At a glance
- What: Construction contract for replacing elevators at the San José airport terminal.
- Where it stands: RES2026-307 adopted September 29, 2026 (10-0-1, Mayor Mahan absent), on a motion by Councilmember Doan seconded by Councilmember Candelas.
- Next: Director of Public Works awards to the lowest responsive bidder after deciding any protests.
Terms
Contract not to exceed $9,415,000, plus a 15% contingency; the Public Works Director may decide timely bid protests. Brian Darby commented virtually; position not recorded.
Sources
- City Council minutes, September 29, 2026: https://sanjose.legistar.com/View.ashx?M=M&ID=1423868&GUID=41519D35-C66F-4C8A-94B9-E0461B3C0025
Log
2026-09-29 - City Council