Anaheim Street Corridor Improvements Project

At a glance

Based on speech-to-text of the meeting video; names and details may be misheard.

  • What: a complete streets project on Anaheim Street from the Los Angeles River to PCH, with access control medians, signals, beacons, crossings, landscaping, ADA upgrades, repaving and bus stop improvements.
  • Where it stands: contract of up to $20,751,053 awarded to All American Asphalt on September 22, 2026; construction runs to spring 2028.

Details

  • The project has about $31 million in funding from 14 agencies; two segments were finished in 2023.
  • A community meeting is set for September 29 at MacArthur Park Community Center.

Sources

Log