DPW Complex Construction Change Orders
At a glance
(From auto-captions; names and numbers may be misheard.)
- What: Construction management change orders for the Department of Public Works complex.
- Where it stands: Change order three, about $3.2 million, approved August 11; the project manager called it the final base GMP.
Log
- 2026-08-11 - Board of Contract and Supply - About $1.3 million final base-scope GMP amendment plus under $2 million in change orders, mainly an added truck wash; about eight months of construction remain (from auto-captions).