High school tennis court renovation

  • 2026-09-24 - Board of Education - Work expected substantially complete by the end of the following week; surfacing to begin midweek and remaining lighting equipment due the next Thursday, with some work possibly redone around the lights.
  • 2026-09-10 - Board of Education - Student representative noted the courts are under construction and will give teams an updated space (from auto-captions).
  • 2026-08-13 - Board of Education - Concrete pour set for the next morning (about 40 trucks), then 28 days of curing before the top coat; parking lot paving on schedule for school start (from auto-captions).