Public Works Facility Project

At a glance

  • What: a new Town public works building, designed by Metropolis Architecture (Marty Marion, see Marty Marion) under a Building Committee led by Brock Hall.
  • Where it stands: ongoing. Design about 50% documented as of September 22.
  • Next: Council said it intended to vote on the design October 5; the October 5 agenda lists the item, and no minutes are posted yet.

The project

  • Meeting space large enough for both boards, office and storage space for park staff, public restrooms, curb and gutter, paving and two picnic shelters at the Town Park.
  • Council chose traditional ground-up construction over a pre-engineered metal building to match the Town Hall and park.
  • Funding is by capital project ordinance from fund balance rather than the annual budget.

Key figures

  • Metropolis agreement $145,400: basic services for the municipal building and parking $97,650; two picnic shelters and parking $47,750.
  • Project Ordinance 26-01, April 6, 2026.
  • Amendment No. 1 (Ordinance 27-02 on the document, 27-01 in the motion) added $9,615 for geotechnical borings by Certerra, raising the project to $155,015, September 8, 2026.
  • Construction costs are not yet estimated; no construction ordinance has been adopted.

Status and next steps

  • Design about 50% documented as of September 22.
  • Picnic shelters about 30 by 40 feet, scissor trusses.
  • Construction documents 8 to 12 weeks after the geotechnical report, then at least a 30 day public bid.

Log

  • 2026-10-05 - Town Council - Agenda lists the Public Works Facility project with Metropolis (agenda only).
  • 2026-09-22 - Town Council Vision Session - Marion reported design and specs about 50% complete, Certerra geotechnical report due in 3-4 weeks, Council satisfied and planned to vote October 5.
  • 2026-09-08 - Town Council - Council amended the project ordinance by $9,615 for geotechnical services (total $155,015; McAlpine/Leonard), conditioned on consulting Jim Lanik.
  • 2026-07-13 - Town Council - First 3D rendering of the building shared; next steps shelter renderings and geotechnical soil testing; no action.
  • 2026-04-06 - Town Council - Council approved the $145,400 Metropolis agreement and Project Ordinance 26-01 unanimously.
  • 2026-02-19 - Town Council Vision Session - Hall presented the Metropolis fee proposal and recommended traditional construction and a project ordinance once costs are known.
  • 2026-01-05 - Town Council - Building Committee update: ground-up construction recommended; full Metropolis proposal expected by February.