years
1:10:05there's been a lot of volatility in the
1:10:07market. Um and um the the higher uh that
1:10:13you hedge the more you would reduce that
1:10:16volatility. Um and then also um you know
1:10:20with respect to the energy management
1:10:22office again um those are functions that
1:10:26need to be performed. uh whether they're
1:10:28done in-house or outouse um would be
1:10:31determined I'm assuming kind of based on
1:10:33cost as well as quality. Um
1:10:37kind of uh from uh moving on to option
1:10:42three, market participation without
1:10:45asset ownership. Uh primary benefits
1:10:47here uh we won't be locked into a
1:10:49long-term energy mix. Uh we can pivot
1:10:51our power portfolio to new technologies.
1:10:54uh no long-term asset liabilities um
1:10:57meaning likely no debt would need to be
1:10:59issued. Um primary concern here um is
1:11:02really price volatility. Um uh secondary
1:11:06concern is really kind of establishing
1:11:08or hiring the uh knowledge base for an
1:11:12energy management office. Um price
1:11:15volatility um and adverse financial risk
1:11:19uh due to market fluctuations. And that
1:11:21would require um either upfront cash or
1:11:23credit to allow trading uh or uh
1:11:26entering into hedges um through uh in
1:11:29this instance purchase power agreements
1:11:32um and um we would be subject to market
1:11:35rate increases.
1:11:37Uh and then finally option four um sale
1:11:40of the electric utility. Primary benefit
1:11:43of this option
1:11:45uh is that post sale uh we no longer
1:11:48have financial risk. Uh however um we
1:11:51would expect cost to increase. Uh we
1:11:53would lose control over future rates and
1:11:56maintenance and service levels for our
1:11:57customers. Uh and we'd also lose control
1:12:00over the energy mix. Um and um we would
1:12:03anticipate a decrease in reliability.
1:12:08So, um, after the deep dive over these
1:12:11the last several months and tonight's
1:12:12overview of these options, we're hopeful
1:12:14now we can discuss which of these
1:12:16options the city council believes we
1:12:18should focus our efforts on. Um, based
1:12:22on discussions to date,
1:12:26uh, we recommend further focusing on
1:12:28option one, further focusing option one
1:12:31down to joining a joint action agency
1:12:34rather than creating a joint action
1:12:36agency. uh on option two, not focusing
1:12:39on option two due to the relatively
1:12:41small size of our demand. Um we can
1:12:44accomplish most of the pros of option
1:12:46two by utilizing purchase power
1:12:48agreements or PPAs. Um under option
1:12:51three. Uh for option three, focusing on
1:12:54option three as the city did this from
1:12:572007 to 2011 with Jiren Goldman Sachs.
1:13:00This would still allow us to dictate
1:13:02sources of generation, but instead of
1:13:05direct ownership, this would be
1:13:07accomplished through uh purchase power
1:13:09agreements for specific generation
1:13:10types. Option three does not present
1:13:14prevent us from pursuing or implementing
1:13:16battery energy storage systems as this
1:13:19is storage as opposed to generation. Uh
1:13:22and then uh finally um not focusing on
1:13:25option four due to the complete lack of
1:13:27future control over cost uh as well as
1:13:30maintenance efforts. Uh to reiterate uh
1:13:34just because an option is one in which
1:13:35we would suggest focusing on um or not
1:13:39focusing on uh as markets and
1:13:41technologies change we could easily
1:13:44revisit any of the options
1:13:50at this time. Uh based on the feedback
1:13:53we've received to date, we'd like to
1:13:56focus our options, our efforts on the
1:13:59options directed by city council. Um so
1:14:01this would be a point to discuss those
1:14:03options and which would be focus points
1:14:06and which ones um would we should uh
1:14:09devote fewer resources towards focusing.
1:14:14>> Okay, we have some questions starting
1:14:16with Councilman Hzar.
1:14:17>> Thank you, Mayor. Um, so make this easy.
