Shank Painter Road Reconstruction
At a glance
- What: Property actions for the Shank Painter Road and Route 6 reconstruction project.
- Where it stands: Both items passed on the consent agenda: an Order of Taking of temporary and permanent easements for public way purposes (July 27) and Certificates of Donation for Town-owned parcels for the project (August 24).
Sources
- Select Board minutes, July 27, 2026 (regular): https://www.provincetown-ma.gov/Archive.aspx?ADID=34981
- Select Board minutes, August 24, 2026 (regular): https://www.provincetown-ma.gov/Archive.aspx?ADID=35208
Log
2026-08-24 - Select Board
Certificates of Donation for Town-owned parcels approved on consent.
2026-07-27 - Select Board
Order of Taking of temporary and permanent easements approved on consent.