Town Hall ADA Ramp
At a glance
- What: Replacement of the Town Hall access ramp with a new, fully enclosed, ADA-compliant ramp.
- Where it stands: Design and cost estimate completed by CSS Architects. Estimated total cost is $829,578, assuming construction begins in July 2027.
- Next: No funding vote is recorded in these minutes.
Detail
- The project includes demolishing the existing ramp and building a new enclosed ramp to improve accessibility for all visitors.
- Reported by Town Manager Leduc in his report; no motion was taken.
Sources
- Board of Selectmen minutes, August 4, 2026 (read from a scanned document): https://www.oxfordma.us/AgendaCenter/ViewFile/Minutes/_08042026-1511
Log
2026-08-04 - Board of Selectmen
Town Manager report: design and estimate done; $829,578 total if construction starts July 2027.