1:14:20As far as the decision point, actually
1:14:23100% agree with um, Director Kger's
1:14:26recommendation of what the focus point
1:14:27should be. So if there's a call for
1:14:30hands in the air later, I will I will
1:14:31support that recommendation from staff
1:14:33as is. Um, I did have a couple of points
1:14:35I wanted to highlight. If uh, we could
1:14:37jump to slide 14.
1:14:43All right. Um, and Mr. Kger, you used
1:14:46the language verbally, which I really
1:14:48appreciated, but I just wanted to
1:14:49highlight um you know, the bottom point
1:14:53says custom programs that's going to be
1:14:55updated to something like flexibility.
1:14:58And um while it says on the screen that
1:15:01we're talking about program choices and
1:15:03programs for our customers, just as you
1:15:05said in your verbal comments, um I would
1:15:08hope in future iterations we're also
1:15:09talking about flexibility for the city
1:15:11to do things like batteries and all the
1:15:13other programs that we talked about. Um
1:15:15for slide 15
1:15:18um you also to your credit uh said this
1:15:22um verbally but I wanted to make sure
1:15:25that we highlight in all future analysis
1:15:29that we have two ways that we're
1:15:32tracking affordability. So one of course
1:15:33is the rate that our um end customers
1:15:37are paying but wholesale rate is also
1:15:40important and the reason I bring this up
1:15:42is um and you know, unless the present
1:15:46act the presentations have been pretty
1:15:48clear. So, I'll just say that um
1:15:52there have been a number of years where
1:15:54our wholesale rates have been higher um
1:15:56than they would have been through other
1:15:57sources. So, um that has a direct impact
1:16:01um downstream. We may have a year where
1:16:03we overpaid on the wholesale side. We
1:16:06were still able to deliver to our
1:16:08customers for a lower rate just because
1:16:10we're more efficient on the delivery
1:16:12end. Um, but I just want to make sure we
1:16:15always compare apples to apples, right?
1:16:17So, if we're making a decision on
1:16:19wholesale sourcing, let's compare
1:16:21compare our wholesale cost to like, you
1:16:25know, competitors that would provide at
1:16:26a wholesale price at a certain rate. Um,
1:16:29I think we get ourselves into a lot of
1:16:31trouble and have gotten ourselves into a
1:16:32lot of trouble comparing um the retail
1:16:35rate paid by consumers to different
1:16:37wholesale rates. So, those are my two
1:16:39comments, but ex excellent job of the
1:16:41presentation. and I'll support the
1:16:42recommendations of staff. Thank you,
1:16:43Mayor.
1:16:45>> Councilman McBroom.
1:16:47>> Thank you, Mayor. Um just so just to be
1:16:51clear, um your recommendation is we we
1:16:56don't focus on two and four. Is that
1:16:58right?
1:17:00>> Don't don't focus on which one?
1:17:01>> On the two two and four options. Uh
1:17:04>> uh yeah. Yeah. I think option two um all
1:17:07the everything uh that we can accomplish
1:17:09under option two I think we can do under
1:17:11option three. Um also would recommend uh
1:17:15not pursuing option four when we had the
1:17:18uh discussion at the council meeting. Um
1:17:20it did not seem like um there was a lot
1:17:23of support for that uh at the council
1:17:26level. Uh Neighborville has always been
1:17:28a community that values local control
1:17:31and option four is the only one where
1:17:34you you pretty much give up complete
1:17:36control. Uh and then on option one the
1:17:39only difference would be um instead of
1:17:41kind of reinventing the wheel with by
1:17:44creating a new joint action agency um if
1:17:47we decide to pursue that path uh select
1:17:50a joint action agency that's already in
1:17:52existence.
1:17:53>> Okay. So fi find an existing joint
1:17:55action agency. Um and and corre remind
1:18:00me when we talked about the timeline
1:18:03option one was a like a next year
1:18:06decision like a June or was that forming
1:18:09our own joint action agency?
