Airport Capital Reserve Appropriations

At a glance

  • What: Two Airport Capital Reserve appropriations: $118,407 for runway repairs (Ordinance 2025-01(b)(AO)) and $50,697 as local match for an air traffic control tower roof project (Ordinance 2026-01(b)(C)).
  • Where it stands: The runway repairs were adopted July 27, 2026; the tower match was introduced the same night.
  • Next: Public hearing on the tower appropriation.

Detail

The runway money fixes seven locations on Runway 08/26 and is ineligible for grant reimbursement; the Airport Board approved it May 14 and Ms. Hall moved adoption. The tower project replaces the 1987 roof, hatch and ladder; the FAA awarded $963,247 for a total of $1,013,944, with design in 2026 and construction in 2027. The Airport Board approved July 9.

Sources

Log

2026-07-27 - Regular Assembly Meeting

Runway money adopted; tower match introduced.

2026-06-08 - Regular Assembly Meeting

Runway money introduced.

  • 2026-11-12 - 2026-11-12 - Airport Board: Recommends a competitive sale of the former Hertz wash bay building at 9221 Cessna Dr; Capital Reserve about $59,000. FAA Airport Improvement Program appropriations 2026-01(b)(K) ($250,420), (L) ($4,861,205) and (M) ($302,489) are set for public hearing on 2026-11-16 - Regular Assembly Meeting.