What: A new EMS base at Government Circle; concepts of $28 to $30 million in three options.
Where it stands: Consensus on one-story Option Three (October 5); McGill/Moseley design contract amendment approved October 19 (about 6 months of design).
Next: Construction is targeted for late 2027 and completion mid-2029, pending a USDA loan and state grants.
Details
Public comment on September 8 raised a site alternative on Highway 221 versus Calvert Street, with a flooding concern.
The board wanted medic feedback on the concepts on September 21.