1:18:11>> Uh you know next year would probably be
1:18:13a forming um because all of these are
1:18:15really kind of like new evolutions.
1:18:18um you know the kind of like the time
1:18:21commitments are are really estimates. Um
1:18:23our hope is that uh as uh next uh next
1:18:28spring and summer as we work through um
1:18:33our uh utility rate study um that we
1:18:36will discuss all of the different
1:18:37options and um the implications on rates
1:18:41that you know selecting uh any of these
1:18:44options might have on us.
1:18:45>> Okay. Thank you. And so, uh, my
1:18:48understanding is kind of pushing this
1:18:50decision off again, we're waiting for a
1:18:52rate study, uh, that'll come in June of
1:18:55next year. Um, and that'll give us some
1:18:57data and that
1:19:00option three or market participate
1:19:01option two, three together, whatever.
1:19:04Um, uh, that that's going to involve
1:19:07planning for upfront cash and a rate
1:19:09stabilization fund. And is that is that
1:19:12what we're waiting on? We're waiting to
1:19:13see what impact that investment would
1:19:17have when we would [clears throat] have
1:19:19to voluntarily raise our own.
1:19:21>> Yeah, you know that's correct. Um
1:19:23depending on which option um is uh
1:19:28selected um will impact the level of
1:19:31cash reserves or deposits
1:19:34um or shity um or in some cases um you
1:19:38know even debt that would need to be
1:19:40issued.
1:19:41>> Okay, just to be even more clear. So the
1:19:42rate study that we get back in June of
1:19:44next year is going to forecast what we
1:19:48may have to pay in 2028 in increased
1:19:51rates if we were to pursue uh market
1:19:54with or without asset generation.
1:19:56>> That that's correct.
1:19:57>> Okay.
1:19:59Um
1:20:01I la last question as far as market
1:20:04participation with asset ownership. This
1:20:06would be purchasing something. Do we
1:20:08have any idea like cost and would that
1:20:10be small, modular, nuclear? What would
1:20:12that
1:20:13>> you know it it wouldn't take anything
1:20:16off the table. Um you know personally I
1:20:18think um that in the future small
1:20:22modular reactors are going to play a a
1:20:24critical role. Um uh however I think um
1:20:28it's too early for us to really kind of
1:20:30like head down that path. Um but um my
1:20:34thought with uh if the council said hey
1:20:37yeah we would we do like uh small
1:20:39modular reactors um that instead of you
1:20:42know owning 2% of one uh we would simply
1:20:46buy um either a block or load following
1:20:49um you know megawatt hour of of power
1:20:53produced by that small module reactor
1:20:56and accomplish the same thing.
1:20:57>> And then just one last comment mayor if
1:20:59I can. Um so uh
1:21:06all right so timeline June rate study um
1:21:10I'm losing my train of about here at a
1:21:12point uh oh so so we've gone through all
1:21:15these options and and some of them have
1:21:18attractive features they all have
1:21:21risk some of them kind of frightening
1:21:23risk to me and uncertainties
1:21:26um but I'm having an open mind and you
1:21:29you know, we're going to delay more and
1:21:30we're going to look, I guess, look for a
1:21:31recommendation from you guys after we
1:21:34narrow it down for you. But, you know,
1:21:36IMEA, I don't even know if they're
1:21:38interested in us being a partner. I I
1:21:40mean, I don't know. Um, and we we really
1:21:43we had we got a letter from the previous
1:21:45CEO that was very, hey, we've like
1:21:48working with you, and it was nice
1:21:49letter. Um, they have a new CEO now. I'm
1:21:53interested in what what they think and I
1:21:55I think it's kind of it's it's kind of
1:21:58interesting that we've gone through this
1:21:59whole process. It's gone on for two
1:22:01years and I has never sat at that podium
1:22:04and I'm curious if they even want us to
1:22:05be a partner and if they do make their
1:22:08case for it. Um because we have people
1:22:10come in here every single meeting and
1:22:12debate whether IMEA can do this or they
1:22:14can't do this or IMEA is bad or IMEA is
1:22:17good. We haven't heard from the people
1:22:19that have been delivering electricity to
1:22:21this for 15 years and and we're with for
1:22:22the next eight almost almost nine years.
