Data center electricity costs for ratepayers

At a glance

Based on human-uploaded captions; names may still contain errors.

  • What: How to keep data center electricity demand from raising costs for other customers or straining the grid, discussed in the Docket No. 1718 hearing.
  • Where it stands: discussion only at the October 19, 2026 hearing; no proposal or vote.
  • What's next: possible work with the state utility regulator on large load tariffs; Planning's thresholds are expected to be based largely on power.
  • Part of Proposed ban on data centers.

Points raised

  • Ayse Coskun proposed grid impact assessments, efficiency and power flexibility standards, and measurement and verification; flexible data centers can cut load at peak hours so utilities need less costly firm capacity.
  • Data center capacity is expected to roughly double in a few years; efficiency alone tends to raise demand.
  • A panelist recommended large load tariffs so large customers pay for the infrastructure and speculative projects do not leave costs with ratepayers; another raised decommissioning costs after an AI downturn.
  • Boston's net zero zoning, emissions ordinance and specialized energy code would require any new data center to be efficient and net zero on day one, according to a city panelist.
  • Councilors raised the East Boston substation fight as a reminder that grid capacity is already contested.
  • Tristan Thomas said utilities have received close to 5,000 MW of data center inquiries statewide, many speculative.

Sources

State context

State-level rules, including Executive Order 658 and a statewide list of local moratoriums and bylaws, are on Massachusetts Data Center Policy.

Discussion time

About 15 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-19 - Planning, Development and Transportation Committee 15