La Colonia Alleyway Resurfacing

At a glance

  • What: the Citywide Alleyway Resurfacing - La Colonia Neighborhood Alley Reconstruction Project (Specification No. PW 25-121) with Toro Enterprises, Inc.
  • Where it stands: the 2026-11-17 consent agenda recommends an additional $480,000 in contingency authority (new not-to-exceed $6,968,559) and a $186,200 appropriation from the Water Operating Fund (601) with transfers in the Capital Outlay Fund (301) to project C2102.
  • Next: Consent item on 2026-11-17; agenda only.

Details

  • Continuation of an item the Council approved on 2026-06-01, so it did not originate in committee.
  • Built from the posted agenda; outcomes are recorded only where the agenda states them.

Sources

Log

2026-11-17 - City Council

  • Scheduled: Additional contingency, La Colonia alley reconstruction.