1:22:25Um that's something that I would I would
1:22:28encourage council to consider and I may
1:22:30be bringing it up in um in our future uh
1:22:33regular meeting. Uh and I don't even
1:22:34know would they be willing to you
1:22:36probably don't know the answer to that
1:22:37but I think it's something that needs to
1:22:39be explored. Um, so
1:22:41>> yeah. Um, yeah, on that point, um, I I
1:22:44do not believe that their absence is due
1:22:47to lack of interest. I think they're
1:22:49simply kind of respecting the decision
1:22:51council made to say, "Hey, we're going
1:22:53to take a pause on negotiation." So, um,
1:22:57I I I think they're kind of honoring
1:22:59council's wishes. If council wanted to
1:23:01have them, you know, come and present
1:23:03and discuss, uh, my guess is that they
1:23:05would be happy to.
1:23:08>> Councilman Wilson. Thank you, mayor. Um,
1:23:10yeah, a couple things I guess to, you
1:23:12know, I guess this ties into the slide
1:23:1714. Um, when we looked at the vision
1:23:20statement and then, you know, looking at
1:23:22our decision framework where again like
1:23:26we just talked about sustainability and
1:23:27the first bullet point, obviously there
1:23:29could be more that fall into this would
1:23:31be reduction of greenhouse gases.
1:23:33Obviously, this is just one, but um to
1:23:38me, these things may end up the vision
1:23:41may end up conflicting where you look at
1:23:44this, and I'm sure there's some people
1:23:46here uh in the audience that might like
1:23:49this and might not, but
1:23:52when when I see this, I I I think, well,
1:23:54how much is this going to cost? Because
1:23:57I I think some people here would go,
1:23:59okay, let's
1:24:01have our own solar farm or whatever. And
1:24:03then, you know, if we hearken back to
1:24:05uh, you know, some of Nest's
1:24:07presentations when we're looking at
1:24:09Lazard's
1:24:10own PDFs that they're citing, and those
1:24:12were going to cost, I I can't remember
1:24:14the exact numbers, but somewhere
1:24:16around$167
1:24:18compared to 30 to $35 of uh cold
1:24:22generation.
1:24:23Um, I I just have concerns with that and
1:24:26the fact that they might conflict with
1:24:27it. So that's just my immediate thoughts
1:24:30of seeing some of these
1:24:33um things with regard to um
1:24:37the decision framework here. Um, and
1:24:40then I guess to go to slide 16. Um,
1:24:47for option one, uh, I guess you you
1:24:50already answered quite a few questions
1:24:53that I had, uh, that Councilman McBroom
1:24:55was asking, but, um, say after we take a
1:24:58look at this rate study and then, um,
1:25:01council, whoever that whoever that is at
1:25:04the time,
1:25:06um, goes, "Okay, well, given the rate
1:25:08study and what demands we might have,
1:25:11could option one potentially be going,
1:25:13oh, hey, We had a good deal with IMEA.
1:25:17Let's bring can we bring them back and
1:25:20restart negotiations if there's will
1:25:21from council. Could that I guess could
1:25:24that be an option here?
1:25:25>> Uh that could be one of the outcomes.
1:25:27Absolutely.
1:25:28>> Thank you, Councilwoman Jane.
1:25:31>> Yeah. Thank you, Mayor. Um just a few
1:25:34points um for clarification. First of
1:25:38all, I appreciate us moving from
1:25:41eliminate to focus on the options. I I I
1:25:45think that's reflective of where many of
1:25:48us are where we're what we're thinking.
