Meeting Event Center Project
At a glance
- What: Downtown Meeting and Event Center, funded with legislatively appropriated money and developed with Red Draw Development; construction expected to begin in the fall or December 2026.
- Where it stands: July 27: the Board approved a Phase 2 construction-services amendment with OHM Advisors ($121,539.51). August 10: staff reported the P3 Board asked for changes that the City is resubmitting.
- Next: Resubmission to the P3 Board; construction in December. Price said to be locked until then.
- Freshness: Possibly stale: the newest information here is from August 2026. Later Board agendas (Sep 28, Oct 12) were image-only and were not read, so any later action is not reflected.
OHM Advisors technical support consultant (July 27)
- The City advertised an RFQ on January 15, 2025 and received two responses; the selection committee met February 19, 2025 and chose OHM Advisors of Frankfort. The Board approved the original services agreement April 28, 2025.
- For Phase 2 (construction, expected to begin this fall), staff asked for Agreement Amendment 1 at $121,539.51, paid from the legislatively appropriated funding for the Center.
- Resolution No. 10, 2026 Series: moved by Commissioner May, seconded by Commissioner Smith-Willis; roll call all five members present voted yes (Commissioners Richardson, Unger, May, Smith-Willis and Mayor Wilkerson), none against.
Work session update (August 10)
- City Manager Monroe described the previous meeting with the P3 Board and the changes it requested; the City is working with Dinsmore and Shohl on changes to resubmit.
- Chuck Knowles spoke about the timeline and a price increase of 7% of total project cost. The price should be locked until December construction, and no change orders are expected from Red Draw.
- Megan Walsen and Garyon Dening of Red Draw said they are waiting on the P3 Board; Washington Street will run parallel to the Center.
Sources
- Board of Commissioners regular meeting minutes, July 27, 2026: https://frankfort.ky.gov/AgendaCenter/ViewFile/Minutes/_07272026-829
- Board of Commissioners work session minutes, August 10, 2026: https://frankfort.ky.gov/AgendaCenter/ViewFile/Minutes/_08102026-831
Log
2026-08-10 - Board of Commissioners Work Session
City Manager Monroe and Chuck Knowles reported P3 Board changes, a 7% cost increase and a December construction start.
2026-07-27 - Board of Commissioners
Resolution No. 10 approving OHM Advisors Phase 2 Amendment 1 ($121,539.51) adopted 5-0.