Fort Boone Pump Station Design Amendment

At a glance

  • What: Amendment No. 10 to the Palmer Engineering Company contract for $12,530.00 of added flood design work on the Fort Boone Pump Station.
  • Where it stands: Approved on consent July 27, 2026, 5-0.
  • Next: Included in the upcoming contractor change order to ease FEMA reimbursement; budgeted for construction in FY26-27.
  • Freshness: Possibly stale: the newest information here is from August 2026. Later Board agendas (Sep 28, Oct 12) were image-only and were not read, so any later action is not reflected.

Details

  • Amendment No. 9 ($89,435.00) was approved June 23, 2025. The contractor's questions about conduit penetrations through the concrete slab prompted additional design effort.
  • Consent calendar moved by Commissioner May, seconded by Commissioner Richardson; all five members present voted yes (Commissioners Richardson, Unger, May, Smith-Willis and Mayor Wilkerson), none against.

Sources

Log

2026-07-27 - Board of Commissioners

Amendment No. 10 approved on consent, 5-0.