1:25:50Um, so
1:25:55I have a little bit of confusion between
1:25:58option two and three and making a
1:26:00decision about focusing our efforts. I
1:26:03guess I want clarification on what we
1:26:05mean by focusing. So let's say we voted
1:26:08that let's say theoretically we voted
1:26:10for option three and one to be the
1:26:13focus. Um what does that mean for next
1:26:16steps for staff?
1:26:19Yeah. Um sure thanks for the question.
1:26:22Um you know uh what what I would take
1:26:27that to mean would be hey you know we
1:26:29look at market participation
1:26:31um we are going to want to hedge to some
1:26:34extent and that our priority in looking
1:26:37at hedges would be power purchase
1:26:39agreements as opposed to um percentage
1:26:43share ownership of actual assets. So um
1:26:46yeah two and three are actually very
1:26:48close. Um it really comes down to kind
1:26:51of like a lease or buy um scenario. Um
1:26:55you know where option two would really
1:26:57be the buy and option three would be
1:26:58kind of like the lease. um from uh you
1:27:01know from a flexibility standpoint uh I
1:27:04think option three has the that
1:27:06advantage over option two because um if
1:27:09we do uh have asset ownership um those
1:27:12are typically like 15 20 year deals and
1:27:16is going to you know reduce our
1:27:18flexibility moving forward whereas with
1:27:20purchase power agreements um you know
1:27:22that's going to be more in kind of like
1:27:24the three to five year time frame. So
1:27:26from a staff bandwidth perspective, do
1:27:29you think there's um a lot more involved
1:27:33with exploring option two with option
1:27:35three? Um and part two to that question
1:27:39is is that exploration or focus being
1:27:42done between now and the rate study or
1:27:45post rate study publication or
1:27:47reporting?
1:27:49>> You know, um right now I'm thinking that
1:27:51would be kind of like post rate study.
1:27:54um and um you know really just kind of
1:27:57focusing on the different options and
1:27:59the impact as it relates to rates for
1:28:01the next you know six nine months.
1:28:04>> Okay. And last question. So between now
1:28:07and June do you foresee us um working on
1:28:12the decision framework and the mission
1:28:14statement in preparation for that
1:28:17exercise when it comes time.
1:28:20>> Uh short answer yes. Um I don't know
1:28:23exactly what that looks like. I would
1:28:25like to hone in on decision framework
1:28:28and then once we have that I think we
1:28:30could move to mission statement. Um you
1:28:32know I haven't det I haven't figured out
1:28:34what uh the best process for that
1:28:37whether you know that would be a
1:28:38separate workshop or whether that would
1:28:40be um reports that would be a component
1:28:43of a city council meeting. Um but yes,
1:28:45we would be um you know providing doing
1:28:49research and providing that information
1:28:51for council so that um when the rate
1:28:53study comes, you know, everybody is up
1:28:56to speed and and ready to go on it.
1:28:58>> Okay. Thank you,
1:28:59>> Councilwoman Gibson.
1:29:01>> Uh thank you. I I think what I had to
1:29:03say largely mirrors what Councilwoman
1:29:05Jane just said. I'm just I'm concerned
1:29:07that the next step slide 22 says direct
1:29:10staff further research and um I feel
1:29:13like there's some really big steps in
1:29:14the middle of the decision framework.
1:29:16While I recognize that there's bullets
1:29:18in this presentation
1:29:20um I think the next step is that we need
1:29:23to talk about the decision framework as
1:29:26a council. Um because coming up with the
1:29:28five pillars tonight even highlighted
1:29:31that we all have different
1:29:32understandings of each of those pillars.
1:29:34So, I just want to make sure that we
1:29:36aren't just taking the decision
1:29:39framework from tonight's presentation
1:29:40that this is going to come back to
1:29:42council before we get um the summer
1:29:462027.
