181 East Hollis Street Transit-Oriented Building

At a glance

  • What: a 48-unit, 5-story transit-oriented building at 181 East Hollis St (address to become 64 Crown St).
  • Where it stands: Front-setback variance approved 4-0 on September 22; site plan approved 8-0 with waivers on October 15.
  • Next: Construction.

Details

  • See the log below for each meeting where this came up.

Sources

Log

2026-10-01 - Planning Board

  • Staff announced the site plan application was postponed to the October 15 meeting at the applicant's request.

2026-10-15 - Planning Board

  • Unanimously approved a waiver, dimensional modifications (floor area ratio 2.1 where 2.0 applies; 70 ft cumulative driveway width across three curb cuts) and the final site plan for the five-story, 48-unit building with podium parking, subject to conditions including a $4,750 traffic contribution to the Main Street corridor.

2026-09-22 - Zoning Board of Adjustment

  • Front-setback variance for the 48-unit transit-oriented building at 181 East Hollis St approved 4-0.