Howard Street Reconstruction

At a glance

  • What: The USDA-financed downtown reconstruction of Howard Street continues; Council heard business impacts and a proposal to reverse the street's direction.
  • Where it stands: Council heard business concerns on September 9, a direction proposal on September 23, and on October 14 reached consensus to finish the current project first.
  • Next: Possible work session on business impacts; none confirmed.

Details

  • September 9: discussion of adding the topic to a work session, temporary business signage, a Downtown Boone Development Association marketing push, and asking the Town Manager to talk to NCDOT about traffic flow.
  • October 14: the Town Attorney said the Town is contractually bound because of the USDA financing.

Sources

Log

2026-10-14 - Town Council

  • Direction-reversal proposal heard. Attorney said the Town is contractually bound (USDA financing); consensus to finish the current project first.

2026-09-23 - Town Council

  • Public comment on a proposal about Howard Street direction.

2026-09-09 - Town Council

  • Requested appearance and public comment on construction impacts on business; signage, marketing and NCDOT traffic flow discussed.