1:29:47>> Yeah, that's absolutely correct. Uh the
1:29:49decision framework was not, hey, we're
1:29:51locked in on this now. It was really to
1:29:53kind of introduce the concept and also
1:29:56have um some discussion on council's
1:29:58part. Um, you know, I I don't want
1:30:00people to think that this means that,
1:30:02oh, you know, you know, we're going to
1:30:04do do go pencils down and not do
1:30:06anything until the rate study because
1:30:08that's absolutely not the case. Um,
1:30:10decision framework um mission statement.
1:30:13Um, we are continuing our um costbenefit
1:30:16analysis for battery energy storage
1:30:18systems. So, there will be um touch
1:30:22points with city council and reports to
1:30:25city council as as time progresses.
1:30:28Okay, great. Thank you. And to that
1:30:29point,
1:30:31you know, for the four options, yes. Um,
1:30:36the only one I would be comfortable
1:30:37eliminating now is the sale of electric
1:30:39utility because that seems like
1:30:41no-brainer. It's the opposite of local
1:30:42control and flexibility. Um, for the
1:30:44other three, you know, I hear your
1:30:46points about asset ownership without
1:30:48asset ownership. Um but I I just I'm not
1:30:52comfortable eliminating any of those
1:30:53until we've uh as a council come to a
1:30:56consensus on the decision framework
1:30:58those decisions.
1:30:59>> Yeah. Um you aren't alone with that.
1:31:01That's why we uh we kind of pivoted um
1:31:04uh after it went out from kind of like a
1:31:07straight up elimination, you know, take
1:31:09it off the table to, you know, kind of
1:31:11more of a prioritization and more of a
1:31:13focus. Um that so that was that was one
1:31:15of the impacts of that. Um and just for
1:31:19my thinking going forward because these
1:31:22options
1:31:24we have more we would have more control
1:31:26and flexibility on it. The option we
1:31:28choose even initially in 2035 could be
1:31:32different from the option we choose in
1:31:342040 2045 2050. Correct.
1:31:36>> That that is absolutely correct.
1:31:38>> Okay. Thank you
1:31:40>> Councilman Hoszar second round.
1:31:42>> Thank you mayor. And just following up
1:31:44on um that point um I just wanted to
1:31:48give a shout out to Mr. Grath and you
1:31:51know and with his recovery hope he's
1:31:52doing well. He's done a a wonderful job
1:31:54leading his team and um also you know
1:31:58the fact that we are focusing on options
1:32:01one and three I think is a testament to
1:32:03the electric department and the faith we
1:32:04have in our employees um that that
1:32:06option isn't what we're focusing on. So,
1:32:09um, I just want to make sure that if
1:32:10they're out there listening, they know
1:32:12that we up here appreciate everything
1:32:14the department does every day and what
1:32:16an amazing community we have. So, thank
1:32:17you, Mayor Council White.
1:32:19>> Yeah. Thank you. Just a few points. Um,
1:32:23um, the IMEA and not having I mean, we
1:32:26haven't heard from them uh was was was
1:32:29stated up here, but I I was kind of
1:32:31wondering that myself. I mean there's we
1:32:34have an open meetings uh format a public
1:32:37u you know where they could come up and
1:32:39speak if they'd like. So uh for public
1:32:41comment as a minimum uh if not just a
1:32:44formal invitation. So um I never have
1:32:47taken that off the board. I'd like to
1:32:49hear what they'd have to say. Um anyway
1:32:52also affordability. Um I know I think
1:32:55the metric you're looking at is
1:32:56comparing it to KMED. Um and maybe
1:32:59that's just an example of who we can
1:33:00compare it to. probably be the main one
1:33:02I get, but um maybe other joint action
1:33:05agencies that are in our vicinity. Um I
1:33:08would like to see it expand a little bit
1:33:10above and beyond just the Cameed
1:33:12comparison.
1:33:13>> Yeah, we we could absolutely um uh
1:33:15include um other Illinois communities uh
1:33:19that are in different joint action
1:33:20agencies um and and include their rates
1:33:23as well.
