Elementary School Roof Replacement Plans

At a glance

  • What: Final plans and cost estimate for an elementary school roof replacement are to be submitted to the state Department of Administrative Services.
  • Where it stands: Board unanimously authorized signing the state review form on September 24, 2026.

Sources

Log

  • 2026-09-24 - Board of Education - Motion carried unanimously to authorize the chair and superintendent to sign the state form.
  • 2026-09-14 - Town Council — Strong School roof about 95 percent complete ($4,200 change order); high school roof nearly done.
  • 2026-08-13 - Board of Education - Strong Elementary roof about 90 percent complete, on schedule and under budget (from auto-captions).
  • 2026-08-10 - Town Council - Subcommittee reported the Hatton School roof 88% complete on July 31 and due before students return; a masonry change order of about $3,885 and a $461,985 invoice were approved (from auto-captions).