What: A roughly $6.5 million restructuring of the county transfer station; on 2026-11-02 the Board awarded construction to Bryant's Contracting LLC.
Where it stands: Construction contract awarded 2026-11-02 (draft minutes): low base bid $3,634,500; with an allowance, an alternate and a 15 percent contingency, $4,507,425.
Next: Construction under the award; the gray-bat environmental review was noted 2026-10-19.
Details
Manager reported on 2026-09-21 that more than $5 million of the roughly $6.5 million was secured.
Bids opened October 5; three bids were being tabulated on October 19.
Minutes for 2026-10-05, 2026-10-19 and 2026-11-02 are unapproved drafts; items marked draft may change on approval.
Construction awarded to Bryant's Contracting LLC: low base bid $3,634,500; $4,507,425 with allowance, alternate and 15% contingency (draft minutes, not yet approved).