1:33:24>> Okay, good. Um uh and I'll go back to
1:33:27sustainability being part of the
1:33:29mission. I mean, I I guess We I I guess
1:33:32we need to look at SEA. We we've been
1:33:34required to know get off of fossil
1:33:37fuels. I think sustainability
1:33:39um from that standpoint should
1:33:41definitely be in there. Um we need to
1:33:43maybe put some parameters around what
1:33:45and defining what we're looking at, but
1:33:47the greenhouse piece of this is not our
1:33:50really not even our call as we've been
1:33:51told that we have to do that. So unless
1:33:54something changes, but as of now that's
1:33:56that's what's uh what we're living with.
1:33:59Um the other thing I would ask about
1:34:01with option two and three
1:34:04um I see some advantages of option two
1:34:06but it it I mean owning an asset that's
1:34:09gets expensive. I get that piece but it
1:34:12also pro I would think provides a hedge
1:34:15for us if we own some portion of
1:34:18something. I I I don't know. I'd like to
1:34:20hear your thoughts there. Um and and
1:34:23with that in mind, do would it be
1:34:25important for us to have a hedge or
1:34:26would or would three somewhat provide
1:34:28that as well?
1:34:30>> Um uh sure. Um I I think it uh I I think
1:34:36it's very important that we would have
1:34:38some form of hedge whether that be
1:34:40actual asset ownership or PPA or um uh
1:34:44power sales contracts
1:34:46um just uh to really protect our
1:34:51customers from a lot of fluctuation.
1:34:54you know, um option two and three, the
1:34:57difference, you know, between kind of
1:34:59like the buyer rent, um uh can work both
1:35:03ways. Uh you know, if you if you
1:35:05purchase a highly performing asset, um
1:35:08and you're locked in for 20 years and
1:35:10rates go up, um you know, you're in
1:35:13great shape. Uh if you purchase a high
1:35:15performing asset and some new technology
1:35:18comes on that's much cheaper, you know,
1:35:20you're you're stuck for 15 or 20 years
1:35:22before you could get out of it. So, um
1:35:24it really can cut both ways. Um but, um
1:35:28I under either of those scenarios, I
1:35:30think that we should have either
1:35:32ownership um or contracts that would
1:35:35kind of hedge our demand.
1:35:39>> Councilman Kelly,
1:35:40>> thank you, mayor. Uh thank you to staff.
1:35:42Good presentation tonight and good
1:35:44discussion up here. I think it seems
1:35:45like we're in a in a positive direction,
1:35:47I think, uh moving forward. Um just one
1:35:50quick question on the four options. I
1:35:54appreciate the pivot. It sounds like
1:35:55we're talking more about focusing than
1:35:57eliminating, but I've heard a little bit
1:35:59mixed on on lack of focus or eliminate
1:36:03on option four. Um the sale of the
1:36:06electric utility, it it seems like I I
1:36:08don't think I've heard anybody say we
1:36:09want to leave that on the table and I
1:36:11just want clarity, I guess, from staff.
1:36:13Are we is that remaining in are all
1:36:16remaining or is option four potentially
1:36:18off the I'll tell you my preference
1:36:19would be to eliminate option four
1:36:21entirely. I I don't think that makes any
1:36:23sense for us. The other three I I think
1:36:26the discussion I've heard I'm happy
1:36:28with. But I'm just curious from staff's
1:36:29perspective, would you plan on spending
1:36:31any time any resources evaluating option
1:36:34four or not at all at this point?
1:36:36>> You know, ba based on council
1:36:38discussion, um I I don't feel it's
1:36:40strong enough to eliminate, but it is
1:36:41not our intention to pursue um
1:36:44discussions or do any additional
1:36:46analysis at this point on option four
1:36:49unless council directed us otherwise.
1:36:51All right, fair enough. Thank you,
1:36:54>> Mr. Kger. On option number two, the
1:36:56asset ownership piece, are you including
1:37:01the bez under asset ownership or would
1:37:04that be a potential option in three
1:37:07since the bez technically is not a
1:37:09generator
1:37:11per se of of electricity? Is that
1:37:14>> Yeah, I um I would I I think that uh a
1:37:18battery energy storage system, you know,
1:37:20could fit under option one, two, or
1:37:22three. Uh because um it's not uh it is
1:37:27ownership of an asset, but it is not
1:37:30ownership of a generating asset. The
1:37:32generating asset would still be out
1:37:34there if we had battery energy storage
1:37:36system. um you know, we could we could
1:37:38charge it up um and discharge it um and
1:37:41it wouldn't violate really any of the
1:37:43premises of the first three options.
1:37:45>> And when it comes to asset owner
1:37:47ownership, you either have to find a
1:37:49site for the asset that's going to be
1:37:51the generator of power in your city or
1:37:54find a place outside of your city. So
1:37:56Neighborville could potentially
1:37:59be investing in wind, solar,
1:38:04u nuclear,
1:38:07gas fired generation. I mean, there's
1:38:10only so many options out there. But if
1:38:12you can't host enough generation in your
1:38:14city, you have to buy it someplace else.
1:38:16Is that your
1:38:17>> Yeah, that is correct. And you know, the
1:38:20kind of the benefit of having Well, you
1:38:22know, having it on site kind of cuts
1:38:23both ways. um you know you can cut down
1:38:26on transmission costs. Uh however um
1:38:29most generating assets are not really um
1:38:32kind of sought after neighbors. Um uh so
1:38:37you know I think the from a practical
1:38:39standpoint uh it would really we would
1:38:42really be looking at a partial ownership
1:38:45of an asset that's located outside of
1:38:47our borders.
1:38:49>> Okay. All right. council. The goal here
1:38:52is to try to um
1:38:55give our professional staff some sort of
1:38:57guidance on what they should be focused
1:38:59on. Um I think the easiest way to run
1:39:02this is take the affirmative position
1:39:04and I'm going to be going option by
1:39:06option and we're looking for a simple
1:39:08show of hands in the air. Majority um
1:39:11simple majority will drive that
1:39:14particular option as a viable option
1:39:16that the city should continue to pursue.
1:39:19Um, and if there's not a simple majority
1:39:22on an option, then that will be guidance
1:39:24to not pursue. So, we'll start with
1:39:27option one.
1:39:30Hands in the air in support of option
1:39:32one.
1:39:37Option two.
1:39:43>> All right. Five hands. Mayor,
1:39:45>> option three.
1:39:50Eight hands also
1:39:52>> option four.
1:39:58So no hands.
1:39:59>> Okay,
1:40:03I believe that's all the questions we've
1:40:05been asked to answer tonight.
1:40:08>> The um uh you know kind kind of wanted
1:40:11to talk about uh next steps. Uh, mayor
1:40:14um really appreciate council's time,
1:40:16very thoughtful discussion. Um, uh, and,
1:40:20uh, think we've, um, really made some
1:40:23great strides in in figuring out our
1:40:26path forward. Um, I, you know,
1:40:29appreciate the, um, you know, the areas
1:40:31to focus on from an option standpoint
1:40:33and, uh, we will direct our staff
1:40:36accordingly. Um you know finally in uh
1:40:392027 um we will be doing a new rate
1:40:42study um uh and recommendations will be
1:40:45presented and um we will present those
1:40:48in conjunction with the evaluation of
1:40:51these remaining options. Um and with
1:40:53that would just like to thank everybody
1:40:55for their time tonight and we'd be happy
1:40:56to answer any additional questions.
1:41:00Thank you for all of your preparation to
1:41:02all the speakers who came forward
1:41:03tonight to the city council for all your
1:41:05participation tonight. I thought it was
1:41:07a very fruitful and uh productive
1:41:09discussion. With that our workshop has
1:41:11ended.
```*